Bat licences: who holds them and which class applies
A survey licence is personal to the ecologist. A mitigation licence is applied for in your name, usually after planning permission. Here is how the two differ and what to check before you instruct anyone.
Only a licensed ecologist can lawfully disturb bats or enter a known roost, and only Natural England can issue the licence. For a self-builder that means two separate things: the person doing your survey work holds a personal survey licence, and if the works will affect a roost, a further mitigation licence is needed before the roof comes off. The second one cannot normally be applied for until planning permission has been granted, which is why bats sit on the critical path of so many conversions.
A draft report is not a licence. PlanScope can draft the planning documents around a bat survey, but the survey itself and the licence application belong to the licensed ecologist, and the authority will check who wrote what.
The statutory basis for bat protection
All bat species in the United Kingdom are protected under the Wildlife and Countryside Act 1981 and, as European protected species, under the Conservation of Habitats and Species Regulations 2017. The offences are wide. It is an offence to deliberately capture, injure or kill a bat, to deliberately disturb bats in a way likely to affect their ability to survive, breed or rear young, and to damage or destroy a breeding site or resting place.
The last limb matters most for building work, because it is not limited to deliberate acts in the same way. A roost is protected whether or not bats are present at the time, so a loft that bats use in summer is still a resting place in February.
There is no small works exemption. A single bat in a garage counts, and the local authority has a statutory duty under the Natural Environment and Rural Communities Act 2006 to have regard to conserving biodiversity when it determines your application.
Survey licences and what they permit
A survey licence is personal to the ecologist. It allows the holder to carry out defined activities for survey purposes: entering a roost, handling bats, using an endoscope, taking droppings for analysis, and in some cases trapping or using a harp trap.
Natural England issues these at graded levels, with higher levels permitting more intrusive methods and requiring more logged field experience. A licence at the lowest level is enough for a careful inspection of a loft. It is not enough for trapping or for handling in all circumstances, so the question to ask is not whether your ecologist is licensed but whether they are licensed for the methods your building actually needs.
A preliminary roost assessment, the first visit where the ecologist looks for droppings, staining, gaps and feeding remains, can largely be done without entering a roost. Emergence and re-entry surveys from outside the building need no licence at all, because nothing is disturbed. The licence becomes necessary at the point of internal inspection and handling.
Ask for the licence number and the level, and ask what it covers. A reputable ecologist will give you both without hesitation, and a Bat Survey report should name its author and state the licence on the front page.
Mitigation licences and who applies for them
Where the works will damage or destroy a roost, or disturb bats, a European protected species mitigation licence is needed. This is a different instrument. It authorises an otherwise unlawful act, and it is granted against three statutory tests: that the work is for a permitted purpose such as overriding public interest, that there is no satisfactory alternative, and that the favourable conservation status of the population is maintained.
The applicant is normally the developer or landowner, with the ecologist named as the person who will carry out the work. So the licence sits in your name, with your consultant's competence behind it, and the obligations in it fall on you.
Natural England will generally expect planning permission to be in place first, because the no satisfactory alternative test cannot be answered while the scheme can still change. Allow time: a bespoke licence application needs a method statement, a mitigation and compensation design, survey data supporting the roost assessment, and monitoring commitments, and the determination period is measured in weeks rather than days.
Registered consultant arrangements
For schemes with limited impact, Natural England operates class licences under which a registered consultant can authorise the work themselves, logging and reporting rather than submitting a full bespoke application. The low impact route is quicker and lower in cost, and is the right answer for many house extensions and loft conversions.
It is restricted. The route is limited by species, by roost type and by the scale of impact, so a small number of common pipistrelles in a modern roof void may qualify where a maternity roost of a rarer species will not. Registration is personal to the consultant and has its own experience requirements.
Natural England publishes the current class licences, their reference numbers and their eligibility conditions, and these change. Check the current list rather than relying on a consultant's description or on an older report, and ask the consultant to confirm in writing that your scheme meets the eligibility conditions for the licence they intend to use.
Checking a licence before instructing
Five questions, asked before you appoint, save most of the trouble.
- What survey licence do you hold, at what level, and what methods does it permit?
- Are you a registered consultant under the relevant class licence, and would my scheme qualify?
- Which professional body do you belong to and at what grade? Membership of the Chartered Institute of Ecology and Environmental Management at a full or chartered grade is the usual marker.
- Who will do the fieldwork and who will sign the report? Graduate ecologists do much of the survey work, which is fine, provided a suitably experienced author takes responsibility.
- What professional indemnity cover do you carry, and does it cover licence applications?
The professional directory is one route to a reviewer for a draft report, and your authority may have its own expectations about the author of ecological evidence.
Survey season and the programme consequence
The programme consequence is the bit people learn too late.
| Stage | When it can happen |
|---|---|
| Preliminary roost assessment | Any time of year |
| Emergence and re-entry surveys | May to September, with May to August the strongest period |
| Bespoke mitigation licence application | After planning permission, weeks to determine |
| Works affecting a roost | Under the licence, in the timing it specifies |
The Bat Conservation Trust good practice guidelines set the number of survey visits by the assessed roost potential, so a building with high potential needs more visits than one with low potential, spread across the season. Start the assessment in October and the emergence surveys cannot begin until May, which delays a submission requiring them by the better part of two seasons.
Two practical consequences follow. Commission the preliminary roost assessment the moment the scheme is a serious idea, because it costs little, it can happen in winter, and it tells you whether you have a problem. And where emergence surveys are needed, submit the planning application with the assessment and a survey programme if the authority will accept it, rather than waiting.
What a licence does not cover
A licence authorises specified acts by specified people in a specified way. It does not give you planning permission, it does not override a planning condition, and it does not cover anything outside its method statement.
It also does not cover other species. Nesting birds are protected under the 1981 Act during the breeding season from March to August, great crested newts need their own consideration, and a Protected Species Survey for newts, reptiles or nesting birds is a separate exercise from the bat work even where one ecologist does both.
A licensed or competent professional is legally required for this work, and a PlanScope draft is a starting point for that professional rather than a substitute. For the wider question of who signs what, see our note on the named author and date on a planning report.
This is general guidance, not legal advice; check the position with Natural England, your local planning authority or a qualified ecologist before relying on it.
PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
Who can carry out a bat survey?
Emergence and re-entry surveys from outside a building need no licence. Entering a roost, handling bats or using an endoscope requires a personal survey licence from Natural England at the appropriate level. Ask for the licence number and the level, and check that it covers the methods your building actually needs.
Do I apply for the mitigation licence or does my ecologist?
Normally the developer or landowner is the applicant, with the ecologist named as the person who will carry out the work. The licence sits in your name and its obligations fall on you, which is why the method statement and monitoring commitments need reading before it is submitted rather than afterwards.
Can I get a licence before planning permission?
Natural England will generally expect permission to be in place first, because the statutory test that there is no satisfactory alternative cannot be answered while the scheme can still change. Allow several weeks for determination after permission, and factor that into the start on site date.
What is the low impact class licence route?
A registered consultant can authorise limited impact works themselves under a Natural England class licence, logging and reporting rather than submitting a bespoke application. Eligibility is restricted by species, roost type and scale of impact, and the current licences and conditions are published by Natural England and do change.
When do bat surveys have to happen?
A preliminary roost assessment can be done at any time of year. Emergence and re-entry surveys run from May to September, with May to August the strongest period, and the number of visits follows the assessed roost potential. Starting in October usually means waiting until the following May.