A cold store is a quiet building with noisy equipment bolted to it. The planning issue is almost never the box: it is the condenser bank running at three in the morning, 20m from a bedroom window, with a fan tone you can hear over the traffic. Cold store plant noise is assessed against the measured night-time background, and that background is lower than most applicants assume.

So the order of work is the opposite of the instinctive one. Measure first, select the plant second, and draw the application third.

When a cold store needs permission

Two separate questions: the structure and the plant.

An extension to an existing food unit may fall within the rights in Part 7 of Schedule 2 to the General Permitted Development Order 2015 for extensions and alterations to industrial buildings and warehouses, subject to limits on floorspace, height, distance from boundaries and the retention of parking and turning space. Part 7 also contains rights for the installation, alteration or replacement of plant and machinery on industrial land, again with height and boundary limits. None of those rights apply on article 2(3) land such as a conservation area, and they are amended from time to time, so read the current Order rather than a summary.

Where the unit is in Class E rather than an industrial class, the position is different and an application is more likely to be needed. And where the cold store is an internal insulated room within an existing building, the structure may not be development at all while the external condensers still are.

The honest answer on most sites is that the chiller plant needs permission even when the building does not.

Condenser siting and the sound it makes

Refrigeration plant produces a broadband fan noise with a tonal component at the blade pass frequency, plus compressor noise that is often tonal too. Tonality is what makes it noticeable at low levels, and the assessment method penalises it.

BS 4142:2014+A1:2019 builds a rating level from the specific sound level of the plant plus corrections for acoustic character. Tonality attracts up to +6 dB depending on how perceptible it is, impulsivity up to +9 dB, and intermittency +3 dB where the operation is readily distinctive against the residual sound. A condenser that measures comfortably below background on a sound level meter can still produce a rating level well above it once the tone correction is applied.

Siting does more than any other single measure. Three principles:

  • Put distance and building mass between the plant and the nearest receptor, because screening by the building itself is free and permanent.
  • Avoid courtyards and reveals, where reflections raise the level at facades and reverberation adds to it.
  • Think in three dimensions. Roof-mounted plant with a solid parapet can be better than ground level plant on a boundary, provided the structure-borne path is dealt with.

Night-time operation and the background level

A cold store runs continuously because the product requires it, so the governing period is night rather than day.

Under BS 4142 the reference time interval at night is 15 minutes, against a background sound level measured as the LA90 over that period. On a quiet industrial estate at 02:00 that figure can be very low, and the margin available to you is correspondingly small. Measure it rather than estimating it, over several nights, at a position representative of the nearest residential facade and at the relevant floor level.

Two measurement points matter more than the rest: the nearest habitable room window, and the garden or amenity space where it exists. Where the receptor is a first floor bedroom, a ground level measurement understates what matters.

The assessment also has to consider context. An existing plant yard already running at night changes what the new condenser adds, so include a cumulative calculation rather than treating the new unit in isolation.

Screening, enclosure and the options that work

Mitigation is a hierarchy, and the low cost end of it is the least effective.

Measure Typical benefit Practical cost
Relocation away from the receptor Often the largest single gain Pipe runs, efficiency loss
Low-noise fan selection with variable speed control Several decibels, and removes the tone at part load Capital cost, usually modest
Night setback on fan speed Useful where load allows Reduced capacity on warm nights
Acoustic enclosure with lined plenum and attenuators Substantial, if airflow is maintained Design cost, maintenance access
Imperforate acoustic barrier close to the plant Moderate, better near the source than the receptor Space, airflow restriction
Anti-vibration mounts and flexible connections Removes structure-borne transmission Minimal

A barrier works only where it breaks the line of sight and has no gaps, including at the base. A barrier that restricts airflow makes the plant work harder and often louder, which is the failure mode specifiers miss.

Variable speed fans deserve particular attention. They reduce level at part load and they also move the tone, which can take a +6 dB correction down to +2 dB. That single change sometimes resolves an application on its own.

Defrost cycles and the character question

Defrost is the detail that causes complaints after permission has been granted.

During a defrost cycle the fans may stop and restart, the compressors change duty, and hot gas valves operate. The result is a change in level and character several times a night, which is exactly the intermittency the standard penalises. An assessment that models steady state operation only has not described what the neighbours will hear.

Say in the submission how many defrost cycles occur in a 24 hour period, when they are scheduled, and what the level and character are during them. Scheduling defrost outside the quietest hours is a straightforward operational commitment and it reads well as an offer.

Illustrative example: a chilled distribution unit adds a six-fan condenser on a flank wall 22m from houses. Night background is measured at a low level over three nights. The initial selection gives a rating level above background once a clearly perceptible tone is corrected for. Switching to variable speed EC fans, adding a lined acoustic screen and scheduling defrost before 23:00 brings the rating level to around the background figure, which is the position the environmental health officer asked for.

The information the assessment needs

A Noise Impact Assessment for refrigeration plant should contain all of the following, and applications are routinely held up because one is missing.

  1. Manufacturer sound power data in octave bands for the selected plant, not an overall A-weighted figure.
  2. A plant layout drawing with heights, orientations and any screening shown.
  3. Receptor locations with floor levels, and a note of which rooms face the plant.
  4. The background survey: dates, positions, weather, instrumentation and the measured LA90 figures by period.
  5. The calculation method and the propagation assumptions used.
  6. Rating level at each receptor, with every character correction itemised and justified.
  7. Cumulative assessment with existing plant on the site and neighbouring sites.
  8. The mitigation scheme, with the performance assumed for each element.

Noise assessment of this kind is work councils expect from a suitably qualified author, and professional review before submission is strongly advised. Note also that planning permission is no defence to a statutory nuisance action under the Environmental Protection Act 1990, so the commissioned performance matters as much as the consent.

Where the unit also cooks or processes food, the extract system is a separate question and a Ventilation and Extraction Statement covers it. The related note on a micro bakery in a retail unit deals with the combination of plant and extract in a small unit.

Enter your postcode on PlanScope to see which of the 66 report types a cold store proposal is likely to need.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. For specialist technical reports, qualified professional input may be required. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Does a cold store extension need planning permission?

It depends on the existing use class and the works. Part 7 of Schedule 2 to the GPDO 2015 contains rights for extensions to industrial buildings and warehouses and for plant on industrial land, subject to floorspace, height and boundary limits, and none apply on article 2(3) land. On most sites the external condensers need permission even where the building does not.

Why is tonality so important?

Because BS 4142:2014+A1:2019 adds a correction of up to +6 dB where a tone is perceptible, and refrigeration fans and compressors are tonal by nature. Plant that measures below the background level on a meter can still produce a rating level above it once the correction is applied, which is what the assessment reports.

When should the background survey be carried out?

At night, because a cold store runs continuously and the night period governs. The reference time interval at night is 15 minutes, and the background is the LA90 over that period. Measure over several nights at a position representative of the nearest residential facade and at the relevant floor level.

Which mitigation gives the biggest improvement?

Relocating the plant away from the receptor, using the building itself as screening. After that, low-noise variable speed fans help twice over: they reduce the level at part load and they move the tone, which can cut a +6 dB correction to +2 dB. Barriers only work if imperforate with no gap at the base.

Do I need to mention defrost cycles?

Yes. Fans stopping and restarting, compressors changing duty and hot gas valves operating all change the level and character several times a night, which is the intermittency the standard penalises. State how many cycles occur in 24 hours, when they run, and offer to schedule them outside the quietest hours.

Does planning permission protect me from complaints?

No. A permission is no defence to a statutory nuisance action under the Environmental Protection Act 1990, and councils retain those powers regardless of the consent. That is why the installed and commissioned performance of the plant matters as much as the wording of the planning condition.

Sources and further reading

cold storerefrigerationnoisebs 4142plant noisecommercial planning

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Commercial Occupiers

View all →
Commercial Occupiers6 min read

A pet crematorium and the environmental permit

Animal cremation sits outside the use classes, needs an environmental permit as well as planning permission, and is normally decided on stack height, odour and the visitor element.

Read article →
Commercial Occupiers6 min read

A seasonal food kiosk on private land: the planning rules

Part 4 of the GPDO allows temporary use of land for 28 days a year, including a moveable kiosk. The curtilage exclusion, the day count across the planning unit and any hardstanding or services decide whether you need to apply.

Read article →
Commercial Occupiers6 min read

Reopening a nightclub after years of closure

A sui generis nightclub use does not lapse through non-use alone, but it can be abandoned. Physical condition, length of closure, intervening use and the owner's intentions decide it, and a certificate of lawfulness settles it.

Read article →
Commercial Occupiers6 min read

Betting shops, sui generis use and the change of use case

Betting offices left Class A2 in 2015 and never joined Class E, so a full application is always needed. Frontage clustering policy, shopfront design and the gambling premises licence decide the outcome.

Read article →
Commercial Occupiers7 min read

A sandwich shop moving into hot food and extraction

Adding hot food may or may not be a change of use. The Class E boundary, the extraction design that councils accept, and the evidence a lawfulness certificate needs.

Read article →
Commercial Occupiers6 min read

An MOT bay added to an existing repair garage

An MOT bay in an existing garage keeps the same use class. The planning questions are the building works, the waiting vehicles and the noise of the test equipment.

Read article →