What a geotechnical assessment has to establish

7 min readBy PlanScope Editorial Team

Eurocode 7 separates the factual ground investigation report from the interpretive design report. Here is what each section has to establish for a planning submission.

Eurocode 7 splits geotechnical reporting into two documents, and most of the confusion on development projects comes from merging them. The ground investigation report is factual: what was found, where, and by what method. The geotechnical design report is interpretive: what the ground means for the structure, with derived parameters and a design position. A single bound volume is fine. Blurring the two is not, because a reader has to be able to see which numbers were measured and which were chosen.

For a planning application the question is usually narrower than for construction. Can this site carry this development, what are the stability, groundwater and ground gas risks, and what has to be conditioned.

The desk study and the ground model

Everything starts with a conceptual ground model built before anyone drills. The sources are consistent across England: published geological mapping and borehole records from the British Geological Survey, historical Ordnance Survey editions, any previous site investigation reports, coal mining and other mineral records where the site sits in a referral area, landfill and waste records, and the topographic survey.

The output is not a list of sources. It is a stated model: a sequence of strata with expected thicknesses and levels, an expected groundwater regime, and a geotechnical risk register naming each hazard with its likelihood and consequence.

That register is what the rest of the investigation is designed to test. An investigation scoped without one tends to produce boreholes in convenient locations to convenient depths, which is how sites get to tender with the compressible layer undiscovered.

Investigation methods and where the holes went

The report must justify the investigation rather than simply describe it. Technique selection, hole positions, depths and the reasoning behind each.

Cable percussion suits clays and granular soils to moderate depth and gives disturbed and undisturbed samples. Rotary coring is needed where rock or dissolution features matter. Window sampling is fast and shallow and is routinely over-relied on for small sites. Trial pits give the best picture of made ground and shallow obstructions and the worst picture of anything below the dig depth. Cone penetration testing gives a continuous profile and no samples.

Depth has to relate to the proposed structure, extending below the zone of influence of the foundation rather than to a round number. For a basement that means below formation level by a margin related to the excavation depth and the wall type.

The report should include an exploratory hole location plan with coordinates and ground levels tied to the site datum, logs prepared to the recognised description standard, and a clear statement of anything that could not be investigated and why. Access restrictions, live services and tree constraints routinely move holes, and a plan showing holes where they were actually sunk is worth more than one showing where they were specified.

Testing, in situ and in the laboratory

In situ testing gives strength and density in the ground. Standard penetration tests in granular soils, hand vane and pocket penetrometer readings in cohesive soils, cone penetration testing for continuous profiling, permeability testing where infiltration drainage is proposed, and plate loading where a bearing value has to be demonstrated.

Laboratory testing divides into classification, strength and chemistry:

  • Classification: particle size distribution, Atterberg limits, moisture content, bulk and dry density.
  • Strength and deformation: triaxial testing, shear box, oedometer consolidation where settlement governs.
  • Earthworks: compaction and California bearing ratio where the scheme includes roads or platforms.
  • Chemistry for concrete design: sulfate and pH to establish the aggressive chemical environment class for buried concrete.
  • Volume change potential on clay, usually via modified plasticity index, which drives foundation depth near trees.

Chemical testing for contamination is a separate exercise with a separate standard and belongs in the land contamination assessment rather than here, though the same fieldwork usually serves both. Keep the reporting separate even where the drilling was shared.

Derived parameters and the line between fact and judgement

This is the section that distinguishes a competent report. Characteristic values under Eurocode 7 are a cautious estimate of the value affecting the occurrence of the limit state, which is a judgement, informed by the spread of test results, the volume of ground involved and the sensitivity of the structure.

Present the derivation. Show the test results, the selected characteristic value, and the reasoning that connects them. A table giving bearing resistance with no visible route from the laboratory data to the number is the most common weakness in reports submitted with planning applications, and it is the thing an independent reviewer will pick up first.

Where parameters are taken from published correlations rather than site testing, say which correlation and why.

Foundation and retaining options

A planning-stage report does not design the foundations. It establishes that a viable foundation solution exists and identifies which solutions the ground supports, which matters because the answer sometimes changes the scheme.

Ground condition Typical implication
Shallow competent stratum under thin made ground Conventional strip or trench fill, depth driven by shrink-swell and tree proximity
Deep variable made ground Piled solution, with the pile type constrained by contamination and groundwater
Soft alluvium over competent strata Piling or ground improvement, with settlement of external works a separate issue
Shrinkable clay with mature trees Foundation depth and possibly heave protection, read together with the arboricultural constraints
Dissolution-prone strata Rotary investigation, void detection and potentially a redesigned layout

For schemes with a basement, retaining options and their construction sequence belong here too, and they feed directly into a Basement Impact Assessment where the local authority requires one.

Groundwater and dewatering

One set of water strikes recorded during drilling is not a groundwater regime. The report should present standpipe or piezometer installations, several rounds of monitoring across different conditions, and an interpretation that distinguishes perched water in made ground from a water table in the underlying stratum.

Where excavation goes below the water level, cover temporary dewatering, the volumes involved, the likely effect on neighbouring ground and structures, and whether a discharge or abstraction authorisation is needed. Hydrostatic uplift on a basement slab is a design case that has to be stated, not assumed away.

Where infiltration drainage is proposed, the soakage testing and the depth to groundwater beneath the proposed base of the soakaway both have to be reported, because a soakaway in the saturated zone does not work.

Hazards the report has to address by name

Silence on a hazard reads as an omission rather than an absence. Address each one present in the region and say whether it applies:

  1. Shrink-swell on clay, with the volume change classification and the influence of existing and removed vegetation.
  2. Dissolution features in chalk, limestone and gypsum areas, including swallow holes and the implications for foundation layout.
  3. Mining legacy, with the relevant authority's records consulted and any required report obtained.
  4. Slope stability on sloping ground, with an analysis rather than an assertion.
  5. Running sand, compressible peat and other construction risks that affect buildability.
  6. Ground gas, with monitoring to the recognised approach and a characteristic situation derived, feeding a gas protection specification.
  7. Radon, which is a regional check rather than a site investigation question.

Recommendations and the work still to come

Close with recommendations that a reader can act on and a clear list of what has not been done. Typical residuals at planning stage are detailed foundation design, additional investigation inside building footprints that could not be accessed, further groundwater monitoring across a seasonal cycle, and confirmatory testing at construction.

Say who should do each and when. A planning officer reading the report should be able to write a condition from that list, and the condition they write will be the one you drafted rather than a generic one copied from another file.

A geotechnical assessment of this kind is a report type where councils expect a suitably qualified author, and professional review is strongly advised. PlanScope can structure the document, cite the standards and insert a flag wherever site data is missing: see the geotechnical assessment page and the full report index for how it sits alongside the rest of a submission.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required.

Frequently asked questions

What is the difference between a ground investigation report and a geotechnical design report?

The ground investigation report is factual: methods, locations, logs and test results. The geotechnical design report is interpretive: derived characteristic parameters, foundation and retaining appraisal and a design position. Eurocode 7 keeps them distinct so a reader can see which numbers were measured and which were chosen. Binding them together is fine; blurring them is not.

How deep should boreholes go?

Below the zone of influence of the proposed foundation rather than to a round number. For a basement that means a margin below formation level related to the excavation depth and retaining wall type. The report should justify the depths against the conceptual ground model and the geotechnical risk register, not against a standard specification.

Is contamination testing part of a geotechnical assessment?

No, though the same fieldwork usually serves both. Chemical testing for contamination follows a different standard and belongs in the land contamination assessment, which is a report type where a suitably qualified and experienced author is expected. Keep the reporting separate even where one drilling visit produced the samples for both.

How many groundwater readings are enough?

More than one. A single water strike recorded during drilling is not a groundwater regime. Install standpipes or piezometers, monitor across several rounds and different conditions, and distinguish perched water in made ground from a water table in the underlying stratum. Infiltration drainage design needs the depth to groundwater below the proposed soakaway base.

What should the recommendations section contain?

Actions a reader can take, and an explicit list of what has not been done: detailed foundation design, investigation inside footprints that could not be accessed, further seasonal groundwater monitoring, and confirmatory testing at construction. Name who closes each item and when, so the planning officer can write the condition from your list.

Sources and further reading

geotechnicaleurocode 7ground investigationfoundationsgroundwaterreport structure

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Report Deep Dives

View all →
Report Deep Dives7 min read

The maintenance section of a landscape strategy

The maintenance section is where a landscape strategy is won or lost. It has to name who does the work, for how long, paid from what, with what happens when planting fails.

Read article →
Report Deep Dives7 min read

The viability appraisal inputs section explained

A reviewer reads the land value derivation and the developer return first. How to set out every input with its source, and test the conclusion honestly.

Read article →
Report Deep Dives7 min read

The mitigation section of a protected species survey

Officers read the mitigation section asking whether the measures can be conditioned and whether a licence is likely. How to write one that answers both.

Read article →
Report Deep Dives7 min read

The sequential test section of a flood submission

The area of search and the list of reasonably available sites decide whether a sequential test survives review. Land ownership is not a filter.

Read article →
Report Deep Dives7 min read

The root protection area section of a tree survey

The root protection area is calculated as 12 times stem diameter and capped at 707 square metres. Everything in the arboricultural submission follows from that figure.

Read article →
Report Deep Dives7 min read

The significance of effects section of an EIA chapter

Matrices do not do the thinking. Here is how to write a significance section a decision maker can follow and a reviewer can test, chapter by chapter.

Read article →