Refusals and Appeals

Appealing a refusal for lack of a required report

7 min readBy PlanScope Editorial Team

A refusal citing insufficient information is appealable with the missing report attached. The inspector will usually admit it and re-consult, which costs time. Resubmission is often faster, and a costs claim may be available.

If the council validated your application and then refused it because a report was missing, you can appeal and submit the report with the appeal. The question the inspector asks is whether the authority could reasonably have dealt with the gap by condition or by a request for further information, and if the answer is yes, you have a decent costs claim as well as a decent appeal. The risk runs the other way too, because new evidence that forces re-consultation can cost you time and, occasionally, costs against you.

Most self-builders in this position pick the wrong remedy. Here is how to choose.

Why authorities refuse on information grounds

Validation and determination are different gates. An authority validates against its published local list, and once the application is valid the officer has to determine it on the information available. If an officer concludes partway through that they cannot assess, say, the effect on a protected species or the capacity of the drainage system, they have three options: ask for the information and agree an extension of time, grant subject to a condition, or refuse.

Pressure on the eight week target pushes officers towards the third. A refusal stops the clock and avoids a non-determination appeal. The standard wording is some version of "insufficient information has been submitted to demonstrate that the proposal would not result in unacceptable harm to X", and the policy cited is usually the generic development management policy plus the national framework.

Read the reason carefully before deciding anything. There is a real difference between "no ecological information was submitted" and "the ecological information submitted is inadequate because it was surveyed outside the active season". The first is curable by producing the document. The second is not curable in time for a quick resubmission.

Submitting the report with the appeal

An appeal under section 78 of the Town and Country Planning Act 1990 is a re-determination on the merits, so the inspector decides on the evidence before them, which can include material the council never saw.

Timing matters. For a householder appeal the deadline is 12 weeks from the date of the decision notice, and for most other appeals it is six months. The report has to be ready when you submit, because the Planning Inspectorate's procedures expect the full case at the start and the written representations route gives you very little opportunity to add to it later.

Put the report in as an appendix to the statement of case, and in the statement itself do two things: explain what the report shows, and explain why it was not before the council. The second is the part people skip. If the answer is that the council never asked, say so, and attach the correspondence.

Whether the inspector will accept it

Usually, yes, but with conditions attached to the process rather than to the permission.

The Inspectorate's approach is that parties should not spring new evidence, because the appeal is meant to turn on the case the authority considered. Where the new material is a technical report that answers the sole reason for refusal, inspectors generally admit it, then invite the council and any statutory consultee to comment on it. That re-consultation is the cost.

Two situations where it goes badly. Where the new report changes the scheme rather than evidencing it, the inspector may treat it as a different proposal and decline to determine it. And where the report arrives after the statement of case, on the day of the site visit or at an inquiry, the inspector can refuse to admit it and may award costs against you for the delay.

A single honest uncertainty here: whether an inspector re-consults or simply reads the report is a judgement call, and it is not predictable from the appeal form. Plan on re-consultation happening.

Costs where the council could have conditioned

The costs regime turns on unreasonable behaviour causing wasted expense. The Planning Practice Guidance on appeals gives examples of unreasonable behaviour by a local planning authority, and two of them fit this scenario closely: refusing an application for a reason that could have been dealt with by a planning condition, and failing to produce evidence to substantiate a reason for refusal.

Where the officer never requested the missing report, never offered an extension of time, and the matter was plainly conditionable, a costs application is worth making. Make it in writing with the appeal, not as an afterthought, and set out the chronology: validation date, any correspondence, the date of refusal, and what was never asked for.

Where the council did ask, did offer an extension and you declined, do not apply. You will lose, and it colours the appeal.

The test for whether a condition could have done the job is the six tests in the guidance on planning conditions, and the one that bites is whether the condition would be necessary and enforceable. A condition requiring a verification report before occupation is enforceable. A condition requiring a survey that might reveal a scheme is undeliverable is not, which is why ecology refusals are harder to argue than drainage refusals.

Re-consultation during the appeal

Once the report is admitted, expect the statutory consultee to be asked for a view. For ecology that is usually the county ecologist, for drainage the lead local flood authority, for highways the local highway authority.

Build the time into your programme. Re-consultation adds several weeks to a written representations appeal and can push a decision past the point where it matters for your build programme or your finance.

One way to shorten it is to send the report to the consultee yourself before you appeal, and to include their response in the appeal bundle. A consultee who has already said the report resolves their concern removes the reason to re-consult.

Resubmission as the faster route

For a curable information gap, a fresh application is often quicker than an appeal, and quicker by months rather than weeks. The authority already knows the scheme, the officer has seen the site, and you are submitting the one document that was missing.

Weigh four things:

  1. Time. A minor application is determined in eight weeks against an appeal timescale measured in months.
  2. Fee. The position on repeat applications has changed in recent years, so check the current Fees Regulations rather than assuming a second attempt is free.
  3. The reason for refusal on the record. A refusal stays on the planning history and will be seen by the next purchaser's solicitor, whereas an allowed appeal corrects it.
  4. Whether the council's objection is really about information. If the officer dislikes the scheme and the information point is the easiest reason to write, a resubmission will come back refused for a new reason.

Point four is the one to test with a direct question to the case officer before you decide.

A Planning Statement that deals with the refusal reason explicitly, rather than restating the original case, is what makes a resubmission land. If you are weighing the two routes more generally, the note on withdraw and resubmit or appeal sets out the decision in full, and if you are going ahead with a costs claim, costs claims against a council for a vague refusal reason covers the drafting.

Avoiding the problem next time

The fix is unglamorous and it works. Ask the case officer, in writing, at around week four, whether they have everything they need to recommend approval. Keep the reply.

Agree an extension of time under article 34 of the Development Management Procedure Order 2015 the moment an officer raises a gap, rather than letting the determination date pass. An extension is a two line email and it removes the incentive to refuse.

And check the local validation list before submitting, not the national one. Most information refusals trace back to a document the local list asked for that nobody read. Browse the 66 report types to see which document answers which objection before you submit.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required, and this is general guidance rather than legal advice.

Frequently asked questions

Can I submit a missing report with my planning appeal?

Yes. An appeal under section 78 of the Town and Country Planning Act 1990 is a re-determination on the merits, so the inspector can consider evidence the council never saw. Attach it to the statement of case at the start, and explain in the statement why it was not before the authority.

Will the inspector re-consult the council on the new report?

Usually. Where new technical evidence answers the sole reason for refusal, inspectors generally admit it and then invite the authority and any statutory consultee to comment. That adds several weeks to a written representations appeal. Sending the report to the consultee before you appeal can shorten it.

Can I claim costs if the council could have used a condition?

Potentially. The Planning Practice Guidance on appeals treats refusing an application for a reason capable of being dealt with by condition as unreasonable behaviour, as it does failing to substantiate a reason for refusal. Apply in writing with the appeal and set out the full chronology of what was and was not requested.

Is resubmitting faster than appealing?

Usually by several months. A minor application is determined in eight weeks while an appeal runs far longer. Check the current Fees Regulations for the position on repeat applications, and test whether the information point is the real objection before committing, because a disguised merits objection will return as a new refusal reason.

How do I stop this happening on the next application?

Ask the case officer in writing around week four whether they have everything needed to recommend approval, and keep the reply. Agree an extension of time under article 34 of the Development Management Procedure Order 2015 as soon as a gap is raised. Check the local validation list, not just the national one.

Sources and further reading

appealsrefusalsection 78costsvalidation

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Refusals and Appeals

View all →
Refusals and Appeals7 min read

Rebutting a design refusal using national design guidance

Design refusals are usually assertions about prevailing character. Replace them with measured context analysis, structure the response around the National Design Guide, and run a costs claim where the reason was vague.

Read article →
Refusals and Appeals7 min read

Rebutting a refusal based on cumulative impact

A saturation refusal rests on a threshold, a count and an assertion of harm. The counting errors to look for, and the order to argue the appeal grounds in.

Read article →
Refusals and Appeals7 min read

Appeal timetables after the inquiry reform changes

Since the 2019 review, inquiry appeals run to an early fixed date and a managed timetable. What that moves forward, and how to staff and sequence the work.

Read article →
Refusals and Appeals6 min read

Appealing where a consultee objection was later withdrawn

A withdrawn consultee objection leaves the refusal reason without evidence. How to pin the council's position, build the costs record and choose between appeal and resubmission.

Read article →
Refusals and Appeals7 min read

Rebutting an ecology refusal where surveys were missing

An evidence refusal on ecology can usually be answered. The survey windows, the reasonable likelihood threshold and the condition wording to offer the inspector.

Read article →
Refusals and Appeals6 min read

Appeal site visits where internal access is needed

Nobody can make a neighbour let an inspector inside. When internal access really matters, how to request it, and the measured evidence that works when it is refused.

Read article →