Costs, Fees and Budgeting

Budgeting a public exhibition for a major scheme

7 min readBy PlanScope Editorial Team

An exhibition that produces a photograph of a full room and no analysis has spent money without buying anything. The budget should follow what the statement has to prove.

A public exhibition for a major scheme is an evidence-gathering exercise with a budget attached, and the budget should be set by what the submission has to prove rather than by what the venue costs. The document it produces is a Statement of Community Involvement, and its value at committee depends entirely on whether it can show who was reached, what they said, and what changed as a result. An exhibition that produces a photograph of a well-attended room and no analysis has spent money without buying anything.

There is no general statutory duty on an applicant in England to consult the community before submitting. What there is, on most major schemes, is a local expectation: the authority's own statement of community involvement, its validation list for majors, and the practical reality that a scheme arriving at committee with no record of engagement attracts a different reception from one that arrives with one.

What the consultation has to achieve

Work backwards from the submission. Four things need to be demonstrable.

Reach. Who was notified, by what method, and how many people that represents against the population of the area consulted. A leaflet drop to 1,200 addresses is a number. "The local community was informed" is not.

Opportunity to respond. The channels available, the period they were open for, and whether someone without internet access or with limited mobility could take part.

What was said. The responses, categorised by theme, with the volume behind each theme stated rather than characterised.

What changed. The specific design or operational changes made in response, and the matters raised where no change was made with the reason given. This is the part that carries weight and the part most often missing.

Everything in the budget should serve one of those four. If a line item does not, it is marketing rather than consultation, and it should be justified on that basis instead.

Venue, materials and staffing

The cost drivers, rather than the costs, which vary too much by location and scale to generalise:

  • venue hire, driven by the day of the week, the duration, the capacity and whether the space needs to be accessible and available in the evening
  • notification, which is usually the largest single line on a major scheme, driven by the number of addresses and whether the drop is by distributor or by post
  • display material, driven by the number of boards, the quality of the visualisations and whether verified views or a physical model are produced
  • staffing, driven by the number of sessions and how many of the design team attend each
  • response capture, meaning printed forms, a tablet or two, and someone to transcribe
  • accessibility provision, including an induction loop, translation where the area needs it, and a large-print version of the boards

Two judgement calls set the total more than any other decision. The number of addresses notified, because notification scales linearly and everything else does not. And whether the scheme produces visualisations for the exhibition or reuses material already prepared for the application, because high-quality verified views are a substantial line in their own right and are often already being produced for a townscape assessment.

Where visual material is being prepared anyway for the application, co-ordinate the two so the exhibition uses the same views. Producing two sets at different stages is a common and avoidable duplication.

Digital consultation and its own costs

A project website with a feedback form is now standard, and it is not free.

The cost sits in four places: building and hosting the site, producing material in a format that works on a phone, moderating and responding to submissions, and the data handling arrangements, because a consultation collecting names, addresses and comments is processing personal data and needs that handled properly.

Digital reach has a specific weakness that committee members know about. Online responses skew towards people who are already engaged and towards certain age groups, so a consultation that reports 400 online responses and 30 attendees at the exhibition is open to the criticism that it did not reach the people most affected. The answer is to run both and to report the demographic reach of each honestly rather than to merge the totals.

Where the authority holds a consultation portal or publishes the scheme on its own site at pre-application stage, use it, because a response submitted through the authority's channel is harder to characterise as developer-managed.

Recording and analysing responses

This is where consultation budgets are usually too small, and it is the part that determines the value of everything else.

The work involved: transcribing paper forms, de-duplicating responses, coding each response against a theme list, counting the volume per theme, identifying the geographic distribution of respondents, and separating comments on matters the application can address from those it cannot.

Build the theme list before the exhibition rather than after, from the issues the policy context and the site constraints suggest will arise. Then add themes that emerge. Coding to a list designed after the event invites the accusation that the categories were chosen to produce a comfortable result.

Keep the raw responses. Where an objector later says the consultation misrepresented local opinion, the raw material is the answer, and authorities occasionally ask for it.

One sensible budget line that is frequently omitted: someone independent of the design team to do the coding. The designers are the worst people to categorise criticism of their own scheme, and a third party costs little and removes the argument.

Reporting the outcome in the submission

The Statement of Community Involvement submitted with the application should be short, factual and structured so that an officer can extract what they need in five minutes.

The structure that works: a chronology of the engagement with dates, the notification method with numbers, the channels and the period open, a table of themes with response volumes, a section setting out each design change with a before-and-after reference to the drawings, a section listing matters raised where no change was made with the reason, and the raw material in appendices.

Avoid two things. Do not report support and objection as a headline score, because a consultation is not a referendum and presenting it as one invites a counting argument. And do not quote individual respondents by name or in a way that identifies them.

Where the authority's validation list requires the statement for major applications, check whether it specifies content, because some do and matching their list saves a round of comments. The report index sets out the other documents a major submission needs.

Where a second round is needed

A second round of consultation is worth its cost in three situations and not otherwise.

Where the design has changed materially in response to the first round, so that showing the revised scheme demonstrates the response was real. This is the strongest case and the one officers value most.

Where a specific group was under-represented in the first round, for example a particular street, a school community or a group of businesses, and a targeted second session reaches them.

Where the scheme has been through a design review panel or a significant policy change between rounds and the proposal the community saw is no longer the proposal being submitted.

A second round purely to improve the numbers is not a good use of the budget. Officers can tell the difference, and the volume of responses is not what carries weight.

Scaling the spend to the scheme

The proportionate answer varies by scale, and the structure to build is a tiered one.

Scheme scale Engagement that is normally proportionate
Minor major, around 10 to 49 units Leaflet to the immediate area, a project web page with a feedback form, a single drop-in session, a short statement
50 to 149 units Wider leaflet drop, web page, two sessions at different times, a meeting with the parish or ward councillors, coded analysis
150 units or more, or a referable scheme Full exhibition programme, targeted sessions with identified groups, digital consultation, independent coding, a second round after design change
Contentious or sensitive site at any scale Treat as one tier above its size

Set the budget as a range with the notification number stated as the main variable, add a separate line for analysis and reporting, and hold a contingency for a second round that you only spend if the design changes.

For how the supporting document costs compare with the rest of the application budget, see pricing, and comparable cost mechanics are covered in full application fees by floorspace and site area and outline and reserved matters fees on a phased scheme.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Is pre-application community consultation compulsory?

There is no general statutory duty on applicants in England to consult before submitting. What exists on most major schemes is a local expectation: the authority's own statement of community involvement, its validation list for major applications, and the practical reality that a scheme arriving at committee with no record of engagement is received differently.

Which cost drives the consultation budget most?

Notification, because the number of addresses scales linearly while venue, staffing and materials do not. The second largest decision is whether visual material is produced for the exhibition or reused from material already being prepared for the application, since verified views are a substantial line on their own.

How should online and in-person responses be reported?

Separately, with the reach of each stated. Online responses skew towards people already engaged and towards certain age groups, so merging the totals invites the criticism that the consultation missed those most affected. Reporting both honestly, with geographic distribution of respondents, is more persuasive than a single large number.

Who should code the consultation responses?

Someone independent of the design team. Designers are poorly placed to categorise criticism of their own scheme, and independent coding costs little while removing the argument. Build the theme list before the exhibition from the known policy and site issues, then add themes that emerge, and keep the raw responses.

When is a second round of consultation worthwhile?

Where the design has changed materially in response to the first round, where a specific group was under-represented and can be reached by a targeted session, or where a design review or policy change means the scheme the community saw is not the one being submitted. A second round purely to raise response numbers is not.

Sources and further reading

consultationcommunity involvementcostsmajor applicationsbudgetingengagement

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting7 min read

Licences to occupy the highway during construction

Highway occupation charges accrue whether or not work is happening, and they sit outside the planning fee and the building control charge. On an urban site they run for the whole programme.

Read article →
Costs, Fees and Budgeting7 min read

Commuted sums for open space maintenance explained

Councils price open space maintenance as area by annual rate by commutation period, then ask for it as a lump sum in the section 106 agreement. Here is how the figure is built and how the drafting changes what you pay.

Read article →
Costs, Fees and Budgeting8 min read

Certificate C and D: notice and advertising costs

Certificates C and D are the only ownership certificates that require advertising, and the newspaper notice decides your submission date rather than the other way round.

Read article →
Costs, Fees and Budgeting9 min read

Nutrient credits and what drives their price

A nutrient credit buys a legally secured, monitored reduction held for the lifetime of your development in the same catchment. Price follows from land value, duration and the budget calculation.

Read article →
Costs, Fees and Budgeting8 min read

Hazardous waste consignment costs on a demolition

On a demolition budget the line that moves most is the classification of the material, not the tonnage. Here is how consignment notes, tax bands and on-site reuse change the total.

Read article →
Costs, Fees and Budgeting6 min read

Resubmit or appeal after refusal: comparing real costs

The free second application and the appeal both cost nothing to lodge. Where the money really goes, and how to read a refusal reason to pick the right route.

Read article →