Scotland: the infrastructure levy power and its status

6 min readBy PlanScope Editorial Team

Scotland has an enabling power for an infrastructure levy and no regulations to bring it into effect. Section 75 obligations still carry developer contributions.

This article is about Scotland. The Planning (Scotland) Act 2019 gives Scottish Ministers power to introduce an infrastructure levy by regulations, and that power has never been exercised. As at October 2026, no infrastructure levy operates in Scotland and developer contributions are still secured through planning obligations under section 75 of the Town and Country Planning (Scotland) Act 1997. Budget on that basis, and check the current position on legislation.gov.uk before relying on any of this, because the enabling power is time-limited and the Scottish Government's intentions have moved more than once.

That is the practical answer. The longer answer matters for anyone appraising a Scottish site with a long programme, because the shape of the power tells you what a levy would look like if it ever arrives, and the gap between the power and the regulations is where the risk sits.

What the enabling power allows

The 2019 Act creates a framework rather than a levy. It allows regulations to impose a charge on development, to set who is liable and when, to provide for how the money is spent on infrastructure, and to deal with collection, enforcement and appeals.

Several features follow from that structure. A levy would be set out in secondary legislation, so the detail would be consulted on separately from the Act. It would sit alongside, rather than replace, the existing obligations regime unless the regulations said otherwise. And it would require charging authorities to produce and examine charging documents, which is itself a multi-year exercise for 34 planning authorities.

The Act also limits the period within which the regulations may be made. Check whether that period has been extended, because the answer determines whether the power is still live at all.

The current status and the as at position

As at October 2026, the position as published is this. The power exists in the 2019 Act. No regulations have been made under it. No charging schedules exist. Nothing is payable.

So when an appraisal or a land promotion document refers to a Scottish infrastructure levy, treat it as a policy possibility rather than a cost line. If someone has put a figure in a residual valuation for it, ask where the figure came from.

I would be cautious about predicting what happens next. The reform has been through consultation, a pandemic, a change of ministerial priorities and the publication of National Planning Framework 4, and at each stage the timetable moved. The honest answer is that nobody can tell you when or whether a levy will arrive, which is exactly why the as at date on any note about it matters.

How it would sit alongside obligations

Section 75 agreements remain the mechanism, and they are not going away whatever happens to the levy. They secure affordable housing, education and transport contributions, open space, and the restrictions that make a development acceptable in planning terms.

Mechanism Current Scottish position
Section 75 obligations In force and used for site-specific and pooled contributions
Section 75A modification or discharge Available, with an appeal to Scottish Ministers against refusal
Infrastructure levy Enabling power only, no regulations made
Good neighbour agreements Available under the 1997 Act as amended

Circular guidance on planning obligations in Scotland sets out the tests for obligations and the expectation that they are necessary, related to the development and reasonable in scale. Those tests are what an appeal against a refusal to modify an obligation turns on.

National Planning Framework 4 forms part of the development plan and its infrastructure-first policy expects the infrastructure implications of development to be addressed from the outset. In practice that has shifted more weight onto obligations, not less, because the policy expectation arrives without a levy to fund it.

Lessons from the English experience

England has run a levy alongside obligations since 2010 and the experience is instructive, which is why Scottish practitioners should pay attention to it even though the regime does not apply.

Three lessons stand out. A fixed charge per square metre is simple to administer and blunt where viability varies across an authority, so charging schedules end up with zones and exemptions that reintroduce complexity. Reliefs and exemptions create procedural traps, since missing a claim before development begins loses the relief permanently. And a levy does not remove the need for obligations, because site-specific infrastructure and affordable housing still have to be secured by agreement.

The Levelling-up and Regeneration Act 2023 took powers in England for a replacement levy, and those powers have not been brought into general operation. Check the current position before describing it to a client. The pattern of a power taken and not exercised is now familiar on both sides of the border.

What developers should plan for

For a Scottish site being appraised now:

  1. Price section 75 contributions from the authority's own published guidance and from recent concluded agreements on comparable schemes
  2. Assume no levy liability unless regulations have been made and a charging document is in place for that authority
  3. Build the obligation negotiation into the programme, because concluding an agreement is often the longest item after determination
  4. Where a scheme has a long build programme, consider how a future levy would interact with permissions already granted, and raise it with your solicitor when the agreement is drafted
  5. Keep the infrastructure case documented, since infrastructure-first policy expects it

A Viability Assessment for a Scottish scheme should state the contributions assumptions explicitly, with their source, rather than carrying an unexplained allowance. Councils usually expect a suitably qualified author for that document and professional review is strongly advised.

Note that PlanScope's drafting is grounded in English national policy and English local plans, so a Scottish application needs National Planning Framework 4, the local development plan and Scottish procedure checked by your reviewer before submission.

Monitoring the reform

Watch three places. Legislation on legislation.gov.uk will show any regulations made under the 2019 Act power, which is the only thing that creates a liability. Scottish Government consultation and policy publications will signal intent before that. And individual authorities' development plan and contributions guidance will show how obligations policy is tightening in the meantime.

Local place plans have given communities a route into plan-making that often raises infrastructure expectations, and the note on local place plans in Scotland explains how they work. The development hierarchy also determines how an application is processed and who decides it, which is set out in the hierarchy of developments in Scotland.

Practical advice now

Do not reserve for a levy that does not exist. Do reserve properly for obligations, which are real, negotiated and often larger than appraisals assume.

Ask the authority early what its expectations are for affordable housing, education and transport on a scheme of your type, and ask for the evidence behind them. In Scotland, as in England, the contributions conversation is won with published policy and comparable agreements rather than with argument.

And keep a dated note in the project file recording the levy position as at the date of your appraisal. When the scheme is reviewed in two years, that note is what tells the reviewer whether the assumption needs rechecking. Applications notified to Scottish Ministers follow a separate track again, as set out in notification of planning applications to Scottish Ministers.

This is general guidance, not legal advice; check the position with your planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Is there an infrastructure levy in Scotland?

No. The Planning (Scotland) Act 2019 contains a power for Scottish Ministers to introduce one by regulations, and as at October 2026 no regulations have been made and no charging documents exist. Developer contributions continue to be secured by planning obligations under section 75 of the Town and Country Planning (Scotland) Act 1997.

Would a levy replace section 75 agreements?

Not entirely. Even where a levy operates, site-specific infrastructure, affordable housing and restrictive provisions still need securing by agreement, which is the English experience of running a levy alongside obligations since 2010. The regulations would set out how the two mechanisms interact.

Should I include a levy allowance in a Scottish appraisal?

No, unless regulations have been made and a charging document applies to that authority. Price section 75 contributions instead, using the authority's published guidance and recent concluded agreements on comparable schemes, and record the date on which you checked the levy position.

Does the enabling power expire?

The Act limits the period within which regulations may be made under the power. Check legislation.gov.uk for the current wording and for any amendment extending that period, because the answer determines whether a levy remains legally possible without fresh primary legislation.

How does National Planning Framework 4 affect contributions?

It forms part of the development plan and its infrastructure-first policy expects the infrastructure implications of development to be addressed from the outset. Without a levy to fund that expectation, the practical effect has been to place more weight on section 75 obligations rather than less.

Sources and further reading

scotlandinfrastructure levysection 75developer contributionsnpf4

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Wales, Scotland and Northern Ireland

View all →
Wales, Scotland and Northern Ireland7 min read

Northern Ireland: development in areas of natural beauty

Development in a Northern Ireland area of outstanding natural beauty is judged on siting and integration as much as principle. The landscape test is where most schemes fail.

Read article →
Wales, Scotland and Northern Ireland7 min read

Wales: the sustainable transport hierarchy in applications

In Wales the sustainable transport hierarchy is national policy applying to site choice and layout, not just to the transport chapter. Active travel duties and maximum parking standards follow from it.

Read article →
Wales, Scotland and Northern Ireland7 min read

Scotland: open space and play provision policy

Scotland puts open space strategies and play sufficiency assessments on a statutory footing. What they mean for layout, standards and section 75 obligations.

Read article →
Wales, Scotland and Northern Ireland7 min read

Wales: minerals and aggregates policy in applications

Welsh minerals applications run on MTAN 1, the regional technical statements and the well-being duty. What to assess and what the submission has to contain.

Read article →
Wales, Scotland and Northern Ireland7 min read

Northern Ireland: the Department's call-in power explained

A call-in takes an application out of a council's hands and removes the appeal to the Planning Appeals Commission. The criteria, the process and the programme risk.

Read article →
Wales, Scotland and Northern Ireland7 min read

Northern Ireland: enforcement powers and immunity periods

Northern Ireland uses a single five year immunity period and sends enforcement appeals to the Planning Appeals Commission. What each notice does and how to respond.

Read article →