Report Deep Dives

The viability appraisal inputs section explained

7 min readBy PlanScope Editorial Team

A reviewer reads the land value derivation and the developer return first. How to set out every input with its source, and test the conclusion honestly.

Two inputs decide the answer in almost every viability appraisal: the benchmark land value and the developer return. Build costs, sales values, fees and finance move the result, but they move it within a range. Change the benchmark land value by 20 per cent and the conclusion on affordable housing changes entirely. That is why a council's reviewer turns to those two inputs first, and why an appraisal that explains everything except its land value assumption is read as evasive.

Planning Practice Guidance on viability and the RICS professional statement on financial viability in planning both set the ground rules. Read them before drafting the inputs section, because the expectations about evidence and transparency are explicit.

Which inputs drive the outcome

A residual appraisal takes gross development value, deducts construction costs, fees, finance, developer return and planning obligations, and arrives at a residual land value. That residual is then compared with the benchmark land value to decide whether the scheme is viable with the policy-compliant package.

Set out every input in a single table at the front of the section, with the value, the unit, the source and the date. A reviewer should not have to hunt through the appendices to find the build cost rate. Then explain the derivation of each input in the order of its effect on the result, which means land value and return first, not last.

State the appraisal software used and the date the appraisal was run. Inputs age, and a file prepared 14 months before submission will be challenged on that ground alone.

Benchmark land value and its derivation

Planning Practice Guidance sets out the existing use value plus a premium approach. The existing use value is established from the current use of the land, and the premium is the amount that provides a reasonable incentive for a landowner to bring the site forward, while still allowing a sufficient contribution to comply with policy.

Four points control whether the figure survives scrutiny.

The existing use has to be evidenced, with the rental or capital evidence that supports it, not asserted from a valuer's experience. The premium has to be justified by reference to market evidence and to policy-compliant transactions, and expressing it as a percentage of existing use value without explanation is the most common weakness. Any alternative use value relied on must be a use that could realistically obtain permission. And the price actually paid for the site is not a justification, because guidance is clear that paying too much does not entitle an applicant to a reduced contribution.

Where the site is in an existing employment use and the proposal would lose it, the land value argument and the policy argument interact, and our note on the evidence an employment land assessment needs for release covers that overlap.

Build costs and the source of the rates

Base construction costs normally come from published cost information adjusted for location and date, or from a quantity surveyor's measured estimate. Either is acceptable. What is not acceptable is a single rate per square metre with no stated basis.

Present the cost build-up in layers:

  • Base build cost by building type and floor area, with the rate source, index date and location factor
  • External works, usually as a percentage of base build with the percentage justified by the site layout
  • Abnormal costs, itemised, each supported by a survey, report or quotation
  • Section 278 and utility costs, where those are not in the obligations package
  • Professional fees as a percentage of construction, with the percentage stated
  • Contingency, commonly in the order of 5 per cent for new build and higher for refurbishment, justified rather than asserted

Abnormals are where disputes concentrate. A reviewer will accept piling costs supported by a ground investigation. They will not accept a lump sum labelled "site constraints" with no documentation behind it, and including one weakens the credibility of the rest of the appraisal.

Sales values and comparable evidence

Gross development value needs comparable evidence set out properly: address, date, size, condition, tenure and the adjustment made to reach the subject property.

Three habits make a difference. Use recent transactions rather than asking prices. Adjust explicitly and show the adjustment rather than presenting a conclusion. And state the new build premium applied, with evidence, because that premium is frequently assumed and rarely justified.

For affordable housing, state the tenure mix, the transfer values assumed per unit, and whether a registered provider has indicated those values. A transfer value assumption significantly below what providers in the area are paying will be challenged, and it depresses the residual in a way that directly affects the conclusion.

Commercial elements need rent, yield, void and incentive assumptions, each evidenced.

Developer return and the risk justification

Planning Practice Guidance indicates that for plan making a return of 15 to 20 per cent of gross development value may be considered suitable, with a lower figure potentially appropriate for affordable housing delivery. Site-specific appraisals work from the same framework.

Two things to get right. Whether the return is expressed on gross development value or on cost makes a material difference, so state which and be consistent. And if the return sought sits above the range, justify it by reference to the actual risk profile of the scheme: scale, phasing, market exposure, abnormal risk, pre-let or pre-sale position. Asserting a higher return because the applicant's internal hurdle rate requires it is not a planning argument.

Returns on affordable housing are conventionally lower, because the risk is lower where there is a forward funding arrangement with a provider. Show the split rather than applying one blended figure across the whole scheme.

Finance, fees and contingency

Finance assumptions need the interest rate, the arrangement fee, the assumed debt proportion and the drawdown profile. The build programme and the sales rate drive the interest cost, so an optimistic programme produces an understated finance line that a reviewer will test.

Acquisition costs include stamp duty, agent and legal fees. Disposal costs include sales agency and legal fees and a marketing allowance. Each of these is conventional and each should still carry a stated percentage.

Planning obligations and the Community Infrastructure Levy are inputs too. State the levy calculation and the relief assumed, and set out the obligations package being tested, since the whole point of the appraisal is to test one package against another.

Sensitivity testing the inputs

A single-point appraisal invites the response that the conclusion is fragile. Sensitivity testing pre-empts it.

Test at least gross development value, base build cost and benchmark land value, each at a stated percentage above and below the central case, and present the results as a table showing the effect on the residual and on the contribution the scheme can support. Where the conclusion flips within a narrow range, say so. Honesty about fragility is more persuasive than a confident result that collapses under a 5 per cent movement.

Scenario testing is different from sensitivity testing and is worth adding where the scheme has genuine alternatives, such as a different tenure mix or a phased delivery.

What an authority's reviewer interrogates first

The order is predictable, and it mirrors the order of influence: benchmark land value derivation, developer return and its basis, abnormal costs and their evidence, sales values and the comparables behind them, then finance and programme.

Expect the appraisal to be made publicly available. Guidance expects transparency as the default, with only limited exceptions, so write the inputs section knowing that objectors and the local press will read it.

Our note on the viability assessment sections a reviewer reads first covers how the rest of the report should be structured around that order. Where the outcome affects the affordable housing offer, the Affordable Housing Statement and the Viability Assessment have to tell the same story, with the same figures.

Councils expect a suitably qualified author for viability work, usually a chartered surveyor working to the RICS professional statement, and professional review is strongly advised. Browse all 66 report types and start a draft at PlanScope, then send it to a reviewer before submission.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

How is benchmark land value established?

Planning Practice Guidance sets out an existing use value plus a premium approach. Evidence the existing use value from rental or capital evidence, and justify the premium by reference to market evidence and policy-compliant transactions. Any alternative use value relied on must be for a use that could realistically obtain permission.

Does the price paid for the site count?

No. Guidance is clear that the price paid is not a justification for failing to comply with policy. An overpayment is a commercial decision between buyer and seller, and transferring its consequences to the affordable housing contribution is exactly what the benchmark land value framework is designed to prevent.

What developer return is acceptable?

Planning Practice Guidance indicates that 15 to 20 per cent of gross development value may be considered suitable for plan making, with a lower figure potentially appropriate for affordable housing. State whether your return is on value or on cost, be consistent, and justify anything above the range by the scheme's actual risk profile.

How should abnormal costs be presented?

Itemised, each supported by a ground investigation, survey, report or contractor quotation. A lump sum labelled as site constraints with no documentation will be removed by the reviewer, and its presence undermines confidence in the rest of the appraisal. Keep abnormals separate from base build and external works.

What sensitivity testing is expected?

At minimum, gross development value, base build cost and benchmark land value, each tested at a stated percentage above and below the central case, with results shown as a table against the residual and the contribution supported. Where the conclusion flips within a narrow range, state that rather than presenting a single confident figure.

Will the appraisal be published?

Expect so. Guidance treats transparency as the default for viability assessments submitted with applications, with only limited exceptions. Write the inputs section on the assumption that objectors, councillors and local press will read it, which is a useful discipline on any assumption that cannot be evidenced.

Sources and further reading

viability assessmentbenchmark land valueaffordable housingsection 106development appraisal

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Report Deep Dives

View all →
Report Deep Dives7 min read

Choosing consultation methods in an SCI

The methods section has to show the consultation could have changed something. That means justifying each method against its audience and reporting what it failed to reach.

Read article →
Report Deep Dives7 min read

Judging significance of effects in an LVIA

Significance of effects in an LVIA is a reasoned judgement built from value, susceptibility and magnitude. Matrices present the conclusions; they do not produce them.

Read article →
Report Deep Dives7 min read

Unregulated emissions in a whole life carbon assessment

Appliances, small power and lifts are not controlled by Part L but still belong in B6. Why figures vary so widely and what a checkable assessment states.

Read article →
Report Deep Dives7 min read

The maintenance section of a landscape strategy

The maintenance section is where a landscape strategy is won or lost. It has to name who does the work, for how long, paid from what, with what happens when planting fails.

Read article →
Report Deep Dives7 min read

The mitigation section of a protected species survey

Officers read the mitigation section asking whether the measures can be conditioned and whether a licence is likely. How to write one that answers both.

Read article →
Report Deep Dives7 min read

The sequential test section of a flood submission

The area of search and the list of reasonably available sites decide whether a sequential test survives review. Land ownership is not a filter.

Read article →