Section by section evidence in a Gateway One fire statement

7 min readBy PlanScope Editorial Team

The Gateway One form is the document, not a narrative report. Answer each section in its own order, cross-reference a drawing against every answer, and evidence access and water supply properly.

The Gateway One fire statement sections are prescribed, and the form is the document. Officers do not want a narrative report with a fire statement bolted on. They want each section of the published form answered, with a drawing reference against each answer, so that the Building Safety Regulator can check a specific question in a specific place.

The requirement sits in article 9A of the Town and Country Planning (Development Management Procedure) (England) Order 2015. An application for planning permission for development involving a relevant building must be accompanied by a fire statement on the form published by the Secretary of State, and the Health and Safety Executive is consulted as the Building Safety Regulator.

Which buildings the requirement applies to

A relevant building contains two or more dwellings or educational accommodation, and either has seven or more storeys or is 18 metres or more in height.

Two measurement points catch people out. Height is measured in the way the Order specifies rather than in the way a drawing happens to be dimensioned, so take the measurement from the definition and show it on a section. And storey counting includes the arrangement at ground and basement level, which on a sloping site produces arguments.

Mixed use schemes need care. A building with commercial units at ground floor and dwellings above still contains dwellings, so the test applies to the building as a whole. A scheme of several blocks on one site may have some relevant buildings and some not, and the statement should say which blocks it covers.

Where the building is close to a threshold, resolve it before submission. An application that should have been accompanied by a statement and was not is liable to be treated as invalid, and the determination period restarts.

The prescribed form and its sections

The form asks for the principles, concepts and approach to fire safety rather than the detailed engineering. In practice the content falls into recognisable blocks.

Section theme What the regulator is looking for
Site and building description Use, height, storey count, number of dwellings, site constraints
Emergency vehicle access Route from the adopted highway, hardstanding position, dimensions
Water supplies Hydrant locations, available flow, any tank and pump arrangement
Means of escape principles Number and position of cores, stair strategy, travel distances in principle
External walls and materials Proposed wall construction and materials, attachments, balconies
Relationship to neighbours Separation distances, boundary conditions, overlooking buildings
Author and competence Who prepared it and on what basis

Answer in the form's own order and language. Where a question does not apply, say why rather than leaving a blank, because a blank reads as an omission.

Cross-reference every answer to a drawing number and revision. The single improvement that makes most difference to a Gateway One response is a schedule at the front of the Fire Statement listing each form section against the drawing that evidences it.

Site access and water supply evidence

These two sections carry more weight than the rest put together, because they are the parts planning permission actually fixes.

For access, show the route from the adopted highway to the building, the hardstanding position and its dimensions, the clear height under any projection or undercroft, the carriageway width and the turning arrangement. State the design vehicle. Where the hardstanding sits on a podium or over a basement, state the structural loading capacity, because an appliance standing on a slab designed for cars is a real objection rather than a theoretical one.

For water supply, do not assume. Obtain written confirmation of hydrant positions and available flow from the water undertaker and reference it, with the date. Where flow is inadequate, the solution is usually additional hydrants or a static supply with a pump, and both occupy space and need to appear on the layout. A statement that supply "will be confirmed at a later stage" is the most common cause of a request for further information.

Both sections should also record what happens during construction, because access and supply arrangements during a phased build differ from the end state.

Means of escape and the planning level of detail

The regulator is not asking for a full escape strategy at planning stage. It is asking whether the building form allows one.

So describe the number of stair cores, their position in plan, whether the stairs are protected and ventilated in principle, whether the scheme relies on a single stair, and the approximate travel distances from the furthest point on a typical floor. Where a single stair is proposed, address it directly rather than waiting to be asked, because the policy environment around single stair residential buildings has moved and a statement that ignores the issue reads as evasive.

Include a typical floor plan marked with the core positions and the escape routes. Include the ground floor plan showing the exits and their relationship to the appliance access position. That is usually the whole of what is needed at this stage.

Firefighting shafts, lift provision and evacuation strategy for disabled occupants should be addressed in principle. The detailed design belongs at the later gateways under the Building Safety Act 2022 framework, and saying so is legitimate provided the principle is settled.

External wall and materials commentary

Material choice is a planning matter and a fire matter at once, which is why this section causes friction.

Say what the external wall construction is in principle, what the cladding and insulation materials are proposed to be, and how attachments such as balconies, canopies and solar panels are treated. Where materials are to be confirmed by condition, propose the condition wording yourself and make clear which products are excluded.

The practical point for an architect is sequencing. A planning permission that fixes a facade appearance achievable only with a material the building control route will not accept creates a problem that is expensive to unwind. Agree the material palette with the fire engineer and the facade consultant before the planning drawings are issued, not after.

The Design and Access Statement and the fire statement should describe the same building. Inconsistency between the two is noticed.

Who must author the statement

A fire statement is a fire engineering document. A licensed or competent professional is legally required for this work under the Building Safety Act 2022 framework and article 9A, and the form asks about the author for that reason.

Name the author, state their competence and the basis for it, and have them sign. An architect can coordinate the submission and assemble the drawings, but the judgements in the statement belong to someone with fire engineering competence. The same is true of the fuller Fire Safety Strategy that follows at building control stage.

Where a draft has been prepared to structure the submission, treat it as a starting point for that professional rather than a finished document. The professional directory is the route to a reviewer who can check and sign off a draft.

Consultee response and how to answer it

Responses arrive in three forms. No concerns raised. A request for further information or clarification. Or a conclusion that the statement is inadequate.

Answer the second and third the same way. Take each point in the regulator's own order, state what has changed with drawing revision numbers, state what has not changed and the technical reason, and confirm who reviewed the revised statement. Send it to the case officer with a request that it be forwarded for a further response, and agree an extension of time in writing so that the clock does not force a decision.

Resist the instinct to push every point to Gateway Two. Some points do belong there and saying so is fair, but a response that defers everything reads as avoidance and tends to produce a refusal.

A Planning Statement drafted in PlanScope will frame the policy case and the consultation chronology, with flags where the fire engineering evidence has to be supplied and signed by your fire engineer.

This is general guidance, not legal advice. For specialist technical reports, qualified professional input may be required.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What is a relevant building for a fire statement?

One containing two or more dwellings or educational accommodation that either has seven or more storeys or is 18 metres or more in height, as defined for article 9A of the Development Management Procedure Order 2015. Measure height the way the Order specifies and show the measurement on a section, because sloping sites create disputes.

Does the statement need a full fire strategy?

No. The planning stage statement covers the principles, concepts and approach, enough to show the building form can accommodate the measures required. Detailed design belongs at the later gateways under the Building Safety Act 2022 framework. Saying so is legitimate, provided the principle for each form section is settled and evidenced.

How should firefighting water supply be evidenced?

With written confirmation of hydrant positions and available flow from the water undertaker, referenced with its date. Where flow is inadequate, show additional hydrants or a static supply and pump on the layout, because both take up space. A statement that supply will be confirmed later commonly triggers a request for further information.

What if the building has a single stair?

Address it directly in the means of escape section rather than waiting for the question. Describe the core position, the protection and ventilation approach in principle, and the travel distances. The policy environment around single stair residential buildings has changed, so a statement that passes over the point reads as evasive.

Can an architect write the fire statement?

An architect can coordinate the submission and prepare the drawings, but the statement is a fire engineering document and a competent professional is legally required for it. Name the author, state their competence and have them sign. An unattributed statement is one of the most common reasons for an inadequacy finding.

Sources and further reading

fire statementplanning gateway onebuilding safety acthigh risevalidation

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Report Deep Dives

View all →
Report Deep Dives7 min read

The maintenance section of a landscape strategy

The maintenance section is where a landscape strategy is won or lost. It has to name who does the work, for how long, paid from what, with what happens when planting fails.

Read article →
Report Deep Dives7 min read

The viability appraisal inputs section explained

A reviewer reads the land value derivation and the developer return first. How to set out every input with its source, and test the conclusion honestly.

Read article →
Report Deep Dives7 min read

The mitigation section of a protected species survey

Officers read the mitigation section asking whether the measures can be conditioned and whether a licence is likely. How to write one that answers both.

Read article →
Report Deep Dives7 min read

The sequential test section of a flood submission

The area of search and the list of reasonably available sites decide whether a sequential test survives review. Land ownership is not a filter.

Read article →
Report Deep Dives7 min read

The root protection area section of a tree survey

The root protection area is calculated as 12 times stem diameter and capped at 707 square metres. Everything in the arboricultural submission follows from that figure.

Read article →
Report Deep Dives7 min read

The significance of effects section of an EIA chapter

Matrices do not do the thinking. Here is how to write a significance section a decision maker can follow and a reviewer can test, chapter by chapter.

Read article →