Evidence where a scheme needs a stopping up order
The public right of passage survives a grant of permission. Here is the evidence a stopping up order needs, how the routes differ and how long to allow.
Planning permission does not give you the right to build over a highway. The public right of passage survives the grant of permission, obstructing it remains an offence, and the only way to remove it is a stopping up or diversion order under a separate statutory process with its own timetable, usually under section 247 of the Town and Country Planning Act 1990 for vehicular highways and section 257 for footpaths and bridleways.
Developers discover this at two points. The good one is at site appraisal. The bad one is when the contractor is on site and the council's highway searches team notices a strip of adopted footway running through the proposed building.
Establishing what is actually highway
Before anything else, establish the extent and status of the highway with documentary evidence rather than from the site plan.
Four sources answer the question:
- The list of streets maintainable at public expense, held by the highway authority, which records adopted carriageway and footway.
- The definitive map and statement, held by the surveying authority, which records public rights of way including footpaths, bridleways, restricted byways and byways open to all traffic.
- Title and Land Registry plans, remembering that the presumption of ownership to the centre line of a highway can coexist with public rights over the surface.
- Historic records and dedication evidence, where a route has been used by the public without formal adoption.
Two traps recur. A route can be a public right of way without being maintainable at public expense, so it may be absent from the street list while still carrying public rights. And a route can have been used by the public for years and be subject to a claim for dedication, which has to be resolved before you can safely treat it as private.
Get the answers in writing from both the highway authority and the surveying authority, and keep the replies on file. The cost is a search fee. The cost of being wrong is a demolition.
Why permission alone does not let you build over it
The highway is a public right, not a planning constraint. A grant of planning permission is permission to develop as against the planning system. It does not extinguish third party rights, and it does not extinguish public rights of passage.
That has three practical consequences. A permission can be perfectly lawful and entirely unimplementable on the part of the site crossed by a highway. An enforcement route exists outside planning, through highway obstruction, which can be pursued by the highway authority or by any member of the public. And the planning authority is not the body that can solve it, because in most cases the decision on a vehicular stopping up order rests with the Secretary of State.
This is the same structural point as other third party interests over a site, such as the position where overhead power lines cross a site. The planning permission and the third party right are decided in different places.
Choosing the right order
The route depends on what is being stopped up and why.
| Route | Used for | Decision maker |
|---|---|---|
| Section 247 TCPA 1990 | Stopping up or diverting a highway, including carriageways, to enable development authorised by planning permission | Secretary of State |
| Section 257 TCPA 1990 | Stopping up or diverting footpaths, bridleways and restricted byways where necessary to enable development | Local planning authority, confirmed by it if unopposed |
| Section 116 Highways Act 1980 | Stopping up where the highway is unnecessary, outside the development context | Magistrates' court on the highway authority's application |
| Sections 118 and 119 Highways Act 1980 | Extinguishment or diversion of public paths on grounds other than enabling development | Order making authority, confirmed by the Secretary of State if opposed |
For development schemes, section 247 and section 257 do most of the work. The distinction between them matters for programme as much as for law, because a section 257 order is made and, if unopposed, confirmed by the local planning authority, which is usually quicker than the Secretary of State route.
Where a scheme affects both a carriageway and a footpath, you may need both.
The application and the evidence it needs
For a section 247 order, the application goes to the Secretary of State and needs:
- The planning permission, or evidence that an application is being determined, since the order enables development authorised by permission.
- A plan to the required standard showing the existing highway, the extent proposed to be stopped up, and any replacement highway, with a clear and consistent colour convention.
- A description of the development and why the stopping up is necessary to carry it out.
- Evidence of consultation with the highway authority, statutory undertakers with apparatus in the highway, emergency services, and user groups where public paths are affected.
- Details of any alternative provision, with its specification and the arrangements for its construction, dedication and maintenance.
Keep the drawn extent tight. An order drawn wider than the development needs invites objections from people whose access is affected and who would otherwise have no interest in the application. Keep the planning statement and the order documents consistent on what the development is, because an inconsistency between them is the first thing an objector's agent will find.
Alternative provision and objection handling
The strongest applications offer a better route than the one being removed.
Where the stopping up affects pedestrian movement, alternative provision should be at least equivalent in directness, width, surfacing, lighting, gradient and safety, and it should be available before or at the point the existing route closes. Where there is a gap in time, say how the route will be managed, because a temporary closure is itself a separate procedure.
Objections come from predictable quarters: residents whose walking route changes, user groups where a public path is involved, businesses whose frontage access is affected, and statutory undertakers with apparatus. Most are resolvable by negotiation before the order is published, which is the single most effective thing you can do for the programme.
Where objections are maintained, the Secretary of State may hold a hearing or a public inquiry, and the timetable extends accordingly. Maintained objections are rarely fatal. They are expensive, though, and an order that goes to inquiry on a small scheme can cost more than the development value of the land being gained.
Programming the order against start on site
An illustrative example. A town centre scheme where a 40 m length of adopted footway crosses the footprint of the proposed building, with a replacement footway proposed around the new frontage. Planning permission is granted in March. The section 247 application is submitted in April with a draft order plan, consultation responses from the highway authority and three undertakers, and a replacement footway specification. The order is published in the summer, two objections are received from local residents, both are withdrawn after a route amendment, and the order is made and comes into force in the following spring. Roughly 12 months from permission, and the building could not start on that part of the site until it took effect.
That is a normal timetable for an unopposed or quickly resolved order. Build it into the programme explicitly:
- Start the stopping up work in parallel with the planning application, not after the decision.
- Assume months rather than weeks, and considerably longer if an inquiry is likely.
- Phase the construction so that work away from the affected land can proceed.
- Do not rely on an order being made. Until it comes into force, the highway remains a highway.
Apparatus, section 278 works and the handover
Stopping up a highway does not automatically deal with the services under it. Statutory undertakers have their own rights, and their apparatus either stays where it is with protection and access rights, or it is diverted at your cost under a separate agreement with its own lead time. Resolve that in parallel, because an order that extinguishes the public right while leaving a live main under your foundations has solved half the problem.
Where the scheme also creates or improves highway, a works agreement under section 278 of the Highways Act 1980 will be needed, and new estate roads intended for adoption run through section 38. The order, the works agreement and the adoption agreement are three different documents with three different timetables, and the sequencing between them is a programme risk worth mapping at the outset.
Set out the access arrangement and the replacement route in the transport assessment so the planning case and the highways case tell the same story from the start.
Browse the 66 PlanScope report types to assemble the supporting evidence, and get the highway status searches done before you commit to a layout.
This is general guidance, not legal advice; stopping up and public path orders turn on statutory procedure and short consultation periods, so take advice from a solicitor or a suitably qualified highways consultant before relying on anything here. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
Does planning permission allow me to build over a highway?
No. Permission operates against the planning system only. The public right of passage survives it, obstruction remains an offence enforceable outside the planning system, and the right can only be removed by a stopping up or diversion order under a separate statutory process with its own timetable and decision maker.
What is the difference between section 247 and section 257?
Section 247 of the Town and Country Planning Act 1990 covers stopping up or diverting highways, including carriageways, to enable development authorised by permission, and is decided by the Secretary of State. Section 257 covers footpaths, bridleways and restricted byways and is made by the local planning authority, which can confirm it if unopposed.
How do I confirm whether a route is adopted highway?
Check the list of streets maintainable at public expense held by the highway authority, the definitive map and statement held by the surveying authority, and title plans. A route can carry public rights without being maintainable at public expense, so absence from the street list does not mean the route is private.
How long does a stopping up order take?
Allow months rather than weeks, and around a year from permission is common for an unopposed or quickly resolved section 247 order. Objections that are maintained can lead to a hearing or public inquiry and extend the timetable considerably. Start the work in parallel with the planning application rather than after the decision.
Does the order deal with services in the highway?
No. Statutory undertakers retain their own rights, so apparatus either stays with protection and access rights or is diverted under a separate agreement at your cost, with its own lead time. Resolve that in parallel, or you can end up with the public right removed and a live main under the foundations.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.