Most appraisals carry the drafting fee for a travel plan and none of the rest. Baseline and monitoring surveys, the coordinator role and the monitoring contribution secured by obligation all have to be priced too.

A travel plan has four cost lines, and most appraisals carry only the first. There is the consultant fee for writing it. There are the travel surveys, at baseline and at each monitoring round. There is the coordinator, who is a real person with real hours for five years or more. And there is the authority's monitoring contribution, secured by planning obligation and payable whether or not your targets are met.

Budget all four at the same time as the transport evidence, because the monitoring obligation is negotiated in the section 106 agreement and by then the appraisal is usually fixed.

Framework and full travel plans

The distinction matters because it decides how much you are paying for now and how much later.

A framework travel plan sets the structure: the objectives, the mode share targets, the measures that will be available, the monitoring regime and the mechanism by which individual occupiers produce their own plans. It suits outline permissions, phased schemes and anything with multiple end users who are not yet known. It is shorter and less expensive to produce, and it defers the detail.

A full travel plan commits to specific measures for a known occupier or a known residential scheme, with named targets, a delivery programme, a coordinator and a monitoring schedule. It costs more to write and it is what the highway authority will want for a single-occupier scheme or a residential development with a defined mix.

Planning Practice Guidance on travel plans, transport assessments and statements sets out what each should contain and expects the scope to be proportionate to the scale of the development and the transport issues it raises. The practical reading of proportionate is that a 60-unit residential scheme needs a shorter document than a distribution warehouse with 400 staff on three shifts, and the authority's own guidance will usually say which it expects.

Where the scheme is large enough to need a Transport Assessment rather than a transport statement, assume a travel plan is coming with it. Councils usually expect a suitably qualified author for transport work, and professional review before submission is strongly advised.

Baseline surveys and when they can be done

On a new development there is no existing travel behaviour to survey, which creates a sequencing problem people only notice once the obligation is drafted.

The usual solution is to set the baseline after occupation, at a stated occupancy trigger, often expressed as a percentage of units occupied or a date after first occupation. The baseline survey then becomes the first monitoring round. Where a comparison is needed earlier, the plan draws on census travel-to-work data, the authority's own survey data or comparable sites, and says plainly that it is doing so.

Survey timing has rules that are worth insisting on in the drafting. Surveys should be carried out in neutral months, avoiding school holidays, late December and August, and should cover the days of the week that matter for the use. A survey window drafted as "within three months of occupation" can land in the school holidays and produce a baseline that makes your later targets harder to meet.

So negotiate the survey window as well as the survey frequency. A clause that requires surveys in a neutral month is a small amendment with a measurable benefit.

Targets, measures and the coordinator

Targets are usually expressed as a mode share shift: a reduction in single-occupancy car trips, or an increase in walking, cycling and public transport use, measured against the baseline over a stated period.

Set them from the measures you are actually delivering. A target that assumes a bus service improvement you are not funding is a target you will miss, and missing it triggers whatever remedial mechanism the agreement contains.

Measures that tend to be deliverable and defensible: a travel information pack for each occupier, cycle parking above the policy minimum with proper covered and secure provision, a car club bay with trial membership, discounted public transport passes for a defined period, personalised travel planning, a car park management regime, and good internal pedestrian and cycle routes. Measures that disappoint: notice boards, intranet pages and vague commitments to promote sustainable travel.

The coordinator is a cost line in its own right. The plan names a role, with contact details, responsibilities and a budget, and that person has to be in post from first occupation. On a residential scheme the role usually sits with the management company, which means the service charge carries it and the buyers need to be told. On a commercial scheme it sits with the occupier, which means it belongs in the lease.

Monitoring surveys after occupation

Monitoring rounds are typically set at intervals across a five year period following occupation, often in years one, three and five, with the plan reviewed after each round.

Each round costs money: the survey itself, the analysis, the report to the authority and the management time. Multiply the per-round cost by the number of rounds and put the total in the cash flow at the right years, because these fall after sales income on a residential scheme and after the appraisal has closed.

The iterative approach most authorities now use means a missed target does not automatically trigger a payment. It triggers a revision: the plan is updated with additional measures, agreed with the authority, and tested at the next round. That is a better outcome than a penalty, and it is worth drafting for.

One practical point on survey response rates. A residential travel survey with a poor response rate tells you very little and the authority can treat it as non-compliance with the obligation. Budget for incentivised response, and set the obligation against a reasonable response threshold rather than an absolute one.

The monitoring contribution secured by obligation

Local planning authorities can charge a monitoring fee for planning obligations, and the travel plan is one of the obligations most often monitored. The fee has to satisfy the statutory tests for obligations: necessary to make the development acceptable, directly related to the development, and fairly and reasonably related in scale and kind, under regulation 122 of the Community Infrastructure Levy Regulations 2010 as amended.

That last limb is the negotiating ground. A monitoring fee should reflect the officer time reasonably required to monitor the obligation, and an authority asking for a figure out of proportion to the work is vulnerable on the scale and kind test. Ask how the figure was calculated. Many authorities publish a monitoring fee schedule, and a published, reasoned figure is harder to argue with than an unexplained one, which cuts both ways.

Three drafting points worth money:

  • Cap the total monitoring sum across all obligations rather than accepting a per-obligation charge with no ceiling.
  • Agree indexation explicitly, and to a named index with a base date, rather than leaving it open.
  • Tie payment to a trigger you control, such as implementation or first occupation, rather than to the date of the agreement.

The monitoring fee sits in the same part of the appraisal as the other obligations, and the interaction with viability is covered in budgeting a viability appraisal and the review it triggers.

Remedial mechanisms and what the tests allow

Some agreements go further than monitoring and require a remedial payment or a bond where targets are missed.

Approach these carefully. An obligation that operates as a penalty, rather than as a measure to make the development acceptable, is exposed on the regulation 122 tests. The more defensible structure is a remedial fund drawn down to pay for additional travel plan measures agreed with the authority, with any unspent balance returned. That is directly related to the development and it gives the authority what it actually wants, which is the behaviour change rather than the money.

Where a bond is proposed, check three things: what event triggers a call, who decides whether the trigger has occurred, and what the release mechanism is. A bond with no clear release date is a cost on the balance sheet for as long as it runs.

And read the definition of the target. A target expressed as an absolute mode share is harder to meet than one expressed as a shift from the measured baseline, and the difference between those two drafting choices can be the difference between a clean release and a remedial draw.

Negotiating the period and the cap

Five years of monitoring after full occupation is the common position for a residential scheme. Ten appears occasionally and is worth resisting on anything other than a large phased development, because the officer time it reflects is unlikely to be spent and the obligation has to be proportionate.

Four asks that authorities frequently accept:

  1. A five year monitoring period from full occupation rather than from first occupation on a phased scheme.
  2. A capped total monitoring sum with a stated index.
  3. Survey windows restricted to neutral months, with a defined response threshold.
  4. An iterative review mechanism in place of an automatic remedial payment.

Put the full cost of the Travel Plan in the appraisal as five separate lines: drafting, baseline survey, monitoring rounds, coordinator, and the authority's monitoring contribution. Most appraisals show one. The obligation is also the item least likely to appear in a consultant's quotation, and what is and is not included is covered in what a planning agent's fixed fee usually includes.

If you are costing the planning documents alongside the transport work, PlanScope pricing sets out the free report, the £50 per report option and the Professional tier at £150 per month or £600 per year. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

This is general guidance, not legal advice. Monitoring fees and obligation drafting vary by authority, so check the current position and take advice from a qualified professional before relying on it.

Frequently asked questions

What is the difference between a framework and a full travel plan?

A framework travel plan sets objectives, targets, available measures and the monitoring regime, leaving individual occupiers to produce their own plans. It suits outline and phased schemes. A full travel plan commits to specific measures, targets, a coordinator and a monitoring schedule for a known occupier or a defined residential scheme.

When is the baseline travel survey carried out?

Usually after occupation, at a stated occupancy trigger, because a new development has no existing travel behaviour to measure. The first monitoring round then doubles as the baseline. Where an earlier comparison is needed, the plan draws on census travel-to-work data or comparable sites and says so explicitly.

Can a council charge a travel plan monitoring fee?

Yes. Authorities can charge a monitoring fee for planning obligations, subject to the tests in regulation 122 of the Community Infrastructure Levy Regulations 2010: necessary, directly related and fairly and reasonably related in scale and kind. Ask how the figure was calculated, and negotiate a cap across all obligations rather than per obligation.

What happens if the travel plan targets are missed?

Under the iterative approach most authorities use, the plan is revised with additional measures agreed with the authority and retested at the next round. Some agreements instead require a remedial payment or call on a bond. A remedial fund spent on agreed measures, with any balance returned, is the more defensible structure.

How long should the monitoring period be?

Five years from full occupation is the common position for a residential scheme. Ten years is worth resisting on anything other than a large phased development, because the obligation has to be proportionate to the officer time reasonably required. Negotiate the start point as full occupation rather than first occupation.

Sources and further reading

travel plansection 106monitoring feestransportbudgetingdevelopers

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting7 min read

The cost of an enforcement notice appeal

Appealing an enforcement notice costs nothing at the Inspectorate. The real spend is the deemed application fee on ground (a), the evidence needed to prove immunity, and the works you will fund if the notice is upheld.

Read article →
Costs, Fees and Budgeting7 min read

The levy exemption for residential extensions

Two reliefs apply to extensions: the minor development rule below 100 square metres, and the residential extension exemption with no size limit. Both depend on the paperwork sequence.

Read article →
Costs, Fees and Budgeting7 min read

What the national planning application fee bands cover

Fees are prescribed nationally, indexed annually and not negotiable. Which band applies depends on dwellings, floorspace or site area, and several concessions are routinely missed.

Read article →
Costs, Fees and Budgeting7 min read

What a planning agent charges for an appeal, by stage

An appeal fee hides four pieces of work, and the prospects review is worth more than the other three. Here is the stage structure, and the breakdown to ask every agent for.

Read article →
Costs, Fees and Budgeting7 min read

Budgeting a hazardous substances consent application

The fee for hazardous substances consent is a flat prescribed sum. The real cost is the substance inventory and containment schedule behind it, plus the consultation distances the consent creates.

Read article →
Costs, Fees and Budgeting7 min read

CIL surcharges, interest and late payment

Start work without a commencement notice and the surcharge is 20 per cent or £2,500. Here is the full schedule, how interest runs and how to appeal.

Read article →