Which Reports Do I Need

Evidence for a section 73 application changing house types

8 min readBy PlanScope Editorial Team

Section 73 varies conditions, not the description of development. Here is the comparative evidence a house type substitution needs, and the traps in drainage, net gain and the levy.

A section 73 application to change approved house types is an application to develop without complying with the condition that ties the permission to the approved drawings. It is not a resubmission, and the evidence is comparative: what was approved, what is now proposed, and what difference the change makes to each matter the original decision turned on. Get that framing right and the document pack is short. Get it wrong and you end up submitting a full application's worth of reports for a change of elevation treatment.

The limits on the power matter more than the procedure. Section 73 varies conditions. It cannot rewrite the permission.

What section 73 can and cannot change

Section 73 of the Town and Country Planning Act 1990 allows an application for permission to develop without complying with conditions attached to an earlier permission. The authority considers only the question of the conditions.

Three limits decide whether the route is available at all.

The description of development cannot be changed. Following the Court of Appeal's decision in Finney v Welsh Ministers in 2019, a variation that would conflict with the description on the original decision notice is outside the power. So if the description says "erection of 24 dwellings" and you now want 26, section 73 will not get you there. If it says "erection of dwellings in accordance with the approved plans", you have more room.

The time limit for implementation cannot be extended. Section 73(5) prevents it, and a permission that has expired cannot be revived by varying a condition.

And the change has to be capable of being described as a variation rather than a different development. There is no statutory definition of a minor material amendment, which is a term from guidance rather than from the Act, so the practical test is whether the authority will accept the application as one properly made under section 73.

What you get is a new, freestanding planning permission. The original stays on the register and remains capable of implementation, which is occasionally useful, as our note on schemes relying on a fallback position explains. Every condition you want to keep has to be re-imposed on the new permission, and conditions already discharged on the original are not automatically discharged on the new one.

Identifying the condition to be varied

Start with the decision notice and name the condition precisely. On a housing scheme the drawings condition is usually condition 2 or 3, listing plan numbers and revisions.

Then check which other conditions the change touches. Changing house types commonly disturbs more than the drawings condition:

  • Materials and finishes, where the new types use different brick or roof tile.
  • Levels, where a wider or deeper footprint changes finished floor levels.
  • Landscaping and tree protection, where plot boundaries move.
  • Parking and cycle storage, where space standards or garage provision change.
  • Drainage, where impermeable area or the position of the attenuation feature changes.
  • Affordable housing, where the mix or tenure location is fixed by condition or by agreement.

List every condition you are asking to vary in the application form and in the covering statement. An application that varies the drawings condition alone, while the new drawings plainly conflict with the approved materials schedule, gets stuck at validation or produces conditions that contradict each other.

Drawings and the comparison schedule

The single most useful document in a section 73 submission is a comparison schedule. It is a table, usually two or three pages, and it does the officer's work for them.

Item As approved As proposed Change
Unit numbers and mix 24 units, 8 x 2 bed, 12 x 3 bed, 4 x 4 bed 24 units, 10 x 2 bed, 10 x 3 bed, 4 x 4 bed Mix altered, total unchanged
Floorspace Stated gross internal area Stated gross internal area Net change, with the figure
Heights Ridge heights by plot Ridge heights by plot Plot by plot difference
Parking Spaces by plot Spaces by plot Net change against the standard
Impermeable area Area in m² Area in m² Net change

Drawings should be submitted as a full new set, properly numbered, with a superseded plans list showing exactly which approved drawing each new one replaces. Where the change is geometric, overlay drawings showing the approved footprint against the proposed one answer most of the questions an officer will otherwise ask by email.

Keep the numbers honest. A comparison schedule that understates a height increase is the fastest way to lose officer trust on a scheme you still have to build out.

Which reports need updating, and which do not

The test is whether the change affects the matter the report addressed. Apply it report by report rather than refreshing everything.

Usually needed:

  1. An updated planning statement, short, setting out the condition to be varied, the comparison, the policy position and why the change is acceptable.
  2. Revised drawings and the superseded plans list.
  3. An updated drainage position where impermeable area, levels or the drainage layout change.
  4. An updated noise or air quality position only where the change alters the relationship between the development and the source.

Usually not needed: archaeology, where the ground disturbance envelope is unchanged. Heritage, where the relationship to the designated asset is unaffected. Transport, where unit numbers and access are unchanged. Contamination, where the remediation strategy is unaffected and already conditioned.

Where a report is not being updated, say so explicitly and explain why. A single paragraph confirming that the approved transport statement remains valid because the number of units and the access arrangement are unchanged is better than silence, which reads as an omission.

Biodiversity and drainage consequences

Two areas catch out experienced applicants.

Biodiversity net gain is the first. The mandatory regime under the Environment Act 2021 came in for major development in February 2024 and for small sites in April 2024, and the transitional provisions deal specifically with section 73 permissions where the original permission predates those dates. The position turns on the detail of the regulations and has been amended, so check the current transitional provisions before assuming either that the regime applies or that it does not. Where it does apply, a biodiversity net gain assessment and a biodiversity gain plan are needed before development begins, and the statutory metric has to be completed by a competent person.

Drainage is the second. Changing house types almost always changes roof area, driveway area and plot levels, and a drainage strategy approved for the earlier layout may no longer work. The lead local flood authority is a consultee on major development and will compare the proposed impermeable area with the approved figure. If it has gone up, expect a request for revised calculations rather than an acceptance that the approved discharge rate still holds.

An illustrative example. A 24 unit scheme where the housebuilder substitutes its current standard types for the types approved three years earlier. Total units unchanged, mix shifted by two units, ridge heights up by 300 mm on six plots, impermeable area up by 180 m². The submission comprises a four page planning statement, a comparison schedule, a full drawing set with a superseded plans list, revised drainage calculations, and a letter confirming that the approved tree protection, archaeology and contamination positions are unaffected. That pack is proportionate, and it is what an officer can determine without a stream of queries.

The section 106 and levy position

Because section 73 creates a new permission, the existing section 106 agreement may not bind it. Check the agreement's own definitions: a well drafted agreement defines the planning permission to include any permission granted under section 73, and many do. Where it does not, you need a deed of variation or a supplemental agreement, and that has to be completed before the new permission is issued.

Community infrastructure levy liability is recalculated against the new permission, with provisions in the levy regulations intended to prevent double counting where the earlier permission has already been charged. The arithmetic depends on the charging schedule, the floorspace change and any existing building credit, so get a fresh liability calculation rather than assuming the earlier notice carries across. Where the change increases floorspace, assume additional liability.

Self build and residential extension exemptions claimed on the original permission do not automatically carry over either. Re-claim them against the new permission before commencing.

Fee, publicity and determination

The fee for a section 73 application is a flat figure set by the fee regulations, which are indexed annually, so check the current schedule rather than a figure from a previous project. It is markedly lower than a fresh application fee on a housing scheme, and that saving is one of the main reasons to use the route.

Publicity and consultation requirements follow the normal rules, so neighbours are notified and statutory consultees are consulted on the varied scheme. The determination period follows the category of development, and extensions of time are common where drainage or ecology comments are outstanding.

One practical point on sequencing. Do not start building the revised scheme on the strength of a submitted section 73 application. Until it is granted, the only permission you hold is the original one, and work that departs from it is unauthorised development rather than a variation in progress.

Browse the 66 PlanScope report types to work out which documents your variation actually engages, then confirm the list with the case officer before submitting.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Can section 73 change the number of units?

Only where the description of development does not state the number. Following the Court of Appeal decision in Finney v Welsh Ministers, a variation that conflicts with the description on the original decision notice falls outside the power. A description reading "erection of 24 dwellings" blocks a change to 26, so a fresh application would be needed.

Does a section 73 permission replace the original?

No. It is a new, freestanding permission that sits alongside the original, which remains on the register and capable of implementation. Every condition you want kept must be re-imposed on the new permission, and conditions already discharged on the original are not automatically discharged on the new one.

Will the existing section 106 agreement bind the new permission?

Only if the agreement's definition of the planning permission extends to permissions granted under section 73. Many well drafted agreements do. Where yours does not, a deed of variation or supplemental agreement is needed and has to be completed before the new permission can be issued.

Does biodiversity net gain apply to a section 73 application?

It depends on the transitional provisions, which deal specifically with section 73 permissions where the original predates the February 2024 and April 2024 commencement dates. Those provisions have been amended, so check the current regulations rather than assuming either outcome. Where the regime applies, a biodiversity gain plan is needed before development begins.

Can section 73 extend the time to implement a permission?

No. Section 73(5) prevents a variation that extends the time limit for implementation, and a permission that has already expired cannot be revived by varying a condition. If the time limit is the problem, the only routes are a fresh application or, where lawful, implementation of the existing permission.

Sources and further reading

section 73minor material amendmenthouse typesplanning conditionscilsection 106

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Which Reports Do I Need

View all →
Which Reports Do I Need7 min read

Signage across an industrial or business estate

Advertisement consent across a multi occupier estate is judged only on amenity and public safety. Deemed consent covers signs on business premises but rarely the shared entrance totem.

Read article →
Which Reports Do I Need7 min read

A substation to serve a new development

The distribution network operator usually builds the substation serving a new development, but siting, access and transformer noise fall to the applicant to resolve in the layout.

Read article →
Which Reports Do I Need7 min read

Enclosing a balcony on an existing flat

Flats have no permitted development rights, so enclosing a balcony needs permission. The amenity space argument, the fire performance question and the consents beyond planning.

Read article →
Which Reports Do I Need7 min read

Reconfiguring a car park and adding spaces

A car park reconfiguration is rarely refused on capacity. It is decided by surface water drainage, accessible bay dimensions, lighting spill and root protection areas.

Read article →
Which Reports Do I Need7 min read

Keeping a structure after a temporary permission expires

Once a temporary permission expires the structure is unauthorised and the removal condition is in breach. The section 73, fresh application, retrospective and immunity routes compared.

Read article →
Which Reports Do I Need8 min read

Bringing a long-empty building back into use

Resuming the use of a building that has stood empty for years may need no permission, or a full change of use application. The dividing line is abandonment, and it is decided on evidence.

Read article →