A temporary marketing suite on a development site
A sales suite open to the public falls outside the temporary building right for construction accommodation. Temporary permission, advertisement consent and a removal condition are the normal package.
A marketing suite planning application is usually needed even on a site that already has permission for the houses. The permitted development right in Part 4 Class A of Schedule 2 to the GPDO 2015 covers buildings and structures required temporarily in connection with building operations, which is site accommodation for the construction work. A sales suite open to the public is a commercial use, and most authorities treat it as falling outside that right.
So the normal route is a temporary planning permission, with a condition limiting the duration and requiring removal. Where the suite was shown on the approved plans for the main scheme, check whether it was actually permitted or merely illustrated, because developers regularly assume the former.
Whether a temporary permission is needed
Three situations, three answers.
A portable cabin used as a site office for the construction team, within the compound, fenced off from the public, generally sits within Part 4 Class A for the duration of the building operations. No separate application.
A purpose built marketing suite with a reception, a kitchen, display units and public parking is a sales use. Apply for temporary permission under section 72 of the Town and Country Planning Act 1990, which allows a permission to be granted for a limited period with conditions controlling what happens at the end of it.
A completed dwelling used as a show home and sales office is the common middle case. The dwelling itself is already permitted. The sales use is not, so either apply for a temporary change of use or, better, ask for a condition on the main permission allowing the plot to be used as a sales office until a stated trigger, after which it reverts to residential use. Agreeing that at the outset avoids an application in year two.
Siting, access and visitor parking
The suite has to be reachable by members of the public without walking through a construction site, and that single requirement drives most of the layout.
Put the suite close to the site entrance with its own access, or with a segregated route separated from construction traffic by solid hoarding rather than by signage. The separation of pedestrians and vehicles is a requirement of the Construction (Design and Management) Regulations 2015 as well as a planning consideration, and the site manager will have a view.
Provide visitor parking at a realistic number for a weekend viewing, not for a weekday afternoon, with at least one accessible bay on a firm level surface and a step free route to the entrance. The suite is a building to which the public have access, so the accessibility standards applying to new non-domestic buildings are the benchmark, and it is a poor look to sell accessible homes from an inaccessible cabin.
Check what the suite sits on. A car park laid within the root protection area of a retained tree, calculated under BS 5837:2012, is a breach of the tree protection condition on the main permission. A suite placed on land allocated as habitat creation in the biodiversity gain plan creates a worse problem, because that land is committed for 30 years and the gain plan was approved on the basis that it would be delivered.
Signage and advertisement consent
Advertisement control is a separate regime under the Town and Country Planning (Control of Advertisements) (England) Regulations 2007, and planning permission for the suite does not carry consent for the signs.
Schedule 3 to the Regulations grants deemed consent for certain classes, which include boards advertising the sale of land or buildings and, within limits, flags on a housing development site. The limits on size, number, height and illumination are tighter than most marketing packs assume. One board at the entrance within the size limit is usually fine. A run of six illuminated totems, an entrance feature wall with applied lettering, a banner across the hoarding and a flag array will need express consent.
Illumination is the detail that attracts objections where existing houses adjoin the site. Where the signage or the car park lighting is illuminated, assess it as light trespass at the nearest windows and offer a curfew. That is far easier than removing it after a complaint.
Drainage, services and welfare
Temporary does not mean unserviced, and the authority will ask.
For foul drainage, the options are a temporary connection to the public sewer with the undertaker's agreement, a package treatment plant, or a cesspool emptied under contract. State which, and say what happens to it on removal. For surface water, the suite and its car park add impermeable area that the approved drainage strategy may not have allowed for at that stage, and the interim arrangement has to discharge at the permitted rate. Where the permanent attenuation is not yet built, the drainage strategy needs an interim solution for the suite as well as for the construction phase.
Welfare facilities for staff are covered by the construction regulations and the workplace regulations rather than by planning, and the water and electricity supply arrangement needs confirming early. Where a generator is used, its noise at the nearest existing dwelling is a planning matter and a running hours restriction is a reasonable thing to offer.
Duration conditions and removal
The duration condition is the part worth negotiating, because a fixed date can be awkward on a slow selling scheme.
Two forms are in common use. A fixed period, often three years, after which the use must stop. Or a trigger tied to the development, for example until the occupation of the final dwelling on the approved layout, or until a stated plot number is complete. The trigger form is usually better for the developer and is often accepted, though some authorities prefer a date because it is simpler to enforce.
Whichever is used, expect a removal condition requiring the structure, the hardstanding and the signage to be taken away and the land restored within a stated period, commonly one to three months after the use ends, in accordance with the approved landscaping scheme. Where the suite stands on a future plot, the condition should also require that plot to be built out to the approved drawings.
Ask about the Community Infrastructure Levy position before you submit. The treatment of a temporary building depends on the regulations and the charging schedule, and the collecting authority will tell you how it applies on that site rather than leaving you to guess.
Effect on the approved phasing
Look at the approved phasing plan before choosing a location, because the suite usually occupies something the permission has already committed.
Check whether the chosen position sits on an approved plot, on open space or play space provision, on the attenuation basin, on a habitat parcel in the gain plan, within a tree protection area, on the route of a foul rising main, or across the line of a phase boundary. Any of those needs resolving, and the resolution may be a minor amendment to the phasing drawing.
Where the change is more than minor, a variation under section 73 is the route, and the evidence approach is the same as in our note on evidence for a section 73 application. Where visitor and construction movements interact, update the construction management plan rather than leaving the two arrangements to be reconciled on site.
The submission
For a temporary marketing suite on a consented site, the pack is short:
- A site location plan and a block plan showing the suite, parking, the visitor access route, hoarding and signage positions.
- Elevations and floor plans of the suite, with the finish and colour stated.
- A planning statement setting out the temporary nature, the duration proposed, the removal arrangements and the relationship to the approved phasing.
- A drainage note covering foul and surface water for the temporary period.
- A lighting note where anything is illuminated.
- A short transport and parking note with the visitor numbers expected at peak.
Propose the duration and the removal wording yourself. An authority that receives a sensible condition set with the application usually grants it, and you avoid the common outcome of a 12 month permission on a scheme that takes four years to sell out. A planning statement that deals with the end state as carefully as the opening does is what makes that happen.
This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it.
PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
Does Part 4 Class A cover a marketing suite?
Usually not. The right covers buildings and structures required temporarily in connection with building operations, which means site accommodation for the construction work. A sales suite open to the public is a commercial use, and most authorities treat it as needing its own temporary planning permission under section 72.
Can a show home be used as a sales office?
The dwelling is already permitted but the sales use is not. Either apply for a temporary change of use, or ask for a condition on the main permission allowing the plot to be used as a sales office until a stated trigger, after which it reverts to residential use. Agreeing that early avoids a later application.
Do the signs need separate consent?
Often yes. Advertisement control is a separate regime under the 2007 Regulations, and planning permission for the suite carries no consent for signage. Deemed consent classes cover sale boards and, within limits, flags on a housing site, but a run of illuminated totems or a feature entrance wall needs express consent.
How long will a temporary permission last?
Either a fixed period, often three years, or a trigger tied to the development such as occupation of the final dwelling. The trigger form suits a slow selling scheme better and is frequently accepted, though some authorities prefer a date because it is simpler to enforce.
What phasing conflicts should be checked first?
Whether the chosen position sits on an approved plot, on open or play space provision, on the attenuation basin, on a habitat parcel in the biodiversity gain plan, within a tree root protection area or across a phase boundary. A habitat parcel is the worst case, because that land is committed for 30 years.
Sources and further reading
- Town and Country Planning (General Permitted Development) (England) Order 2015, Schedule 2
- Town and Country Planning (Control of Advertisements) (England) Regulations 2007
- Town and Country Planning Act 1990, section 72
- Construction (Design and Management) Regulations 2015
- Planning Practice Guidance: use of planning conditions
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.