Costs, Fees and Budgeting

Utility diversions and the cost nobody budgets

7 min readBy PlanScope Editorial Team

A cable across the site or a main under the access is a six figure possibility and a programme item measured in months. This covers surveys, cost liability, quotations, easements and abandoned apparatus.

Utility diversion cost is the line most often missing from a development appraisal, and the reason is simple: nobody knows it exists until the topographical survey is overlaid with the asset records. A high voltage cable across the middle of a site, a water main under the proposed access, a gas main along the frontage where the footway is to be widened. Each one is a six figure possibility on a medium sized scheme and a programme item measured in months rather than weeks.

The cost itself is often unavoidable. The programme damage usually is avoidable, and that is where the money actually goes.

Identifying apparatus before the layout is fixed

Start with record enquiries to every undertaker that could plausibly have apparatus in the area: the electricity distribution network operator, the gas transporter, the water and sewerage undertaker, the telecommunications operators, cable operators, and on some sites high pressure gas or fuel pipeline operators, transmission network owners and the Ministry of Defence.

Records are indicative rather than accurate. They show that something is there, roughly, and they are frequently wrong about depth and alignment. So the second step is a physical utility survey, carried out to the recognised specification for underground utility detection and verification, which works through desk study, site reconnaissance, geophysical detection and then verification by trial hole. Each level costs more and tells you more, and the decision about how far to go should be driven by what the layout depends on.

Do this before the layout is fixed. A diversion avoided by moving a building five metres is the least expensive diversion there is.

Two habits pay for themselves. Get the asset records plotted onto the survey drawing by the surveyor rather than kept as PDFs in a folder, so that everyone designs against the same information. And walk the site looking for the evidence above ground: marker posts, valve covers, stop taps, inspection chambers, poles, stay wires and the line of a recent reinstatement across a road.

Who bears the cost of a diversion

The general position is that whoever requires the diversion for their own purposes pays for it. A developer moving a cable to build a house pays the full cost of moving that cable, including design, supervision and any temporary supply arrangements.

Where a highway authority carrying out highway improvement works requires apparatus to be diverted, regulations made under the New Roads and Street Works Act 1991 share the cost between the authority and the undertaker, with an allowance recognising the betterment the undertaker gets from new apparatus replacing old. That sharing does not help a developer directly, but it matters where your scheme includes highway works delivered through an agreement with the authority, because the cost allocation can differ from a straight developer funded diversion. The note on how section 278 highway works costs are built up covers how those packages are assembled.

Where apparatus sits in private land under an easement, the position turns on the terms of the easement rather than on street works legislation. A deed granting the undertaker rights in perpetuity, with a covenant preventing building over, means the diversion is negotiated rather than required.

Quotations, their validity and their exclusions

Undertakers usually work in two stages: a budget estimate, which is indicative and unpriced in detail, and a formal quotation, which is firm for a limited period. The validity period is short, often a matter of weeks or a few months, and it lapses quietly.

Read what the quotation excludes. Common exclusions are reinstatement to the highway authority's specification, traffic management beyond a basic arrangement, works outside normal hours, third party land costs, legal fees for new easements, protection or diversion of other undertakers' apparatus encountered during the works, and any outage or switching costs where the network has to be reconfigured.

Ask three questions on every quotation. What is the assumed alignment, because a change of route after acceptance is a new quotation. What programme does it assume, including any seasonal restriction on working. And what happens to the price if trial holes show the apparatus is not where the records said.

Lead times and the programme effect

This is the cost nobody budgets, because it appears as finance and preliminaries rather than as a diversion line.

The sequence for a significant diversion runs: enquiry, budget estimate, design, formal quotation, acceptance and payment, legal work for new easements, programming into the undertaker's own workload, notices under the street works regime, and then the works themselves. On higher voltage electrical apparatus the switching window may only be available at particular times of year, and on a single circuit feeding other customers a temporary supply may be needed first.

Several months is normal. Longer is common. Treat the diversion as an item on the critical path from the day you find the apparatus, not from the day the contractor arrives.

Where the diversion crosses third party land, add the time to negotiate access and rights, because that is entirely outside the undertaker's control and yours.

Easements, wayleaves and building over

The legal position is as important as the physical one, and the two words are not interchangeable. An easement is a permanent right over land, registered against the title. A wayleave is usually a terminable agreement, and overhead electricity lines commonly sit on wayleaves rather than easements.

That distinction drives the strategy. A terminable wayleave can be brought to an end, subject to its notice provisions and to the undertaker's statutory powers to seek a necessary wayleave where the supply must continue. A registered easement has to be released or varied by deed, which means the undertaker's legal team, its own valuation of the right, and time.

Building over retained apparatus is the alternative to moving it. Water and sewerage undertakers operate build over and build near agreements for public sewers, with conditions on foundation design, access and protection, and the drainage design has to reflect them, as set out in a Drainage Strategy. For electricity and gas, build over is generally refused and protection or diversion is the only route.

Check the title for existing easements before you buy. An easement that prohibits building within a corridor across the site is a planning constraint in everything but name, and a restrictive covenant can have the same practical effect.

Abandoned apparatus and its risk

Asset records show what an undertaker believes it owns. They are far less reliable about what it has stopped owning.

Abandoned cables, redundant mains, disused service connections and old lead pipes are common on brownfield sites, and undertakers frequently decline to remove them or to confirm they are dead. The practical consequences are real: a cable that cannot be confirmed as de-energised has to be treated as live, which means hand digging and safe working precautions. An abandoned gas main may still contain gas. Asbestos cement pipework is a controlled waste with its own handling requirements.

Budget for investigation rather than for removal. A trial hole and a written confirmation from the undertaker are much less expensive than a stoppage while somebody establishes what a cable is.

Sequencing it against the layout

The order that keeps the cost down:

  1. Record enquiries and a utility survey before the layout is fixed.
  2. Plot everything on one drawing, with the easement corridors from the title plan alongside the physical apparatus.
  3. Test the layout against the apparatus, and move the buildings before you move the cables.
  4. Raise diversion enquiries in parallel with the planning application, not after permission.
  5. Reflect the diversion programme in the phasing and in the cash flow, and price temporary supplies where the works split a circuit.
  6. Coordinate with any adoption agreement, because diverted apparatus in a road being offered for adoption affects the technical approval and the commuted sum discussion covered in the note on section 38 adoption and the commuted sum negotiation.

A Utilities Assessment submitted with the application should set out the apparatus identified, the capacity position for each service, the diversions proposed and the constraints they impose on phasing. Officers rarely refuse a scheme over utilities. They do impose phasing conditions that assume a diversion is straightforward, and those conditions are much easier to write sensibly if the evidence is in front of them.

See PlanScope pricing: one free report, £50 per report, or Professional at £150 per month or £600 per year.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Who pays to divert a utility for a development?

Generally whoever requires the diversion for their own purposes, so a developer moving apparatus to build pays the full cost including design, supervision and temporary supplies. Where a highway authority carrying out highway improvements requires a diversion, regulations under the New Roads and Street Works Act 1991 share the cost with the undertaker, with an allowance for betterment.

How accurate are utility record drawings?

They reliably tell you something is present and are frequently wrong about depth and alignment. That is why a physical survey to the recognised specification for underground utility detection is worth commissioning, working from desk study through site reconnaissance and geophysical detection to verification by trial hole where the layout depends on the answer.

How long does a utility diversion take?

Several months is normal and longer is common. The sequence runs from enquiry through budget estimate, design, formal quotation, payment, legal work for new easements, programming into the undertaker's workload, street works notices and then the works. Higher voltage apparatus may only have switching windows at particular times of year.

Can I build over a sewer or a cable instead of diverting it?

Sometimes over a public sewer, through a build over or build near agreement with the sewerage undertaker, subject to conditions on foundations, access and protection. For electricity and gas apparatus, building over is generally refused and the options are protection in place or diversion. Check the position before the foundation design is fixed.

What is the difference between an easement and a wayleave?

An easement is a permanent right over land, registered against the title, and it has to be released or varied by deed. A wayleave is usually a terminable agreement, common for overhead electricity lines, which can be brought to an end subject to its notice provisions and to the undertaker's statutory powers where the supply must continue.

Sources and further reading

utilitiesdiversionscostsprogrammeeasementsdevelopment

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting8 min read

Costing a stopping up order for a highway or footpath

Public rights do not lapse through disuse and planning permission does not override them. This covers the section 247 and 257 routes, what objectors actually argue about, and how to keep the order off the critical path.

Read article →
Costs, Fees and Budgeting7 min read

Costing an affordable housing review mechanism

Early and late stage review mechanisms are decided by their definitions, not their headline percentages. This covers the inputs that move the answer, who pays for the review and the caps to secure before signing.

Read article →
Costs, Fees and Budgeting7 min read

Costing an employment land assessment for an allocated site

On an allocated employment site the fee sits in evidence gathering, not analysis. This covers the marketing records councils expect, the suitability tests that decide it, and how to sequence the work.

Read article →
Costs, Fees and Budgeting7 min read

Costing an odour assessment for a kitchen or waste use

The fee for an odour assessment depends on whether the council accepts a qualitative risk based appraisal or expects dispersion modelling. Here is what sits behind each, and how to scope the work before you commission it.

Read article →
Costs, Fees and Budgeting6 min read

Costing a telecommunications compliance declaration for a mast

An ICNIRP declaration is produced by the operator's own radio engineers and closes the health issue. Siting and appearance are the only matters the council can decide on.

Read article →
Costs, Fees and Budgeting6 min read

Costing an equalities impact assessment for a public applicant

The public sector equality duty is continuing, so an equalities impact assessment has to be revisited at every material change. Budgeting for one document is the common mistake.

Read article →