Which Reports Do I Need

What to submit for a scheme needing a new junction

7 min readBy PlanScope Editorial Team

A new access onto an adopted highway is decided on three pieces of evidence: measured speeds, capacity modelling and an independent safety audit. Here is the full submission list.

A new junction onto an adopted highway is the part of a scheme most likely to be decided by someone who is not the planning officer. The highway authority's view on access governs whether the application is recommended for approval, and that view rests on three pieces of evidence: a speed survey that fixes the visibility requirement, capacity modelling for the assessment years, and a stage one road safety audit. New junction planning evidence that is missing any of the three usually attracts a holding objection.

Deal with access first, because everything else on the layout depends on where the road comes in.

Access in principle and the highway authority's view

Access is capable of being a reserved matter on an outline application, and in practice highway authorities resist that for a scheme forming a new junction. They want the access fixed, because its position determines visibility, the loss of frontage vegetation, the drainage and sometimes the viability of the layout.

Start with a pre-application discussion with the local highway authority, or with National Highways where the junction is onto the strategic road network, which is governed by its own circular on development affecting that network. Ask three questions: which design standard applies to this road, what assessment years and growth assumptions they expect, and whether they want a stage one safety audit at application stage.

Record the answers. A transport chapter that opens by stating the agreed scope is far harder to argue with than one that sets its own.

Visibility splays and the speed survey

Visibility is calculated, not assumed, and the calculation starts with measured speeds rather than the posted limit.

The standard approach on a street or lower speed road is to take the 85th percentile wet weather speed from an automatic traffic count over a period of about a week in each direction, then read the stopping sight distance for that speed from the tables in Manual for Streets. On higher speed roads and the strategic network, the design standards for roads and bridges apply instead and the distances are longer.

The splay is then set out as an X distance back from the edge of the carriageway, conventionally 2.4 m for a junction, and a Y distance along the carriageway equal to the stopping sight distance in each direction, measured between driver eye height and object height and kept clear of obstruction above a stated height.

What trips schemes up:

  • the measured speed exceeding the posted limit, which lengthens the splay and can push it onto third party land
  • hedges, walls and trees inside the splay, where removal needs the owner's agreement and may need consent if a tree is protected
  • a splay that crosses a neighbour's frontage, which has to be shown as land within the applicant's control or dedicated as highway
  • vertical as well as horizontal visibility, on a road with a crest or a dip
  • the splay being achievable on day one and then growing back, which is why a condition usually requires it to be kept clear in perpetuity

Where frontage trees have to go, a tree survey to BS 5837:2012 should be done before the access position is fixed, not after. Losing a category A oak for a splay changes the planning balance.

Capacity modelling and the assessment years

Capacity work tests whether the junction will operate acceptably with the development's traffic added.

The method depends on the junction form. Priority junctions and roundabouts are modelled with the standard junction capacity programs, signals with a signal modelling package, and the outputs are expressed as a ratio of flow to capacity or a degree of saturation, with queue lengths and delay.

Junction form Output to report Conventional threshold
Priority junction Ratio of flow to capacity per arm Around 0.85
Roundabout Ratio of flow to capacity per arm Around 0.85
Signal junction Degree of saturation Around 90 per cent

The years assessed matter as much as the model. Expect the opening year and a future year, with background growth applied from the national traffic growth dataset and committed development added separately. Trip generation normally comes from the national trip rate database, with sites selected and justified rather than accepted as defaults.

Two arguments worth preparing for. Whether the trip rate site selection is representative, which is the commonest point of dispute, and whether committed development has been double counted with background growth. Both are answered by an annex showing the selection criteria and the committed development list.

Where the scheme is small, a transport statement with a short capacity check may be enough. Where it crosses the threshold for a full transport assessment, the junction modelling sits inside that document with the trip generation, distribution and safety analysis.

Safety audit at design stage

A stage one road safety audit is an independent review of the design by auditors who have had no part in it, carried out to the national road safety audit standard, with a designer's response to each problem raised.

Submit the audit and the response together. An audit with unanswered problems reads as an outstanding objection, and highway officers treat it that way. Where a problem is accepted and the design changed, show the change on the drawing. Where it is not accepted, the designer's response has to give a reason rather than a disagreement.

Common stage one findings on new accesses: inadequate forward visibility on the approach, a pedestrian crossing point placed where drivers will not expect it, a bus stop too close to the junction mouth, the access gradient at the back of footway, and swept path conflicts for the largest vehicle expected to use it.

Include vehicle tracking for the design vehicle, which on a residential scheme means the refuse vehicle and the fire appliance, and on a commercial scheme the largest articulated vehicle that will serve it.

Land ownership for the splays and the works

Two separate land questions, and both get overlooked until validation.

First, the application has to be accompanied by the correct ownership certificate, and where the visibility splays or the junction works fall on land you do not own, notice has to be served on that owner. An application certified wrongly is vulnerable.

Second, the works themselves. Alterations to the existing highway are carried out under a section 278 agreement with the highway authority under the Highways Act 1980, which brings technical approval of the detailed design, inspection fees, a bond and often a commuted sum for future maintenance. New estate roads intended for adoption go through a section 38 agreement. Neither can be left to be discovered after permission, because the cost is material and the technical approval can require design changes.

Where the access crosses a verge containing apparatus, or where overhead lines or underground mains run along the frontage, the utility position has to be resolved in parallel. The same discipline applies as for a site with overhead power lines across it.

Construction access and the interim arrangement

The permanent junction is rarely available at the start of construction, so the application needs to say how plant and materials will reach the site in the meantime.

Options are a temporary access elsewhere on the frontage, early construction of the permanent junction under the section 278 agreement before the main works, or use of an existing field gate with improved visibility for the construction period. Each has consequences: a temporary access needs its own visibility and its own reinstatement, and building the junction first needs the section 278 agreement completed early.

Set this out in the construction traffic management plan with routing, hours, wheel washing and a commitment on verge protection. Highway officers care about construction traffic more than applicants expect, because it is what generates complaints during the build.

The evidence set, in one place

An illustrative example. A 60 dwelling scheme on the edge of a village forms a new priority junction onto a 30 mph road with a measured 85th percentile speed of 36 mph. The higher measured speed lengthens the required splay, which takes in a stretch of mature hedge on a neighbour's frontage. The applicant negotiates the hedge removal and replanting behind the splay, serves notice on the owner, submits a transport assessment with opening year and future year modelling, a stage one audit with responses, swept path drawings for a refuse vehicle, and a drainage detail for the new junction. The highway authority removes its holding objection before committee.

Work through the list before you submit: speed survey data, visibility drawings with X and Y dimensions stated, capacity modelling with assumptions annex, trip generation justification, stage one safety audit and designer's response, swept path analysis, junction drainage, street lighting where required, tree and hedge survey covering the splay land, ownership certificates and notices, section 278 heads of terms, and construction access arrangements.

This is general guidance, not legal advice. Check the position with your local planning authority, the highway authority or a qualified professional before relying on it. For specialist technical reports, qualified professional input may be required.

Browse all 66 report types to assemble the rest of the pack around the access evidence.

Frequently asked questions

Can access be a reserved matter on an outline application?

In law yes, but highway authorities usually resist it where a new junction is proposed, because the access position determines visibility requirements, frontage vegetation loss and drainage, and often the viability of the layout. Expect to fix the access at outline stage and to agree the scope of the transport work before submission.

How are visibility splays calculated?

From measured speeds rather than the posted limit. The 85th percentile wet weather speed is taken from an automatic traffic count over about a week in each direction, then the stopping sight distance for that speed is read from Manual for Streets, or from the roads and bridges standards on higher speed roads. The X distance is conventionally 2.4 metres.

What capacity results does a highway authority expect?

Ratio of flow to capacity per arm for priority junctions and roundabouts, with around 0.85 treated as the practical limit, or degree of saturation for signals with around 90 per cent as the equivalent. Queue lengths and delay should be reported alongside, for an opening year and a future assessment year.

Is a stage one road safety audit needed at application stage?

Many highway authorities ask for one, and it is worth confirming at pre-application. It must be carried out by auditors independent of the design, and it should be submitted with the designer's response to each problem raised. An audit with unanswered problems reads as an outstanding objection.

What is a section 278 agreement?

An agreement with the highway authority under the Highways Act 1980 allowing a developer to carry out works to the existing highway. It brings technical approval of the detailed design, inspection fees, a bond and often a commuted sum for maintenance. New estate roads intended for adoption go through a section 38 agreement instead.

Sources and further reading

highwaysvisibility splaystransport assessmentsection 278road safety auditwhich reports do i need

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Which Reports Do I Need

View all →
Which Reports Do I Need7 min read

Signage across an industrial or business estate

Advertisement consent across a multi occupier estate is judged only on amenity and public safety. Deemed consent covers signs on business premises but rarely the shared entrance totem.

Read article →
Which Reports Do I Need7 min read

A substation to serve a new development

The distribution network operator usually builds the substation serving a new development, but siting, access and transformer noise fall to the applicant to resolve in the layout.

Read article →
Which Reports Do I Need7 min read

Enclosing a balcony on an existing flat

Flats have no permitted development rights, so enclosing a balcony needs permission. The amenity space argument, the fire performance question and the consents beyond planning.

Read article →
Which Reports Do I Need7 min read

Reconfiguring a car park and adding spaces

A car park reconfiguration is rarely refused on capacity. It is decided by surface water drainage, accessible bay dimensions, lighting spill and root protection areas.

Read article →
Which Reports Do I Need7 min read

Keeping a structure after a temporary permission expires

Once a temporary permission expires the structure is unauthorised and the removal condition is in breach. The section 73, fresh application, retrospective and immunity routes compared.

Read article →
Which Reports Do I Need8 min read

Bringing a long-empty building back into use

Resuming the use of a building that has stood empty for years may need no permission, or a full change of use application. The dividing line is abandonment, and it is decided on evidence.

Read article →