Fire, Structural and Basements

What the Building Safety Regulator asks of a fire statement

7 min readBy PlanScope Editorial Team

The Building Safety Regulator comments on whether fire safety shaped the design. Here are the themes a Gateway One review covers, the drawing package behind the form, and how to answer a request for more information.

The Building Safety Regulator, which sits inside the Health and Safety Executive, is a statutory consultee on planning applications for relevant high-rise residential buildings. It does not grant or refuse anything. What it does is tell the local planning authority whether the fire statement shows that fire safety has shaped the design rather than been bolted on afterwards, and authorities take that advice seriously because they have no in-house capability to second-guess it.

The duty comes from Article 9A of the Town and Country Planning (Development Management Procedure) (England) Order 2015, inserted in 2021, and it sits alongside the gateway regime created by the Building Safety Act 2022. Planning Gateway One is the planning stage of that regime.

The Regulator's role at Gateway One

Gateway One is a consultation, not a consent. The authority must consult the Regulator on a qualifying application and must have regard to the response, and the Regulator provides substantive comments on the fire statement and the accompanying drawings.

Three things follow from that structure. The Regulator's comments are advice, so an authority can grant permission over an unfavourable response, though in practice very few do. The comments go on the public file, so an objector or a future purchaser can read them. And because the comments are about design rather than compliance, a response that says the submission is insufficient to allow an opinion is the worst outcome available: it stalls the determination without telling you what to change.

When the duty bites

The duty applies to development involving one or more relevant buildings. A relevant building is one containing two or more dwellings or educational accommodation, and which has at least seven storeys or is at least 18 m in height.

Height is measured from ground level to the floor surface of the top storey, excluding any storey that consists exclusively of plant rooms. That definition catches schemes that feel below the threshold. A six-storey block on a sloping site measured from the lower ground level can exceed 18 m on one elevation, and a rooftop plant enclosure does not save it if the top occupied floor is already above the line.

Work through the measurement before you assume the duty does not apply. An application that should have been consulted on and was not is vulnerable, and the remedy is a fresh consultation that costs you the time you were trying to save.

The questions a Gateway One review asks

The review is structured around whether the fire safety principles have constrained the design. In practice the questions reduce to a small number of themes.

How does the fire and rescue service get to the building, and can an appliance reach the hardstanding positions the strategy relies on. What is the water supply for firefighting, and where is it. What is the means of escape strategy, and does the plan form support it. What is the external wall construction, in principle, and how do balconies and openings interact with it. Where are the firefighting shafts and how are they accessed. What constraints does the site impose that the strategy has to work around, such as a single point of vehicular access, a level difference, a railway boundary or a basement.

That last theme is the one developers underestimate. A site constraint that forces an unusual fire strategy needs to be named and addressed in the statement, because the Regulator will see it on the site plan whether you mention it or not. Basement light wells are a recurring example, and the interaction between escape from a basement and flood risk is exactly the sort of combined constraint that attracts comment.

Information the Regulator expects at planning stage

The fire statement must be submitted on the form published for the purpose, and the form is a framework rather than the whole submission. What makes a statement work is the drawing package behind it.

  • A site layout showing appliance access routes, turning and hardstanding positions, with dimensions and gradients.
  • Hydrant and water supply positions, with the available flow where known, and the proposed arrangement where it is not.
  • Floor plans at a scale that shows core arrangement, stair and lift positions, lobby arrangements and escape routes.
  • Sections showing the storey heights used in the height measurement and the position of any plant storey.
  • A statement of the principles of the external wall construction, identified by materials and reaction to fire classification at a level of detail appropriate to planning stage.
  • An account of the site constraints and how the strategy responds to them.

Say what is settled and what is not. A statement that commits to a principle and flags the detail for Gateway Two is more credible than one that implies the whole strategy is fixed at planning stage, because the Regulator knows it is not.

Where the structure is mass timber or another material with a fire performance that raises questions, deal with it head on. The design questions that mass timber schemes attract from planners overlap heavily with the ones the Regulator asks.

Where submitted statements fall short

The pattern of weak submissions is consistent, and none of the gaps is expensive to close.

Gap What it looks like in the file
No appliance access evidence Site plan with no turning head, no hardstanding and no dimensions
Water supply unaddressed A sentence saying supplies will be agreed with the fire authority
Escape strategy asserted Stated travel distances with no floor plan at a readable scale
External walls deferred entirely Reference to future compliance with the Building Regulations
Site constraints unmentioned A single access point visible on the plan and absent from the text
Author competence unstated No indication who prepared the statement

The last row matters more than it looks. The statement is expected to be prepared by someone with the fire engineering competence to stand behind it, and naming the author and their basis of competence removes an easy reason for the Regulator to discount the document.

How comments reach the authority and what they mean

The Regulator responds to the authority, which places the response on the application file. The case officer then has to weigh it alongside the other consultee responses.

A response raising specific design points usually generates a request from the case officer for a revised statement or an addendum, and the application sits still until that arrives. A response saying the submission does not contain enough information to comment produces the same stall with less direction. Either way the fix is an addendum that answers the points in the order they were raised, cross-referenced to revised drawings.

Resist the urge to argue. The Regulator's comments are about whether the design has been shaped by fire safety considerations, and a reply that defends the original submission rather than improving it reads badly on a file that a planning inspector may later see.

Timing inside the determination period

Statutory consultees work to a 21-day period, and the practical effect on a major application with a 13-week determination period is that the Gateway One round has to start in the first fortnight to leave room for a revision.

Three habits save time. Submit the fire statement and the fire drawings as a complete package at validation rather than following them up later. Ask the case officer to confirm when the consultation was issued, because consultation sometimes slips behind validation. And agree an extension of time early if an addendum is needed, rather than letting the authority refuse at week 13 for want of information.

Responding to a request for further information

Treat the response as a short, structured document rather than a redrafted statement. Number the Regulator's points, answer each one directly, and say which drawing has changed and how.

Where a point cannot be resolved at planning stage, say so and explain which gateway will resolve it. That is a legitimate answer for detailed external wall specification and for the full fire engineering strategy, which belongs in the fire safety strategy prepared under BS 9991 or BS 9999 rather than in a planning-stage statement. It is not a legitimate answer for appliance access or water supply, because those depend on site layout and site layout is what the planning permission fixes.

The documents the regime expects are set out on the fire statement page, which covers what the statement contains and who can prepare it. A Fire Statement is a report type where a professional with the necessary fire engineering competence is legally required, and PlanScope's draft is a starting point for that professional rather than a substitute for them.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required. You can enter the site postcode to see which fire and structural reports a scheme is likely to need.

Frequently asked questions

Which buildings trigger Planning Gateway One?

Development involving a relevant building: one containing two or more dwellings or educational accommodation, with at least seven storeys or a height of at least 18 m. Height is measured from ground level to the floor surface of the top storey, excluding storeys consisting exclusively of plant rooms, so sloping sites need careful measurement.

Can the Regulator refuse a planning application?

No. The Building Safety Regulator is a statutory consultee under Article 9A of the Development Management Procedure Order 2015. It provides substantive comments and the local planning authority must have regard to them. The authority decides. In practice very few authorities grant permission over an unfavourable Gateway One response.

Who should prepare a fire statement?

Someone with the fire engineering competence to stand behind it. The statement is submitted on the published form, but the credibility comes from the author and the drawing package. Naming the author and the basis of their competence removes an easy reason for the Regulator to discount the document.

What drawings should accompany the fire statement?

A site layout showing appliance access, turning and hardstanding with dimensions and gradients; hydrant and water supply positions; floor plans at a readable scale showing cores, stairs, lobbies and escape routes; and sections showing the storey heights used in the height measurement and any plant storey.

How long does the Gateway One consultation take?

Statutory consultees work to a 21-day period. On a major application with a 13-week determination period, that means the consultation needs to start in the first fortnight to leave room for an addendum. Ask the case officer to confirm the date the consultation was actually issued, because it can slip behind validation.

Can detail be left to a later gateway?

Yes for the detailed external wall specification and the full fire engineering strategy, which belong at Gateway Two and in a BS 9991 or BS 9999 strategy. No for appliance access and firefighting water supply, because both depend on the site layout that the planning permission fixes.

Sources and further reading

fire statementgateway onebuilding safety acthigh riseconsulteesdevelopers

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Fire, Structural and Basements

View all →
Fire, Structural and Basements7 min read

Smoke control strategy and its effect on elevations

Smoke control ends up as openings in a facade and boxes on a roof, both of which a planning officer assesses. Know the spatial envelope before the elevations are drawn.

Read article →
Fire, Structural and Basements8 min read

Risers, hydrants and the core layout at planning stage

Fire mains are a Building Regulations matter with planning consequences. Inlet position, appliance standing and hydrant distances decide what the ground floor and the core can be.

Read article →
Fire, Structural and Basements8 min read

Second staircase provision in tall residential design

A second stair changes the core, the floor plate, the massing and the elevations, and none of those can be revisited after permission. How the threshold is measured and what it does to the plan.

Read article →
Fire, Structural and Basements8 min read

Fire statements for the conversion of an existing block

On a conversion you are describing a building nobody has seen inside since it was built. What to survey, which existing constraints shape the strategy, and how to present residual uncertainty.

Read article →
Fire, Structural and Basements6 min read

Cross laminated timber in a residential planning application

Above 18 metres the external walls of a relevant building cannot contain combustible material, which pushes mass timber schemes towards hybrids. Floor depth, encapsulation and the carbon case follow from that choice.

Read article →
Fire, Structural and Basements7 min read

Structural survey before buying a site with a retained building

On a retained building the survey has to tell you whether your scheme is possible, and what you could not find out before exchange. The second answer costs more.

Read article →