Keeping a structure after a temporary permission expires
Once a temporary permission expires the structure is unauthorised and the removal condition is in breach. The section 73, fresh application, retrospective and immunity routes compared.
When a temporary planning permission expires, the structure becomes unauthorised on the day after the period ends, and the condition requiring its removal becomes a breach from that date. There are four routes to keeping it: a section 73 application to remove the time condition while the permission is still live, a fresh full application for permanent retention, a retrospective application under section 73A once the period has passed, or a certificate of lawfulness if the breach has run long enough to be immune. Doing nothing is the fifth option and the only one with no upside.
Deal with it at least six months before expiry. After expiry your position is weaker in every respect, including the one that matters most to a lender.
What happens when the temporary period ends
A temporary permission is granted using the power to impose conditions requiring the removal of buildings or works and the reinstatement of land at the end of a specified period. The condition does the work, not the permission. So once the date passes, the use is unauthorised and the building is in breach.
National guidance is blunt about the reasoning. A temporary permission is appropriate where there is a reasonable expectation that the activity will cease, and the fact that an applicant has become accustomed to the use is not a material consideration in favour of making it permanent. Expect that sentence to appear in the officer's report.
Two enforcement tools are available. A breach of condition notice requires compliance with the condition and carries no right of appeal to the Planning Inspectorate, with challenge limited to judicial review. An enforcement notice carries full appeal rights but takes longer to serve and to take effect. Authorities reach for the breach of condition notice precisely because it is harder to resist.
Applying for permanent permission
If the permission has not yet expired, a section 73 application to vary or remove the time condition is the cleanest route. It is determined on the condition rather than on the whole scheme, the fee is lower, and a grant produces a new permission without the time limit.
Once the period has expired there is nothing left to vary. The permission has been implemented and spent, so the route becomes a fresh full application, or a retrospective application under section 73A where the development has already been carried out and the breach has begun.
A further temporary period is often the realistic ask. Where the original harm was genuine but is diminishing, a second temporary permission of a defined length, with tighter conditions, gives the authority a way to say yes. It also resets the clock on your enforcement exposure, which has its own value.
The evidence requirements are much the same as for the section 73 route described in evidence for a section 73 application changing house types: deal with what has changed, not with the original merits.
Evidence that circumstances have changed
The application has to answer the reason the permission was temporary in the first place. Find that reason in the original officer's report or the committee minutes, and address it directly.
What tends to work:
- Monitoring data covering the temporary period: noise measurements, traffic counts, trip surveys, hours of operation records
- Physical mitigation installed since the original grant, with before and after evidence
- A change in the development plan or in national policy since the original decision that now supports the use
- Evidence that the alternative the authority had in mind has not come forward, where that is a matter of public record such as a lapsed allocation
- Where the condition was imposed to protect a specific interest, such as a visual effect, updated photography from the agreed viewpoints with vegetation as it now stands
What does not work: length of occupation on its own, the cost of removal, or the absence of complaints presented as proof of acceptability. Do not make assertions about how the council has behaved unless you can cite its own published documents.
Be honest about the harm that remains. An application that concedes a residual effect and offers a condition to control it reads better than one that claims there is nothing to weigh.
Enforcement risk while an application is pending
An authority can serve a notice while an application is under consideration. In practice many will hold off if an application is validated and progressing, but that is a courtesy and not an entitlement, and it is not something to rely on in a report to a funder.
Reduce the exposure in three ways. Write to the enforcement team before expiry, setting out the intended application and the timetable. Submit early enough that validation problems do not push you past the date. And keep operating within the terms of the expired permission, because a breach that has also grown in scale is a much easier enforcement case.
Non-compliance with a breach of condition notice is a summary offence. The penalty is a fine, but the record and the disclosure consequences usually matter more than the amount.
Where time has run and immunity may apply
In England the enforcement time limit for a breach of planning control is now ten years for all breaches, following the change made by the Levelling-up and Regeneration Act 2023 and brought into force in April 2024. The previous four year period for buildings and for a change of use to a single dwellinghouse no longer applies to breaches occurring after that change. Check the current position and the transitional arrangements, because the detail determines which period applies to your breach.
A continuing failure to comply with a condition requiring removal can in principle become immune after the relevant period of continuous breach, at which point a certificate of lawfulness of existing use or development settles the position formally. The burden of proof is on the applicant, on the balance of probabilities, and the evidence has to cover every year of the period without a gap.
This route is slow, fact-specific and no substitute for applying. It matters most when you are buying or refinancing a site where somebody else let the period lapse years ago.
Removal and reinstatement obligations
If the answer is removal, read the condition carefully. Many require reinstatement of the land to a specified condition, not merely the removal of the structure, and some specify a timescale after the period ends.
Three things get overlooked. Reinstatement works may themselves need permission or fall under permitted development rights, so check before assuming. A structure that has stood for years may have been colonised by bats or nesting birds, and both are protected, so a survey is needed before demolition; the issues are the same as those set out in evidence base for a site with a bat roost in the roof. And the demolition waste carries duty of care obligations, with hazardous materials such as asbestos cement sheeting requiring separate handling.
Where the ground beneath has been used for storage, fuel or vehicle maintenance, expect the authority to ask about contamination before accepting the land as reinstated.
What to submit
For a permanent retention application, the pack is usually: the application forms and fee, a location plan and block plan, existing and proposed elevations of the structure as built, a Planning Statement that addresses the original reason for the temporary condition head on, and the technical reports that respond to it.
Which technical reports depends entirely on that original reason. A noise-based condition needs an acoustic assessment with monitoring data. A visual condition needs updated photography and, on an open site, a landscape and visual appraisal. A highways condition needs trip and parking survey data from the operating period. Browsing all 66 report types is the quickest way to match the document to the constraint.
Include a chronology: the original permission number and date, the condition wording verbatim, the expiry date, and what has happened since. Officers deciding these applications are working out whether the situation is drifting or being managed, and a clear chronology answers that before they have to ask.
PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it.
Frequently asked questions
Can I use a section 73 application to extend a temporary permission?
Only while the permission is still live. Section 73 varies or removes a condition on an extant permission, so once the temporary period has expired there is nothing left to vary. After expiry the routes are a fresh full application or a retrospective application under section 73A for development already carried out.
What enforcement action can the council take after expiry?
A breach of condition notice, which requires compliance and carries no right of appeal to the Planning Inspectorate, with challenge limited to judicial review. Or an enforcement notice, which carries full appeal rights but takes longer to take effect. Authorities often prefer the breach of condition notice for that reason.
Does long occupation help the case for permanent permission?
No. National guidance states that the fact an applicant has become accustomed to the use is not a material consideration in favour of making it permanent. The application has to address the reason the permission was made temporary, with evidence from the operating period rather than an appeal to habit.
Is a second temporary permission worth asking for?
Often yes. Where the original harm was real but is reducing, a further defined period with tighter conditions gives the authority a way to grant rather than refuse, and it resets your enforcement exposure. It also builds a longer monitoring record for a permanent application later.
How long before the breach becomes immune from enforcement?
In England the limit is now ten years for all breaches of planning control, following the change made by the Levelling-up and Regeneration Act 2023 and brought into force in April 2024. Transitional arrangements determine which period applies to an older breach, so check the current position.
Do I need a survey before removing the structure?
Probably. A building that has stood for years may support roosting bats or nesting birds, both of which are protected, so an ecological check before demolition is prudent and often necessary. Demolition waste also carries duty of care obligations, with asbestos cement and similar materials handled separately.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.