Which Reports Do I Need

Reports needed for a battery storage site by a substation

6 min readBy PlanScope Editorial Team

Grid-scale battery storage in England is determined by the local planning authority whatever its capacity. This is the evidence base a scheme next to a substation actually needs.

A grid-scale battery storage scheme in England is decided by the local planning authority, whatever its capacity. Storage other than pumped hydro was taken out of the national infrastructure consenting regime in 2020, so the 50 MW threshold that used to send larger schemes to the Secretary of State no longer applies. You are making a full planning application to a district or unitary council, and the battery storage planning reports that matter are the ones that answer noise, fire, flood and restoration.

That is the good news and the bad news. A local determination is faster than a development consent order and it puts an environmental health officer, a lead local flood authority and a county landscape officer in a position to shape the conditions. Scope the evidence to those consultees rather than to a national template.

The consenting route and the site that grid chooses

Battery schemes are site-constrained in a way that most development is not. The point of connection is offered by the distribution network operator or the transmission owner, and the offer fixes the search area to a few fields around an existing substation. Planning arguments about sequential site selection tend to fail on that point, which means the landscape and agricultural land questions have to be answered on the site you have.

Where the site sits on grade 1, 2 or 3a agricultural land, expect the authority to ask about the loss of best and most versatile land. An Agricultural Land Classification survey settles the grade, and the survey has to be done when the soil is workable rather than waterlogged, so it is one to commission early in the year rather than in January.

Screening for environmental impact assessment

Most battery schemes are screened rather than assumed. Energy installations fall within Schedule 2 to the Town and Country Planning (Environmental Impact Assessment) Regulations 2017, and once the site area passes the indicative threshold the authority has to issue a screening opinion. Request one formally. A screening opinion in hand is worth more at validation than a consultant's view that the scheme is obviously below the line, and a negative opinion closes off a ground of challenge later.

Where a screening opinion comes back positive, the Environmental Impact Assessment has to be prepared by competent experts under the 2017 Regulations, and the environmental statement becomes the document the whole application hangs from. Programme six months for that, not six weeks.

Noise from inverters and cooling at night

Noise is where these applications are won or lost. The plant runs at night, the sources are continuous, and inverters and transformers produce tonal sound that people notice at levels well below the total. Environmental health officers assess it under BS 4142:2014+A1:2019, which compares a rating level against the measured background sound level and applies corrections for tonality, impulsivity and intermittency.

Three points decide the outcome:

  1. The background survey has to cover the quietest representative period, which for a rural site means several nights, not a single Tuesday.
  2. The rating level must include the character correction. A transformer hum can attract a correction of several decibels, and an assessment that ignores it will be sent back.
  3. The assessment has to model the worst realistic operating case, which is usually a hot night with cooling fans at full duty during charging.

A Noise Impact Assessment prepared on that basis normally leads to a condition fixing a rating level at the nearest noise-sensitive facade, with acoustic barriers or container selection as the mitigation.

Fire, thermal runaway and the fire and rescue service

Lithium-ion cells can enter thermal runaway, and the resulting fire produces toxic gas and cannot be put out in the ordinary way. Fire and rescue services have taken a close interest in these applications, and the National Fire Chiefs Council has published guidance on grid-scale storage that authorities routinely refer to when consulting.

Expect to submit a fire safety document dealing with separation distances between containers and to the boundary, detection and gas venting, access for appliances on two sides, hardstanding able to carry an appliance, static water supply or hydrant provision, and a plan for firewater containment so that run-off does not reach a watercourse. This is fire engineering work and should be prepared by someone with the relevant competence. It is worth saying clearly that the Article 9A fire statement regime under the Development Management Procedure Order 2015 applies to relevant residential buildings, so it does not catch a battery site; the document here is a bespoke one agreed with the fire and rescue service.

Firewater containment is the point that most often comes back from the Environment Agency. Bunding, a penstock valve on the outfall and an attenuation basin sized for a firefighting event are the usual answers.

Landscape, visual effect and the security kit

Containers stand around three metres high, and the visible scheme is rarely just the containers. Acoustic barriers, a two and a half metre security fence, CCTV columns, external lighting and a substation compound all appear in the photomontages, and an assessment that models the containers alone will be picked apart at committee.

A Landscape and Visual Impact Assessment following GLVIA3 should agree viewpoints with the authority before the photography is done. Lighting is worth handling separately, because a rural site with security lighting on all night creates an obtrusive light objection that ILP GN01 guidance is used to test. Specify a lighting scheme that runs on detection rather than dusk-to-dawn and much of that objection goes away.

Flood risk, drainage and hardstanding

Two questions arise. The first is the flood zone and the vulnerability classification of the development, which determines whether the sequential test and exception test apply. Battery storage is often argued as essential utility infrastructure under the planning practice guidance classification, and authorities do not always accept that, so agree the classification with the authority and the Environment Agency in writing before the assessment is finalised rather than after.

The second is surface water. Compacted stone, container plinths and access tracks change the run-off regime across a field, and the lead local flood authority will want discharge restricted towards the greenfield rate with attenuation sized for climate change allowances. A Drainage Strategy sitting alongside the flood risk work covers the hierarchy, infiltration testing and the outfall agreement.

The document bundle and the restoration condition

For a typical field-scale scheme next to a substation, the submission usually comprises a planning statement, a design and access statement, the noise assessment, the landscape and visual assessment, a flood risk assessment and drainage strategy, a preliminary ecological appraisal with the biodiversity net gain metric, an arboricultural assessment where hedgerows or trees are affected, a construction traffic management plan covering abnormal loads, the fire safety document, and a decommissioning and restoration statement. Where the screening opinion is positive, all of that folds into an environmental statement instead.

Decommissioning is not an afterthought. Authorities commonly grant a temporary permission tied to the design life of the plant and impose a condition requiring a decommissioning and restoration scheme, sometimes backed by a bond through a section 106 agreement. Draft the restoration scheme yourself and submit it with the application. A scheme written by the applicant, with soil handling and reinstatement to agricultural use set out properly, is far better than one written for you by condition.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. For specialist technical reports, qualified professional input may be required.

Enter your postcode on PlanScope to see which of the 66 report types a battery site is likely to need. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Does a battery storage scheme over 50 MW still go to the Secretary of State?

No. Electricity storage other than pumped hydro was removed from the national infrastructure consenting regime in England in 2020, so a battery scheme of any capacity is now determined by the local planning authority as an ordinary planning application. Check the current position for Wales separately, because the devolved thresholds differ there.

Is an environmental impact assessment always required for battery storage?

Not always. These schemes usually fall within Schedule 2 to the Environmental Impact Assessment Regulations 2017, which means the authority issues a screening opinion rather than the assessment being automatic. Request a formal screening opinion before submission, because a documented negative opinion removes a ground of challenge later on.

Which noise standard applies to inverter and transformer noise?

BS 4142:2014+A1:2019 is the method environmental health officers use for sound of an industrial or commercial character. It compares a rating level with the measured background sound level and adds corrections where the sound is tonal or intermittent. Transformer hum usually attracts a tonal correction, and an assessment that leaves it out tends to be rejected.

Do I need a fire statement under Article 9A for a battery site?

No. The Article 9A fire statement requirement in the Development Management Procedure Order 2015 applies to relevant residential buildings, not to energy infrastructure. Battery schemes instead submit a bespoke fire safety document covering separation, detection, appliance access, water supplies and firewater containment, prepared by someone with fire engineering competence.

How long is planning permission for battery storage usually granted?

Authorities commonly grant a temporary permission matched to the design life of the plant, with a condition requiring a decommissioning and restoration scheme at the end of that period. Some also seek a bond through a section 106 agreement. Submitting your own restoration scheme with the application gives you more control over the soil handling and reinstatement standard.

Will the loss of farmland be a problem for a battery site?

It can be where the land is grade 1, 2 or 3a, which counts as best and most versatile. An Agricultural Land Classification survey establishes the grade on the ground rather than relying on the provisional national mapping. Because the grid connection offer fixes the search area, the argument usually turns on soil handling and reversibility rather than alternative sites.

Sources and further reading

battery storagebessenergy infrastructurenoisefire safetymajor developmentwhich reports

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Which Reports Do I Need

View all →
Which Reports Do I Need7 min read

Reports for a rooftop pool on a flat conversion

A rooftop pool on a converted block turns on three pieces of evidence: the weight of water on the existing structure, the noise of wet plant, and what the enclosure does to the roofline.

Read article →
Which Reports Do I Need7 min read

Reports for a sand and gravel extension of six hectares

A six hectare gravel extension is decided by the mineral planning authority, needs an EIA screening opinion, and turns on hydrogeology and restoration rather than on blasting.

Read article →
Which Reports Do I Need6 min read

Reports for a traveller site with four pitches

A four pitch traveller site is a minor application with a major policy test. Need evidence, pitch separation and flood vulnerability decide most of these cases.

Read article →
Which Reports Do I Need7 min read

Reports for a micro hydro scheme on a weir

Micro hydro at a weir needs planning permission plus abstraction, impoundment and flood risk permits. The fish pass is often the costliest item, and it has to be settled before the drawings.

Read article →
Which Reports Do I Need7 min read

Reports for a student accommodation scheme of 200 beds

A 200 bed student scheme is a major application with two documents that have no equivalent on a standard residential pack: the institutional need case and the student management plan.

Read article →
Which Reports Do I Need7 min read

Reports needed for a church hall replacement

Rebuilding a church hall means answering three questions at once: the community facility replacement test, the setting of the adjoining listed church, and what lies under a churchyard.

Read article →