Permitted Development

Hard standing, plant and storage at an industrial unit

7 min readBy PlanScope Editorial Team

Part 7 of Schedule 2 covers hard surfaces, plant and private ways at industrial premises. Article 3(4) removes those rights where the original permission carries a condition, which is where most disputes begin.

Most of what an industrial occupier wants to do in a yard is permitted development, and most of it is still caught by something else. Part 7 of Schedule 2 to the General Permitted Development Order 2015 gives industrial and warehouse premises rights to extend, to lay a hard surface, to install plant and to form private ways within the site. Article 3(4) of the same Order then removes those rights wherever the work would breach a condition on the planning permission that created the unit. That is where nearly every dispute starts, so read the original permission before reading the Order.

What the relevant Part allows at industrial premises

Part 7 contains the non-domestic rights. The classes relevant to a working industrial estate cover extensions and alterations to an industrial building or warehouse, and development on industrial land for the purposes of the undertaking: hard surfaces, plant and machinery, private ways, private railways and sidings, sewers and drains.

Read the class text in the Order itself rather than a summary. Part 7 has been amended repeatedly, the class letters have moved, and the conditions attached to each class are where the limits actually sit. Three features run through all of them.

The right belongs to the industrial undertaker for the purposes of the undertaking carried on there. A landlord cannot use it speculatively, and a hard surface laid for a different business is outside the class. The rights do not apply on article 2(3) land, which means conservation areas, National Parks, National Landscapes, the Broads and World Heritage Sites. And the works must not involve a change of use, which is the limit people trip over most often.

Floorspace and height limits on plant

Extensions are capped twice over, in absolute floorspace and as a proportion of the original building, and the height of an extension cannot exceed the height of the building it extends. Those caps run from the building as originally built rather than as it stands today, so a unit extended by a previous occupier may have no headroom left.

Plant and machinery on industrial land has its own allowance, with a height limit of 15 metres above ground level or the height of the plant it replaces, whichever is the greater. Check the current figure in the Order before relying on it, because this is one of the limits amendments have touched.

Item What usually governs it
Building extension Part 7 floorspace cap, proportion of the original building, height of existing building, distance from boundary
Dust extraction or process plant Plant height allowance, plus noise and air quality assessment in practice
Chiller, condenser or air handling unit Plant allowance if within the undertaking, with acoustic screening usually needed
Silo or tank Plant allowance by height, with bunding and pollution control separately regulated
Hard surface in the yard Industrial land class, with surface water drainage the practical constraint

A plant enclosure built to screen the unit is a building rather than plant, which changes the class it has to fit. The same distinction causes trouble at domestic scale, where a plant enclosure is treated differently from the plant inside it, and the logic is identical on an industrial site.

External storage and open yard use

This is the single most misunderstood point on an industrial estate. Laying a hard surface under a permitted development right does not authorise storing anything on it.

Open storage ancillary to the lawful use of the unit is normally within the planning unit's existing use, so stacking pallets of your own finished goods outside the roller shutter is usually fine. Storage that changes the character of the site is not. Racking a yard three metres high, taking in goods for third parties, parking plant for hire, or turning a service yard into an open storage compound can all amount to a material change of use needing permission.

Two tests help. First, is the storage incidental to the activity inside the building, or has it become an activity in its own right? Second, has the intensity or the visual character of the site changed in a way a neighbour would notice? If the answer to the second is yes, expect a planning contravention notice rather than a polite letter.

Check the original permission for a condition on external storage. Conditions limiting storage to a defined area, to a maximum height, or prohibiting it outside the building are extremely common on industrial estates granted permission in the last thirty years, and Article 3(4) means such a condition switches off the permitted development right rather than merely sitting alongside it.

Boundary distances and residential neighbours

Distance from the boundary is a hard limit in the extension classes and a practical limit everywhere else. Where industrial land adjoins residential curtilage, the yard is where the complaints come from, and the planning position follows the environmental one.

Think about the operation from the boundary inwards. Where is the plant, and does it face the housing or the estate road? Where do lorries reverse, and does the beeper carry over a fence? Which part of the yard is lit at 5am? A layout that puts the quiet activities against the sensitive boundary and the noisy ones against another industrial unit will survive scrutiny that an identical layout, mirrored, will not.

Trees and planting on the boundary are worth protecting rather than clearing. A hedge that nobody values until it is gone becomes the first paragraph of every objection letter afterwards.

Noise, lighting and drainage consequences

Permitted development is not a shield against environmental law. Statutory nuisance powers under the Environmental Protection Act 1990 apply to noise, dust, odour and artificial light from industrial premises regardless of whether the works needed permission. Environmental permitting may apply to the process itself.

New plant should be specified against a target rather than installed and then silenced. A Noise Impact Assessment using BS 4142:2014+A1:2019 compares the rating level of the specific sound against the measured background at the nearest sensitive receptor, and the night time background is what sets the specification. Doing this before purchase costs a fraction of retrofitting attenuation afterwards, which is the same argument that applies to domestic air conditioning units and the rights that cover them.

Drainage is the sleeper issue with hard surfacing. Replacing a gravel yard with impermeable concrete increases run-off, and the lead local flood authority, the sewerage undertaker or the Environment Agency may all have an interest. Where a yard is used for vehicle movements or storage of oils and chemicals, interceptors and a pollution incident response plan matter as much as the attenuation volume. A Drainage Strategy is worth preparing even where no application is needed, because it is the document that answers the undertaker's question about discharge rates.

Lighting is easy to get wrong and expensive to put right. Floodlights aimed horizontally across a yard put light into first floor windows two hundred metres away, and the fix is a different fitting rather than a different timer.

Conditions on the existing permission

Pull the original permission and every subsequent approval before you plan any work. Look for conditions on hours of operation, vehicle movements, external storage, plant and machinery requiring prior written approval, lighting, surfacing materials, landscaping to be retained, and restrictions on the use of the building to a named class or a named occupier.

Where a condition blocks something you need, the route is an application under section 73 of the Town and Country Planning Act 1990 to vary or remove it, which is determined on the merits of that condition alone rather than reopening the whole permission. Where the condition is unenforceable or imprecise, say so in the application and explain why, because an authority is often content to replace an old condition with a better drafted one.

An Article 4 direction can also remove Part 7 rights across an area. It is rare on industrial land and not unknown near housing, so check the constraint layer rather than assuming.

PlanScope can draft the Planning Statement and supporting documents for a yard or plant application from your site details and answers, and you can see which reports the proposal is likely to need before briefing anyone. This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Can I lay a hard surface in my industrial yard without permission?

Often yes. Part 7 of Schedule 2 to the General Permitted Development Order 2015 includes a right to provide a hard surface on industrial land for the purposes of the undertaking carried on there. The right does not apply on article 2(3) land, and Article 3(4) removes it where a condition on the planning permission prohibits or controls surfacing.

Does a hard surface right allow me to store goods on it?

No. Laying the surface and using it are separate questions. Storage incidental to the activity inside the building is normally within the lawful use, but racking a yard, taking in third party goods or creating an open storage compound can be a material change of use requiring permission, and may breach an existing condition.

How high can plant and machinery be under permitted development?

The industrial land class in Part 7 allows plant and machinery subject to a height limit of 15 metres above ground level, or the height of the plant it replaces where that is greater. Check the current figure in the Order before relying on it. A structure built to enclose plant is a building rather than plant and is assessed under a different class.

What does Article 3(4) of the GPDO actually do?

It provides that the permissions granted by Schedule 2 do not apply where the development would be contrary to a condition imposed on a planning permission granted otherwise than by the Order. In practice a condition on the original industrial permission controlling storage, plant, lighting or surfacing switches off the corresponding permitted development right entirely.

Can I remove an old condition that blocks the work?

Yes, by an application under section 73 of the Town and Country Planning Act 1990 to vary or remove the condition. The authority considers that condition on its merits rather than reopening the permission as a whole. Where the wording is imprecise or unenforceable, say so and offer a better drafted replacement.

Do I need a noise assessment for new plant if no permission is needed?

Not as a planning requirement, but the statutory nuisance provisions of the Environmental Protection Act 1990 still apply. Specifying plant against a BS 4142 target measured from the night time background at the nearest sensitive receptor costs far less than retrofitting attenuation after a complaint, and gives you a defence if one arrives.

Sources and further reading

permitted developmentindustrialexternal storageplantnoisedrainage

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Permitted Development

View all →
Permitted Development9 min read

Permitted development where an earlier permission conditions the site

A rear extension can sit well within Class A and still be unlawful, because a condition on the permission that created the house says otherwise. How Article 3(4) works in practice.

Read article →
Permitted Development8 min read

Agricultural prior approval refused on siting or design

Under Part 6 the council can only refuse the siting, design and external appearance you proposed. The permitted development right survives, so a revised set of details usually beats an appeal.

Read article →
Permitted Development8 min read

Shopfronts, signs and the consents a new occupier needs

Planning permission, advertisement consent and listed building consent are three separate regimes with different tests. Sequencing them correctly is what protects a shop fit out programme.

Read article →
Permitted Development6 min read

Water and sewerage undertaker works near your site

Schedule 2 to the GPDO grants undertakers wide rights for water and sewerage works, so planning objections go nowhere. What to do instead, and where an application is still needed.

Read article →
Permitted Development7 min read

Permitted development before the new house is finished

On a self-build plot the permitted development allowance only exists once the house does. What substantial completion means, which conditions remove the rights, and when to vary the permission instead.

Read article →
Permitted Development6 min read

Permitted development that needs a habitats assessment

Where development granted by the GPDO is likely to have a significant effect on a habitats site, it cannot begin until the authority has approved it. What that means for prior approval timetables and nutrient budgets.

Read article →