Which Reports Do I Need

What to submit for a scheme replacing an employment building

7 min readBy PlanScope Editorial Team

Design is not what decides these applications. Marketing at realistic terms, a refurbishment appraisal and the authority's own supply evidence are what carry the case.

Loss of employment land documents are not really about design. A scheme that removes an existing employment building is judged on two questions: whether the site has a reasonable prospect of continuing in employment use, and whether the authority's employment land supply can absorb the loss. Answer those with evidence and the rest of the application is ordinary. Answer them with assertion and the officer has nothing to defend at committee.

Most local plans carry a protective policy for employment sites, and most of those policies set out a test with marketing evidence at its centre. That is where to start, because the marketing period runs in real time and cannot be compressed once the application is in.

How loss of employment floorspace is assessed

The typical adopted policy allows release where the applicant demonstrates that the site is no longer suitable, viable or available for employment use. Some policies add a sequential requirement: test other employment uses first, then a mixed use retaining some employment floorspace, then full loss.

Read the policy wording closely, because the burden is on you and the policy usually says so. "Demonstrate" means produce evidence an officer can rely on in a committee report. It does not mean explain.

National policy supports the re-use of land and discourages the long-term protection of sites with no reasonable prospect of coming forward for their allocated use, which is the hook for a release case. But that hook only works where the local evidence supports it, and the authority will have its own employment land evidence base saying something different.

Where a refusal has already landed, the response follows a different structure, dealt with in answering a refusal based on loss of employment land.

Marketing evidence and the period expected

Marketing is the single document most often rejected, almost always for the same reason: the terms were not realistic.

Local plan policies and supplementary documents commonly require 12 to 24 months of active marketing. Check the adopted wording, since the period is a policy requirement rather than a convention, and marketing that falls short by two months is marketing that fails the test.

What the evidence needs to contain:

  1. Instruction of a commercial agent with experience in that market, with the instruction letter dated.
  2. Quoting terms at a level that reflects existing use value, not an aspirational value based on the alternative use. Over-pricing is the commonest defect and officers spot it immediately.
  3. A board on site, photographed and dated, and listings on the portals the market actually uses.
  4. An enquiry log recording every approach, the date, the party, what was discussed and the outcome.
  5. Viewing records and copies of any offers, with a written explanation of why each was not accepted.
  6. The agent's own written market commentary on demand, comparable transactions and why the building is unlettable in its present form.

Flexibility matters too. Marketing a 2,000 square metre unit as a single let when the demand is for 300 square metre units invites the response that you marketed the wrong product. If subdivision is physically possible, test it, and if it is not, say why with a structural opinion behind it.

Condition and refurbishment viability

The second limb is whether the building could be brought back into use. Expect to prove it could not, or could not economically.

That needs a condition survey covering structure, roof, cladding, services, floor loading, eaves height, drainage, asbestos and compliance with current energy standards. The energy point has grown in importance: a building that cannot be let because of its energy performance rating needs the cost of upgrading it set out rather than asserted.

Then a refurbishment cost plan from a quantity surveyor, and an appraisal comparing refurbishment and continued employment use against the proposed scheme. The appraisal should follow recognised viability methodology, with the inputs stated and justified: existing use value, refurbishment cost, achievable rent, yield, void period and finance. Keep the input assumptions sourced, because an authority's reviewer will test each one.

A structural survey carries the condition evidence and a viability assessment carries the comparison. Both belong in the submission rather than being held back for negotiation.

Employment land supply context

The authority has an employment land review or equivalent evidence base, a monitoring report with take-up figures, and a position on whether it has a sufficient supply of employment land over the plan period. Read all three before you write a word.

Where the authority's own evidence shows a surplus, or shows that the type of floorspace on your site is in oversupply while the demand is for something your site cannot deliver, that is the strongest argument available and it comes from the authority's own documents. Where the evidence shows a shortfall, the release case has to be made on the site's specific unsuitability instead: access, constrained layout, residential neighbours, contamination, or a location that no modern occupier will take.

An employment land assessment is the document that pulls this together, and it should quote the authority's figures with the document name, date and page rather than paraphrasing them. Do not assert anything about local market behaviour that you cannot source from a published document or the agent's evidence.

The parallel reasoning applies to the loss of other protected uses, which follows the structure set out in losing a community facility and the policy tests.

Alternative uses and policy sequencing

Where the policy requires a sequence, work through it visibly. Could the site accommodate light industrial or storage uses inside Class E(g), B2 or B8 at a different configuration? Could a mixed scheme retain employment floorspace on the ground floor with residential above? Can flexible or subsidised workspace be secured by obligation?

Partial re-provision is often what wins consent. A scheme offering a smaller quantum of modern, subdivided workspace, secured by a section 106 obligation with a letting strategy and an affordability mechanism, gives the officer something to point to. A scheme offering nothing relies entirely on the marketing and viability evidence holding up.

Where the existing use is in Class E, check whether the prior approval route for commercial to residential change is available, since it carries vacancy and floorspace limits and does not apply to B2 or B8 uses. For a building in industrial or storage use, that route is closed and a full application is the only way.

The document set that answers the objection

For a redevelopment scheme replacing an employment building, the submission usually runs to:

  • Planning Statement setting out the release test and how each limb is met
  • Employment Land Assessment with the authority's own supply evidence quoted
  • marketing report with the agent's commentary and the enquiry log
  • condition survey and refurbishment cost plan
  • Viability Assessment comparing refurbishment with redevelopment
  • Economic Impact Assessment where jobs lost and created are in issue
  • Design and Access Statement
  • Transport Statement or Assessment reflecting the change in trip generation, which often falls
  • land contamination desk study, and intrusive investigation where the industrial history warrants it
  • noise assessment addressing the agent of change principle where residential is proposed alongside remaining industry
  • air quality assessment where the site is in or near an air quality management area
  • Biodiversity Net Gain Assessment and a pre-redevelopment audit covering materials and demolition

Two of those deserve emphasis. The agent of change principle means new residential development next to an existing business must mitigate the effects of that business rather than constrain it, so the noise assessment has to show how the layout, glazing and ventilation strategy protect future occupiers without putting the neighbouring operator at risk of complaint. And the contamination work on a former industrial site legally requires a suitably qualified and experienced practitioner, with an AI-assisted draft serving as a starting point for that professional rather than a substitute.

Browse all 66 report types by category to match the list against your site, and read the evidence councils expect on employment land release alongside it.

Enter your postcode on PlanScope to see which reports your redevelopment is likely to need.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

How long do I need to market an employment building before applying?

Check the adopted local plan policy or the relevant supplementary document, because the period is a policy requirement. Twelve to twenty-four months of active marketing is common. Marketing that falls short of the stated period usually fails the test outright, so start it well before you intend to submit the application.

Why is marketing evidence usually rejected?

Because the quoting terms were unrealistic. Marketing has to be at a level reflecting existing use value rather than a figure based on the hoped-for alternative use. Officers and their advisers identify over-pricing quickly. The other common defect is marketing the wrong product, such as offering a large unit whole where demand is for smaller subdivided space.

What condition evidence does a council expect?

A survey covering structure, roof, cladding, services, floor loading, eaves height, drainage, asbestos and energy performance, followed by a refurbishment cost plan from a quantity surveyor. The appraisal then compares continued employment use after refurbishment against the proposed scheme, with every input assumption stated and sourced so a reviewer can test it.

Does partial re-provision of employment floorspace help?

Often decisively. A smaller quantum of modern, subdivided workspace secured by a section 106 obligation, with a letting strategy and an affordability mechanism, gives the officer something concrete to weigh against the loss. A scheme offering nothing depends entirely on the marketing and viability evidence surviving scrutiny.

What is the agent of change principle here?

It means new residential development introduced next to an existing business must mitigate that business's effects rather than constrain its operation. On a part-released employment site the noise assessment has to show how layout, glazing and ventilation protect future residents while leaving the remaining operator free to carry on as before.

Sources and further reading

employment landloss of employmentmarketing evidenceviabilityredevelopmentwhich reports

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Which Reports Do I Need

View all →
Which Reports Do I Need7 min read

Reports for a vertical farm in a warehouse

A controlled environment vertical farm in an existing warehouse needs permission, and the use class is unsettled. Grid capacity, light spill, plant noise and trade effluent drive the evidence.

Read article →
Which Reports Do I Need7 min read

Reports for a dental practice in a converted house

A house to dental surgery conversion needs full permission for a change of use from Class C3 to Class E(e). Parking demand and plant noise are what actually decide the application.

Read article →
Which Reports Do I Need8 min read

Reports for a parcel locker and courier hub

A last mile courier hub needs transport, noise, drainage and utilities evidence shaped around pre-dawn van departures and fleet charging load, not warehouse trip rates.

Read article →
Which Reports Do I Need7 min read

Reports for a film studio on an industrial estate

There is no use class for a film studio, and standard industrial trip rates do not describe one. The evidence base is noise, lighting, grid capacity and transport, with a fire strategy for undivided stages.

Read article →
Which Reports Do I Need8 min read

Reports for a caravan storage compound on farmland

Storing unoccupied touring caravans on a field is a material change of use. The application is decided by winter visibility of the stored units and by what the hardstanding does to runoff.

Read article →
Which Reports Do I Need8 min read

Reports for a shisha lounge in a parade of shops

A shisha lounge is usually sui generis, and its application turns on a contradiction: the smoke-free definition of substantially enclosed forces an open shelter that amenity policy resists.

Read article →