Which Reports Do I Need

Reports for a site with no mains foul drainage

8 min readBy PlanScope Editorial Team

A site with no foul sewer needs percolation test results, a drainage field design sized from them, and the FDA1 form. Test before you fix the house position.

A site with no mains foul drainage needs three things in the application that a connected site does not: a completed foul drainage assessment form, percolation test results carried out to the recognised method, and a drainage field design sized from those results. Get the percolation test done before you fix the house position, because on a clay site the drainage field may need more space than the garden has.

No mains drainage planning documents are not a formality. Many authorities refuse or hold applications where the foul solution is described as "package treatment plant to soakaway" with nothing behind it.

The hierarchy and why connection is tested first

National guidance and Building Regulations both set out the same order of preference for foul drainage, and an application that skips a step will be asked to justify it.

  1. Connection to the public foul sewer.
  2. A package treatment plant discharging to a drainage field.
  3. A septic tank discharging to a drainage field.
  4. A package treatment plant discharging to a watercourse.
  5. A cesspool, which stores rather than treats and needs emptying by tanker.

Connection comes first even where the sewer is some distance away, so expect to show why it is not reasonable. The usual evidence is a quotation or a written response from the sewerage undertaker giving the connection point, the route, and the cost or the physical obstacle. A long pumped rising main across third-party land is a legitimate reason to move down the hierarchy. "There is no sewer in the lane" is not evidence until somebody has asked.

A cesspool is the answer of last resort and several authorities will refuse one outright for a new dwelling, because the whole-life cost and the tanker movements are both poor outcomes.

Percolation testing and the method that counts

The test that counts is the one in Approved Document H of the Building Regulations, which follows the method in BS 6297. Anything else, including a hole filled with a hosepipe and timed with a phone, will be challenged.

The method in outline: dig at least two trial holes in the proposed drainage field area, each 300 mm square, to a depth 250 to 300 mm below the invert of the proposed distribution pipe. Fill each to a depth of 300 mm and allow it to seep away overnight. Then refill to 300 mm and record the time taken for the water to fall from 225 mm to 75 mm. Repeat three times per hole. Divide the average time in seconds by 150 to get the percolation value, Vp, in seconds per millimetre.

Two results rule out a drainage field altogether. A Vp below 15 means the ground drains too fast and effluent would reach groundwater untreated. A Vp above 100 means it drains too slowly and the field will flood. Both are common, and both are better discovered in February with a spade than in August with a contract.

A separate trial hole dug deeper checks the water table. If groundwater sits within one metre of the proposed invert level at the wettest time of year, a drainage field is not acceptable. Test in winter or early spring if you can, because a summer test on a site that floods in January proves very little.

Sizing the field and the space it needs

The area is calculated from the percolation value and the population the system serves. Approved Document H gives the formulas, and they differ depending on what is upstream.

System Drainage field area formula Example at Vp 40, 5 persons
Septic tank A = p x Vp x 0.25 50 m²
Package treatment plant A = p x Vp x 0.20 40 m²

Illustrative example: a four-bedroom house counted as five persons, on a site with a percolation value of 40 seconds per millimetre, needs roughly 40 m² of drainage field with a treatment plant. At a Vp of 90 the same house needs about 90 m². That is before the separation distances.

Those distances are what usually breaks the layout. A drainage field has to sit at least 10 metres from any watercourse or permeable drain, 50 metres from a well, borehole or spring used for supply, and 15 metres from any building. It cannot go under a driveway, a patio or anywhere vehicles will run, and it needs an area of similar size kept in reserve for future replacement.

On a half-acre plot with a stream along one boundary and a neighbour's borehole beyond the hedge, the available area can disappear entirely. Plot that constraint diagram before the architect starts, not after.

When you need a permit rather than the binding rules

Most domestic systems operate under the general binding rules, which allow a small sewage discharge without a permit provided the conditions are met. An environmental permit from the Environment Agency is needed where they are not.

The volume thresholds are the first test. Discharges to ground above 2 m³ per day, and discharges to surface water above 5 m³ per day, need a permit. A single house will be well below both. Five houses on a shared plant may not be.

The other triggers are about location. A discharge to ground within a groundwater source protection zone 1, or close to a protected site such as a Site of Special Scientific Interest or a Special Area of Conservation, generally needs a permit and sometimes cannot be permitted at all. New discharges to surface water in some catchments face the same position.

Where your site falls into a nutrient neutrality catchment, additional foul flows have to be offset before permission can be granted, whatever the drainage method. That is a separate exercise with its own cost and programme, and it has delayed plenty of small schemes by many months. Check the catchment position at feasibility stage.

Choosing and maintaining a package treatment plant

Specify the unit, not the concept. The application should name a plant certified to BS EN 12566-3, give its population equivalent rating, and show where it sits in relation to the house, the access for de-sludging and the power supply.

Three practical points officers and building control both ask about:

  • Access for a tanker within the hose reach stated by the manufacturer, usually from a hard surface rather than across a lawn.
  • Electrical supply, because most plants need power and a plant that is switched off to save money stops treating.
  • A maintenance regime with an annual service and a de-sludging interval, which the general binding rules require you to follow.

Treatment plants are not a way round a poor percolation result. A plant produces better quality effluent than a septic tank, which reduces the drainage field area by a fifth under the formulas above, and it does nothing at all if the ground will not accept water.

Discharging to a watercourse

Where a drainage field is impossible, discharge to a watercourse is the next option, and it comes with its own set of requirements. A septic tank may not discharge to surface water. A treatment plant may, subject to the binding rules or a permit.

You need a watercourse that flows throughout the year, not a ditch that is dry each summer. You need a legal right to discharge into it, which means riparian ownership or the written agreement of the owner, and that agreement should be in the application rather than promised. The outfall itself needs designing, with headwall, erosion protection and a non-return arrangement where the watercourse can back up. Consent from the lead local flood authority may be needed for works in an ordinary watercourse.

What to submit, and what the conditions will ask for

The submission pack for a non-mains site usually runs to four documents beyond the drawings.

The foul drainage assessment form, FDA1, accompanies the application form where non-mains drainage is proposed, and it asks directly about the sewer connection test, the percolation results and the proposed system. A Foul Sewage Assessment sets out the hierarchy, the evidence against each step and the chosen solution with its calculations. A Drainage Strategy deals with surface water separately, because the two are assessed by different people and surface water has its own hierarchy. And where the site has no mains water either, a Water Supply Assessment covers the borehole or spring supply, which also interacts with the 50 metre separation distance.

Expect a condition requiring the foul drainage details to be approved before development begins, and a second requiring the system to be installed as approved before first occupation, with evidence. Keep the percolation test sheets, the plant data sheet, the installation photographs and the maintenance contract in one file. You will be asked for all four, and the as-built position of the drainage field is the one nobody photographs before it is backfilled.

Other buried constraints work the same way, in that the evidence has to come before the layout, as with a site crossed by a high pressure gas main easement.

This is general guidance, not legal advice, and the permit position depends on your site's location, so check with the Environment Agency and your local planning authority before relying on it. For specialist technical reports, qualified professional input may be required. Enter your postcode on PlanScope to see which drainage and site reports your project is likely to need.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What percolation value rules out a drainage field?

A percolation value below 15 seconds per millimetre means the ground drains too quickly for effluent to be treated before reaching groundwater. A value above 100 means it drains too slowly and the field will flood. Either result rules out a drainage field, and both are common. Groundwater within one metre of the proposed invert also rules it out.

How big does a drainage field need to be?

Approved Document H gives the formula. For a septic tank the area in square metres is the number of persons multiplied by the percolation value multiplied by 0.25; for a treatment plant the multiplier is 0.20. A five-person house at a percolation value of 40 needs about 40 m² with a treatment plant, before separation distances are applied.

Do I need an environmental permit for a septic tank?

Usually not. Most domestic systems operate under the general binding rules. A permit is needed where the discharge exceeds 2 m³ per day to ground or 5 m³ per day to surface water, or where the site sits in a groundwater source protection zone 1 or close to a protected site such as an SSSI or Special Area of Conservation.

Can a septic tank discharge to a stream?

No. A septic tank may only discharge to a drainage field. Discharge to surface water requires a package treatment plant, a watercourse that flows all year, and a legal right to discharge into it through riparian ownership or the owner's written agreement. The outfall needs designing, and works in an ordinary watercourse may need consent.

What separation distances apply to a drainage field?

At least 10 metres from any watercourse or permeable drain, 50 metres from a well, borehole or spring used for supply, and 15 metres from any building. It cannot sit under a driveway, patio or any area vehicles will cross, and an area of similar size should be kept in reserve for future replacement.

Sources and further reading

foul drainageseptic tankpackage treatment plantpercolation testself-builddrainage field

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Which Reports Do I Need

View all →
Which Reports Do I Need7 min read

Reports needed for a holiday lodge park on a former quarry

A lodge park on a former quarry needs restoration conditions checked, faces and fill tested for stability, and the habitat that has colonised the site surveyed. This is the evidence base that follows.

Read article →
Which Reports Do I Need7 min read

Reports needed to deck an existing surface car park

Trip generation barely moves when parking goes vertical. Daylight, overlooking, vehicle fire risk, raised lighting and collected drainage are what decide the application.

Read article →
Which Reports Do I Need7 min read

Reports needed for a garden centre cafe and canopy

A cafe reached through the plant area is ancillary. A destination restaurant on an out-of-centre site is not. Here is the document list and the conditions that catch people.

Read article →
Which Reports Do I Need7 min read

Reports needed for self-storage in a converted mill

Heritage, flood risk and bats decide a mill self-storage application, and two of them have seasonal constraints. Here is the document list and the sequence that avoids rework.

Read article →
Which Reports Do I Need6 min read

Reports needed for a poultry unit extension near homes

A poultry shed extension near dwellings pulls in EIA screening, odour and ammonia evidence, noise work and an environmental permit. Here is the document set and the order to commission it in.

Read article →
Which Reports Do I Need7 min read

Reports needed for a riding arena with lighting

Keeping horses for riding is not agriculture, so a floodlit arena needs full permission. Here is the evidence base a rural council will look for, and the order to assemble it in.

Read article →