Water and sewerage undertaker works near your site
Schedule 2 to the GPDO grants undertakers wide rights for water and sewerage works, so planning objections go nowhere. What to do instead, and where an application is still needed.
Most water and sewerage work near a development site proceeds without a planning application, because Schedule 2 to the General Permitted Development Order grants undertaker permitted development works rights to statutory undertakers for water and sewerage purposes. That is why a trench appears across the frontage of your site with no notice on a lamp post and nothing on the planning register. It is also why objecting through the planning system is usually the wrong channel.
What you can do is find out what is planned, understand which powers the undertaker is using, and coordinate your own programme around it. On a site where a connection, a diversion or an easement is needed, that coordination is worth more than any objection would be.
What the Order permits
The water and sewerage Part of Schedule 2 grants rights for the laying, inspection, repair, renewal and removal of mains, pipes, cables and other apparatus, together with associated excavation, and for certain operational development on an undertaker's own operational land within stated limits. Check the current contents of Schedule 2 on legislation.gov.uk, because the Parts have been amended and renumbered over time.
Two limits matter.
The rights are tied to the undertaker's statutory functions. Development that is not for the purposes of the undertaking does not benefit.
Size and cost thresholds apply to buildings and structures, so a significant extension to a treatment works, a new pumping station above a stated scale, or a storage reservoir will need a planning application in the normal way.
Separate Parts of Schedule 2 deal with other utilities, and the detail differs between them, so do not assume the water position applies to electricity or telecommunications apparatus.
Works you cannot object to through planning
Where the Order grants the permission, there is no application, no publicity and no decision to object to. Three practical consequences.
The authority has no power to impose planning conditions on works carried out under the Order. Reinstatement standards come from the street works regime and the highway authority, not from planning.
Representations about noise, hours of working or traffic management go to the undertaker and, where appropriate, to the highway authority or the council's environmental health team under their own powers. The council can take action on statutory nuisance independently of planning.
An environmental permit or consent from the environment regulator may still be required for a discharge or for works in or near a watercourse, and that is a separate process with its own publicity in some cases.
So the useful questions are not about planning at all. They are about programme, apparatus location and whether the work affects your own connection strategy.
Land acquisition and easements
Undertakers have statutory powers to acquire land and rights, and in practice most apparatus sits under an easement rather than on land the undertaker owns.
For a developer, three issues arise.
An existing easement strip across your site constrains where you can build, and the constraint usually extends several metres either side of the apparatus. Check the title and the undertaker's asset records, because the two do not always agree.
Building over or near a public sewer requires the undertaker's agreement under its own procedures, which sit alongside the Building Regulations rather than inside the planning system. Start that conversation early, because a refusal will move your building line.
Where apparatus has to move, the Water Industry Act 1991 provides a route for a developer to require a water main or sewer to be diverted, at the developer's cost. Budget it properly. Diversions of large diameter mains are slow and expensive, and the programme is set by the undertaker rather than by you.
Trees, access and reinstatement
Three recurring points of friction on development sites.
Trees over apparatus. An easement strip prevents planting within it, and the undertaker's rights of access can override landscaping intentions. Where a tree is already present and protected, works affecting it need care, because undertakers' statutory rights and tree protection controls interact in ways worth checking before a chainsaw arrives. A Tree Survey to BS 5837:2012 should record the easement strip alongside root protection areas, so the conflict is visible on the constraints plan rather than discovered on site.
Access for maintenance. Permanent access to chambers, valves and pumping stations has to be designed in. A scheme that puts a manhole inside a private rear garden with no gate creates a problem for the next 60 years.
Reinstatement. Where the work is in the highway, the street works regime sets reinstatement standards and guarantee periods, and the highway authority inspects. Where it is on your land, the terms of the access agreement govern, so write the standard into it rather than relying on an assurance.
Coordinating your programme with theirs
A sequence that works on a site where undertaker works are in prospect.
- Ask each undertaker for asset plans at the feasibility stage, and ask specifically whether any scheme is programmed in the area.
- Establish the connection route for foul and surface water early, and get it into the Drainage Strategy rather than leaving it to the contractor.
- Where capacity is the issue, raise it formally. The Water Industry Act 1991 provides routes for requisitioning a sewer or water main where capacity is lacking, and for the adoption of new sewers by agreement.
- Where a diversion is needed, start the application with the undertaker before planning submission, because the design will affect the layout.
- Record the connection position in a Foul Sewage Assessment with the dates of the correspondence, because a capacity answer given two years ago may no longer hold.
One naming trap to avoid. The right to connect to a public sewer sits in section 106 of the Water Industry Act 1991, which has nothing to do with the planning obligations in section 106 of the Town and Country Planning Act 1990. Write the Act out in full in correspondence, because the confusion is common and the consequences of acting on the wrong one are real.
Where an application is still required
The main cases, in rough order of frequency.
New or substantially extended treatment works and pumping stations above the scale the Order permits. Development on land that is not operational land of the undertaking. Schemes requiring environmental impact assessment, where the screening outcome removes the benefit of the Order. Works affecting a habitats site, where a separate approval is needed before development can begin. And anything the undertaker chooses to apply for because it wants the certainty of a permission.
Where an application does come forward, it is determined like any other, and a Utilities Assessment or other technical evidence may be part of the submission. That is also the point at which the publicity requirements apply and representations go to the planning authority.
Raising concerns through the right channel
Match the concern to the body with the power.
- Programme, working hours, plant noise and reinstatement on site: the undertaker, in writing, with photographs and dates.
- Traffic management, road closures and reinstatement in the highway: the highway authority.
- Statutory nuisance from noise, dust or odour: the council's environmental health team.
- Discharges to watercourses and works in a flood risk area: the environment regulator.
- Anything that does require planning permission and is proceeding without it: the planning authority's enforcement team.
A complaint sent to the right body with a date, a location and a photograph gets a response. The same complaint sent to the planning department about works permitted by the Order does not.
This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it.
Frequently asked questions
Why was there no planning application for the works outside my site?
Because the water and sewerage Part of Schedule 2 to the General Permitted Development Order grants statutory undertakers permission for laying, inspecting, repairing, renewing and removing apparatus and associated excavation. Where the Order grants the permission there is no application, no publicity and no decision to object to.
Can the council impose conditions on undertaker works?
Not where the works are permitted by the Order. Reinstatement standards and working arrangements in the highway come from the street works regime and the highway authority. The council can still act on statutory nuisance through environmental health powers, and the environment regulator controls discharges separately.
Who pays to divert a sewer or water main?
The developer, where the diversion is required to enable development. The Water Industry Act 1991 provides the route, and the undertaker controls the design and the programme. Price it at feasibility stage, because diversions of larger mains are slow and the cost can change a scheme's viability.
What is the difference between the two section 106s?
Section 106 of the Water Industry Act 1991 is the right to connect to a public sewer. Section 106 of the Town and Country Planning Act 1990 is the planning obligation. They are unrelated, and the confusion causes real problems in correspondence, so write the Act out in full every time.
When does an undertaker need planning permission?
For buildings and structures above the scale the Order permits, for development on land that is not operational land of the undertaking, for schemes requiring environmental impact assessment, and where a habitats assessment is needed before development can begin. Some undertakers also apply voluntarily for certainty.