Flood, Drainage and SuDS

Sewer flooding records and what they tell you

6 min readBy PlanScope Editorial Team

Undertakers hold registers of properties at risk of sewer flooding and incident histories with causes. How to get them, how to read them and where they fall short.

Sewerage undertakers hold a register of properties they know are at risk of sewer flooding, and in England that history is obtainable. For a site where surface water or foul drainage will connect to a public sewer, those sewer flooding records in planning terms are often the strongest evidence you can put in front of a lead local flood authority, because they describe what the network has actually done rather than what a model predicts.

The records an undertaker holds

Three sets of information are worth asking for, and they are not the same thing.

The flooding risk register, long known in the industry by its regulatory reporting code, lists properties assessed as at risk of internal or external sewer flooding at a stated return period. Entries distinguish internal flooding, where effluent enters a building, from external flooding, where it surfaces in a garden, yard or road.

The incident history is separate. It records reported flooding events with a date, a cause and an outcome, and the cause matters more than the count. Hydraulic overload means the sewer lacked capacity in the rainfall event. Blockage, collapse, equipment failure and third-party action mean something else entirely, and a run of blockage incidents on a flat shared drain says nothing about network capacity.

The sewer records themselves, which undertakers must keep available for inspection under section 199 of the Water Industry Act 1991, give you the pipe layout, diameters, materials and whether the system is combined, foul or separate. Those three documents together let you say whether a connection is sensible.

How to request the history

Start with developer services. Every undertaker runs a pre-development or pre-planning enquiry service that returns sewer records, capacity commentary and often an indication of flooding history for the catchment, and it is the quickest route because the output is formatted for planning use.

Where the response is thin, there is a second route. Sewerage undertakers are treated as public authorities for the purposes of the Environmental Information Regulations 2004, so a request for environmental information about sewer flooding in a defined area can be made under those Regulations, with the usual 20 working day period for a response.

Expect the data to come back aggregated. Addresses are usually withheld or reduced to a postcode sector, because individual property flooding history is personal data. That is normally enough for a planning argument, which is about the catchment rather than one house.

Request What it gives you Typical turnaround
Developer services pre-development enquiry Sewer records, capacity commentary, connection advice Weeks, varies by undertaker
Request under the 2004 Regulations Flooding incident data for a defined area, aggregated 20 working days
Section 199 sewer map inspection Pipe layout, diameter, material, system type On request

Reading internal and external entries

An internal flooding entry is serious evidence. It means foul water has entered a habitable building from the public sewer, and a cluster of them downstream of your site will shape what the undertaker will accept.

External entries are more common and more ambiguous. Surcharging from a manhole in a road during an extreme event is not the same as a garden filling with sewage twice a year, and the register entry alone will not tell you which. Ask for the return period attached to the entry and the date range of the incidents behind it.

Watch the geography. Records are catchment-based, so an entry 400 m away on the same trunk sewer is more relevant to your connection than one 50 m away on an unconnected branch. Plot the entries against the sewer record rather than against a street map, and the pattern usually resolves itself.

Using the records in a drainage assessment

The records do two jobs in a Drainage Strategy. They justify the discharge hierarchy decision, and they set the design constraint for any connection you do propose.

On hierarchy, national policy and the non-statutory technical standards for sustainable drainage expect surface water to go to the ground first, then to a surface water body, then to a surface water sewer, with a combined sewer last. Documented hydraulic flooding downstream is the clearest possible support for infiltration or an attenuated outfall to a watercourse instead. Our note on which rainfall dataset to cite in a drainage calculation covers the rainfall inputs that sit alongside it.

On design, a history of surcharge means the receiving sewer is under pressure, so a restricted discharge rate, attenuation storage sized for a surcharged outfall, and a non-return valve or pumped connection become sensible rather than cautious. Where foul capacity is the issue, the evidence belongs in a Foul Sewage Assessment and will frame what the undertaker says about reinforcement.

Where the site is also in a mapped flood zone, keep the two strands separate in the Flood Risk Assessment. Sewer flooding is a source of flood risk in its own right and is often omitted from the sources section entirely.

What the records mean for your connection

Section 106 of the Water Industry Act 1991 gives a right to connect to a public sewer, and section 94 places a general duty on the undertaker to maintain and improve the system. In practice the undertaker can impose conditions on the connection and can require the discharge to be restricted or phased while reinforcement is programmed.

That is where a Grampian condition appears, tying occupation to the completion of off-site sewer works. For a developer the question is the programme, because reinforcement schemes run on the undertaker's investment cycle rather than yours. Asking early whether any reinforcement in the catchment is already funded is worth more than arguing about capacity later.

If the answer is that no works are planned, the options narrow to reducing the discharge, storing on site, or a private treatment solution. Each has a cost that belongs in the appraisal before the land is bought.

Where the records understate the problem

Be honest about the limits of this evidence, because a consultee will be.

  • The register records known risk. Properties never reported as flooded do not appear, so absence of entries is weak evidence of safety.
  • Residents in rented or managed stock report less often, so some catchments are systematically under-recorded.
  • Entries can be removed after mitigation works, which means a historic problem may have vanished from the current register.
  • Causes are assigned at the time by a field operative, and hydraulic overload is sometimes logged as a blockage.
  • Climate change allowances mean a sewer that coped historically may not cope across the development's design life.

So present the records as one line of evidence rather than the whole case. The strongest submissions put the flooding history next to the undertaker's own capacity commentary, the topographic survey and the modelled surface water flow paths, and show that all four point the same way. Our note on managing runoff on a steeply sloping site deals with the case where they do not.

PlanScope drafts drainage and flood documents around the records and calculations you provide, and marks any missing site data rather than filling it in. For specialist technical reports, qualified professional input may be required. Reports should be reviewed before submission, and PlanScope does not guarantee planning approval.

Frequently asked questions

How do I get sewer flooding history for a site?

Start with the undertaker's developer services pre-development enquiry, which returns sewer records and capacity commentary formatted for planning use. Where the response lacks flooding data, a request under the Environmental Information Regulations 2004 can be made, since sewerage undertakers are treated as public authorities for those purposes, with a 20 working day response period.

What is the difference between internal and external sewer flooding?

Internal flooding means effluent has entered a building. External flooding means it surfaced in a garden, yard or road without entering a property. Internal entries carry far more weight with a lead local flood authority, while external entries need their return period and incident dates before they can be interpreted sensibly.

Will the undertaker give me individual addresses?

Usually not. Property level flooding history is personal data, so responses are commonly aggregated to a postcode sector or a catchment. That is normally sufficient for a planning argument, which turns on the behaviour of the network rather than on which particular house flooded.

Does a history of sewer flooding stop a connection?

No. Section 106 of the Water Industry Act 1991 gives a right to connect, and the undertaker has a general duty under section 94 to maintain and improve the system. The practical effect is conditions on the connection, a restricted discharge rate, on-site storage, or a Grampian condition linking occupation to off-site reinforcement.

Can the absence of entries be used as evidence of no risk?

Only weakly. The register records reported and assessed risk, so properties that never reported flooding do not appear, and some catchments are under-reported. Entries may also be removed after mitigation. Treat the records as one line of evidence alongside modelled flow paths and the undertaker's capacity commentary.

Sources and further reading

drainagesewer floodingflood risksudswater industryevidence

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Flood, Drainage and SuDS

View all →
Flood, Drainage and SuDS8 min read

Phasing drainage across a multi-phase site

An approved drainage scheme usually describes the finished site. On a phased development the interim conditions are where discharges and pollution incidents happen. What to draw, condition and document.

Read article →
Flood, Drainage and SuDS7 min read

Permeable paving where the ground is contaminated

Infiltration supplies the pathway between contaminated soil and groundwater, which is why source protection zones and made ground push designers towards lined permeable systems. How to evidence and condition the alternative.

Read article →
Flood, Drainage and SuDS7 min read

Trash screens, blockage scenarios and sensitivity tests

A culvert that performs perfectly in the design case can flood a site when the screen clogs. Blockage scenarios are where the real risk usually sits.

Read article →
Flood, Drainage and SuDS7 min read

Surface water from a neighbouring site and riparian rights

Water running downhill onto your land is usually lawful. Water that a neighbour has collected, concentrated or piped towards you is a different matter.

Read article →
Flood, Drainage and SuDS7 min read

Compensatory flood storage: level for level in practice

Build in the floodplain and the water you displace has to go somewhere. Level for level compensation is the test, and most schemes fail it on location rather than volume.

Read article →
Flood, Drainage and SuDS6 min read

Flood defence condition and residual life

Defended land stays in its flood zone for a reason. How to read condition grades and standards of protection, and what the breach scenarios have to resolve.

Read article →