Under Part 6 the council can only refuse the siting, design and external appearance you proposed. The permitted development right survives, so a revised set of details usually beats an appeal.

A determination that prior approval is required, followed by a refusal of that approval, does not take away the right to put up the building. Part 6 of Schedule 2 to the General Permitted Development Order 2015 still grants permission for agricultural development that meets the class limits. What the council has refused is the siting, design and external appearance you proposed, and those are the only things it can refuse. So the next move is a revised set of details, not a planning application, and in most cases that revision can be submitted straight away.

What the council may and may not consider

Where agricultural development under Part 6 involves erecting, extending or altering a building, or forming or altering a private way, the developer must first apply to the authority for a determination as to whether its prior approval is needed. For a building the approval covers siting, design and external appearance. For a private way it covers siting and means of construction. That is the whole of the authority's jurisdiction at this stage.

What falls outside it is a longer list than most applicants realise. Agricultural need in the business sense, highway capacity, noise from the operation, odour, traffic generation, loss of residential amenity, landscape policy in the local plan and the merits of the enterprise are not matters for the determination. Objections raising them are not irrelevant to the officer's life, but they cannot lawfully found a refusal of prior approval.

There is a separate and prior question, which is whether the development is permitted development at all. That turns on the class conditions rather than on the authority's discretion: whether the land is an agricultural unit of the required size, whether the development is reasonably necessary for the purposes of agriculture on that unit, and whether the proposal falls within the limits on ground area, height, proximity to a classified or trunk road and, for livestock buildings and slurry storage, distance from a protected building. Check the current figures in the Order text, because the limits have been amended.

If the authority says the development is not permitted development at all, that is a different decision with different consequences, and the answer may be a lawful development certificate under section 192 of the Town and Country Planning Act 1990 rather than a revised design.

Why a refusal is not a refusal of the building

The permitted development right comes from the Order. Prior approval is a control over how the right is exercised rather than a gateway to the right itself. Refuse the details and the right remains, unexercised.

That distinction has practical value. You do not need to demonstrate agricultural need afresh. You do not reopen the question of whether a building is acceptable in principle in that location. You are negotiating about where exactly it sits, how it is shaped and what colour it is.

It also sets the limits of what a revision has to achieve. If the refusal says the building would be prominent in views from the lane and the cladding colour would stand out against the woodland backdrop, those are the two things to fix. A redesign that also reduces the floor area, changes the roof form and relocates the access is wasted effort and invites a fresh set of comments.

Read the decision notice closely. A well written refusal identifies siting, design or appearance specifically. A poorly written one recites objections about traffic and smell, and if that is what you have, say so in the covering letter to the resubmission and ask the officer to address the matters within the determination.

Resubmitting with amended siting

Refusal ground What usually resolves it
Prominent siting in open views Move the building to sit against existing buildings or a mature hedge line, or cut it into the slope
Scale and bulk out of keeping Lower the eaves, reduce the ridge by shallowing the pitch, break the mass with a lower lean to bay
Cladding and roof colour Dark grey or olive profiled sheeting, matt finish, dark grey roof rather than light or galvanised
Appearance on the approach Reorient the gable away from the public view and plant a native hedge along the exposed boundary
Private way alignment and construction Follow a field boundary rather than cutting across, and use a bound surface only where necessary

Siting is the ground most often cited and the easiest to resolve, because the farm usually has somewhere better. Grouping with the existing farmstead almost always helps, and a building seen against other buildings reads very differently from the same building standing alone in a field.

Where siting cannot move for operational reasons, say why in plain terms. Slurry storage has to sit downhill of the parlour. A grain store has to be reachable by an articulated lorry. Officers accept operational constraints when they are explained, and reject them when they are asserted.

Levels work matters too. Cutting a building half a metre into a slope removes more visual impact than any amount of planting, and it costs less than relocating.

Appeal rights and the timetable

A refusal of prior approval carries a right of appeal to the Planning Inspectorate under section 78 of the 1990 Act. The appeal is against the refusal of approval of the prescribed details, so the inspector decides siting, design and external appearance and nothing wider.

The practical point is timing. A resubmission is quicker and costs less than an appeal in nearly every case, because the authority has 28 days to notify whether prior approval is required and the whole process is measured in weeks rather than months. Appeal where the authority is refusing on grounds outside its jurisdiction and will not change position, where the siting the business needs is the siting that was refused, or where the real dispute is whether the development is permitted development at all.

Watch the deadline. Appeals against refusal of prior approval are not householder appeals, so the shorter householder timetable does not apply, and the general period for lodging an appeal runs from the date of the decision notice. Check the current deadline on the Planning Inspectorate's appeals guidance before relying on a remembered figure.

Design information that avoids a determination

The best outcome is an authority that decides prior approval is not required at all. That happens when the submitted information leaves nothing to worry about.

  1. A site plan showing the building in context, with the existing farmstead, field boundaries, the public highway and any dwelling within the relevant distance marked and measured.
  2. Elevations and a section with eaves and ridge heights dimensioned, and the existing ground profile drawn through the building.
  3. A materials schedule naming the profile, finish and colour reference for walls and roof, with the colour reference stated rather than described.
  4. Two or three photographs from the nearest public viewpoints, with the building outline sketched on, which does more than any paragraph of text.
  5. A short statement explaining the agricultural purpose, the unit area, and how the proposal sits within the class limits.
  6. Where planting is proposed, a drawing showing species and positions rather than a promise.

Keep that pack to a handful of sheets. A Planning Statement is not required for a Part 6 notification and a long one can prompt questions the officer would not otherwise have asked. Where a real landscape sensitivity exists, a short Landscape and Visual Impact Assessment focused on the chosen viewpoints is more persuasive than a full assessment.

Material choice deserves its own thought. The same reasoning that governs rendering and cladding under the householder classes applies here. A finish that reads as recessive in the particular landscape beats one that merely matches the neighbouring shed.

Access, highway comments and record keeping

Highway authorities comment on Part 6 notifications and sometimes object. Their comments on visibility splays and the suitability of an access are not matters the determination can turn on, unless the private way itself is the development, in which case siting and means of construction are in scope.

Treat highway comments as useful intelligence rather than as a refusal ground. If the access needs work, that is a separate conversation about the highway authority's own consents, and resolving it voluntarily removes the loudest objection from the file.

Keep records for the holding. The agricultural unit area and its boundaries. The dates and ground areas of every building erected under Part 6 in the last two years, since aggregation rules can bring a new building outside the class. The agricultural use of each building and the date it started, which matters for any later conversion. The determination applications, decisions and approved drawings, filed together. And photographs of the completed building.

That file is worth more than it looks. It answers an enforcement query in a morning, it supports a later lawful development certificate, and it is the first thing a buyer's solicitor asks for. You can also check which reports a farm project is likely to need before deciding how much supporting material to prepare. This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What can a council consider on an agricultural prior notification?

For a building, only the siting, design and external appearance. For a private way, only the siting and means of construction. Agricultural need in a business sense, highway capacity, noise, odour, traffic and residential amenity fall outside the determination and cannot lawfully found a refusal of prior approval, however often objectors raise them.

Does a refusal of prior approval stop me building?

It stops you building what you proposed. The permitted development right comes from the Order rather than from the authority, so the right survives the refusal unexercised. Submit revised details addressing the specific siting, design or appearance grounds given, and you do not have to re-establish that a building is acceptable in principle.

Should I appeal or resubmit after a refusal?

Resubmit in most cases, because the authority has 28 days to respond and the whole process runs in weeks. Appeal where the refusal rests on grounds outside the authority's jurisdiction and it will not move, where the siting the business needs is the siting refused, or where the real dispute is whether the development is permitted development at all.

What usually fixes a refusal on siting?

Grouping the building with the existing farmstead or against a mature hedge line, and cutting it into a slope where the ground falls. A building seen against other buildings reads very differently from the same building alone in a field. Half a metre of excavation removes more visual impact than any amount of new planting.

What colour cladding do officers accept on farm buildings?

Dark, matt, recessive finishes in profiled sheeting, typically dark grey or olive for walls with a dark grey roof. Name the colour reference in a materials schedule rather than describing it, because an unspecified colour invites a condition or a refusal. Light and galvanised finishes are the ones most often objected to in open landscapes.

How do I avoid prior approval being required at all?

Submit enough information that there is nothing left to worry about: a site plan with measured distances, dimensioned elevations and a section through existing ground, a materials schedule with colour references, photographs from the nearest public viewpoints with the building outline sketched on, and a short statement of agricultural purpose and unit area.

Sources and further reading

part 6agricultural buildingsprior approvalpermitted developmentrural planningappeals

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Permitted Development

View all →
Permitted Development7 min read

A householder extension built over a public sewer

Permitted development rights say nothing about drains. If a public sewer runs under the garden, the water company has a separate say, and foundations are the expensive part.

Read article →
Permitted Development7 min read

Extending a home created by a commercial conversion

A dwelling created by prior approval does not automatically arrive with householder permitted development rights. Flats have none, and the date tests run from when the building was built.

Read article →
Permitted Development9 min read

Permitted development where an earlier permission conditions the site

A rear extension can sit well within Class A and still be unlawful, because a condition on the permission that created the house says otherwise. How Article 3(4) works in practice.

Read article →
Permitted Development7 min read

Hard standing, plant and storage at an industrial unit

Part 7 of Schedule 2 covers hard surfaces, plant and private ways at industrial premises. Article 3(4) removes those rights where the original permission carries a condition, which is where most disputes begin.

Read article →
Permitted Development8 min read

Shopfronts, signs and the consents a new occupier needs

Planning permission, advertisement consent and listed building consent are three separate regimes with different tests. Sequencing them correctly is what protects a shop fit out programme.

Read article →
Permitted Development6 min read

Water and sewerage undertaker works near your site

Schedule 2 to the GPDO grants undertakers wide rights for water and sewerage works, so planning objections go nowhere. What to do instead, and where an application is still needed.

Read article →