Deliveries and routing in a construction traffic plan

7 min readBy PlanScope Editorial Team

A routing section that promises to use the primary network where practicable will be returned. Name the roads, give the peak vehicle numbers, and say how a breach is handled.

The routing section of a construction traffic management plan has to name the roads vehicles will use, say how many vehicles of what type will use them, and show how a driver who gets it wrong will be prevented from repeating it. A deliveries routing construction traffic management plan that says heavy goods vehicles "will use the primary road network where practicable" does not discharge the condition, and highway officers return it.

The plan is normally secured by a pre-commencement condition, so an inadequate submission stops the job rather than delaying a report.

What the routing section has to settle

Six things, each capable of being checked on the ground:

  • The agreed route from the strategic or primary road network to the site access, named road by road.
  • The reverse route for departing vehicles, which is often different because of turning restrictions.
  • The prohibited roads, listed explicitly, with the reason.
  • The number of vehicle movements by type and by phase, with a daily and weekly profile.
  • The permitted delivery hours, and any narrower windows near sensitive receptors.
  • How the route will be communicated to every driver and subcontractor, and what happens when it is breached.

The last item is where plans are weakest. A route that exists only in the plan is a route the authority cannot enforce, so include the driver briefing document, the signage at the site entrance, and the contractual mechanism applied to a haulier who ignores it.

Agreeing the route with the highway authority

The local highway authority is the consultee that matters, and on anything touching the strategic road network National Highways will be involved as well, applying its own approach to development affecting trunk roads and motorways.

Start the conversation before the application is determined, not after the condition is imposed. Highway officers know which bridges have weight restrictions, which junctions are on the school run, which residential streets have been the subject of complaints, and which routes the authority has already agreed for other sites nearby. That knowledge is not available from a desk study.

Bring three things to that meeting: a route plan at a legible scale, a vehicle schedule, and a swept path drawing for the site access. Those are the documents that let an officer agree or object with reasons.

Where several schemes are building at once, expect the authority to raise cumulative effects and to want the routes separated or the timings staggered.

Vehicle numbers, types and the daily profile

Give real numbers. The authority is assessing effect, and effect is a function of how many vehicles arrive and when.

Phase Typical dominant vehicle What to state
Demolition and site clearance Tippers and grab lorries Loads per day, duration in weeks
Earthworks and muckaway Articulated tippers Volume to remove, loads per day, peak week
Substructure Concrete mixers and pumps Pour dates, number of mixers per pour
Superstructure Flatbeds and crane lifts Deliveries per day, any road closures for lifts
Fit-out Rigid lorries and vans Deliveries per day, van parking demand
Landscaping and completion Tippers and vans Loads per day, duration

Two refinements make the profile credible. State the peak, not the average, because the peak is what the neighbours experience and what the junction has to accommodate. And state the duration of the peak, because a fortnight of muckaway is a different proposition to six months.

Concrete pours deserve their own paragraph. A large pour brings mixers at short intervals over several hours, and a holding arrangement is needed so that waiting vehicles do not queue on the public highway.

Access, turning and swept paths

The site access is where most objections are founded. Three drawings answer them.

  1. A swept path analysis for the largest vehicle entering and leaving, showing the vehicle can do so in forward gear where the frontage is onto a classified road.
  2. A visibility splay drawing for the access, measured against stopping sight distance for the road's speed using the method in Manual for Streets.
  3. A site layout showing the internal holding area, the turning head, and the position of the wheel wash relative to the exit.

Internal holding capacity is the item that gets cut from a tight site and then causes the complaints. Calculate it from the peak arrival rate rather than from the space available, and if the numbers do not fit, book deliveries to a timed slot system and say so in the plan.

Where the access works themselves affect the public highway, a separate agreement under section 278 of the Highways Act 1980 will be needed, and that has its own programme. Temporary works in the highway, scaffolding and material storage need licences under sections 169 and 171.

Wheel washing, sheeting and road cleanliness

Depositing mud on the highway is an offence, and the authority has powers to require it to be removed. The plan should commit to the method rather than the aspiration.

Specify the wheel wash type, its position far enough inside the site that a cleaned vehicle does not cross dirty ground before exiting, the water supply and the silt disposal arrangement. Add a road sweeper, with a stated frequency and a trigger for additional sweeps in wet weather. Commit to sheeting all loads of loose material, which also serves the dust control commitments in the construction environmental management documents, as set out in our note on the construction dust section of an air quality report.

Highway condition is the other half of this. Carry out a joint condition survey of the agreed route with the highway authority before works start, with photographs and a dated record. Section 59 of the Highways Act 1980 allows a highway authority to recover the cost of damage caused by extraordinary traffic, and the pre-start survey is what keeps that discussion factual.

Timing restrictions near schools and houses

Delivery hours are usually conditioned as a window, commonly starting after the morning peak and ending before the evening one on weekdays, with shorter Saturday hours and no Sunday or bank holiday deliveries.

Where the route passes a school, expect a narrower restriction around the start and end of the school day, and expect it to be enforced. Where the route passes a hospital, a care home or a residential street with on-street parking on both sides, the same logic applies with different hours.

An illustrative example. A 90 unit scheme with a single access onto a B road, 400 metres from a primary school on the only sensible approach. The agreed arrangement: deliveries between 9.30am and 2.30pm and 3.45pm and 5pm on weekdays, no deliveries during the 8.30am to 9.15am and 3pm to 3.45pm school periods, an eight-vehicle internal holding area, a timed booking system during the eight week muckaway peak, and a banksman at the access throughout. The restriction costs the contractor productive hours, and it is the reason the condition was discharged first time.

Monitoring and complaints

A plan without a monitoring commitment is a statement of intent. Include a named site contact with a telephone number displayed at the entrance and notified to neighbouring occupiers, a complaints log with response times, and a reporting arrangement to the authority at an agreed interval.

Many contractors also register with a considerate constructors style scheme and commit to recognised logistics and fleet safety standards, which gives the authority an external reference point. Say which standards apply and to whom, because a commitment that binds only the principal contractor and not the hauliers is of limited use.

Then keep the log. The discharge of a condition is a one-off event, but the plan governs the site for its whole duration, and a breach recorded by a resident is the start of an enforcement enquiry.

Submit the Construction Traffic Management Plan and the wider Construction Management Plan together where both are conditioned, cross-referenced rather than duplicated. The traffic figures should also match those used in the Transport Assessment submitted with the application, because an officer will compare them.

Agree the route before you price the groundworks. A prohibited road discovered late changes the haulage cost on every load.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What must a construction traffic routing section contain?

The agreed route named road by road, the reverse route for departures, the prohibited roads with reasons, vehicle movements by type and phase with a daily and weekly profile, the permitted delivery hours, and how the route will be communicated to every driver and subcontractor along with the consequence of a breach.

Who agrees the construction route?

The local highway authority, with National Highways involved where the strategic road network is affected. Start the discussion before the application is determined rather than after the condition is imposed, because highway officers know the weight restrictions, school run junctions and routes already agreed for nearby sites.

Should the plan state average or peak vehicle numbers?

Both, but the peak matters most. The peak is what the junction has to accommodate and what neighbours experience, so state it alongside how long it lasts. A fortnight of muckaway at peak rate is a very different proposition from six months, and the authority assesses effect rather than totals.

Why does a joint highway condition survey matter?

Section 59 of the Highways Act 1980 allows a highway authority to recover the cost of damage caused by extraordinary traffic. A photographed, dated condition survey of the agreed route carried out jointly before works start keeps any later discussion factual rather than contested, and it costs very little to do.

What delivery hours are typically conditioned?

Usually a weekday window starting after the morning peak and ending before the evening one, with shorter Saturday hours and no Sunday or bank holiday deliveries. Where the route passes a school, expect narrower exclusions around the start and end of the school day, and expect those to be enforced.

Sources and further reading

construction trafficctmphighwaysplanning conditionsdeliveriesswept path

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Report Deep Dives

View all →
Report Deep Dives6 min read

Population equivalent in a Foul Sewage Assessment

Population equivalent sets the design load for every other figure in a Foul Sewage Assessment. Here is how to build it, convert it to flow, and use it in a capacity enquiry.

Read article →
Report Deep Dives7 min read

Specifying odour abatement in an extraction statement

The abatement specification follows from the odour risk assessment. Cooking type, extract volume and receptor distance set the number of treatment stages needed.

Read article →
Report Deep Dives7 min read

Choosing consultation methods in an SCI

The methods section has to show the consultation could have changed something. That means justifying each method against its audience and reporting what it failed to reach.

Read article →
Report Deep Dives7 min read

Judging significance of effects in an LVIA

Significance of effects in an LVIA is a reasoned judgement built from value, susceptibility and magnitude. Matrices present the conclusions; they do not produce them.

Read article →
Report Deep Dives7 min read

Unregulated emissions in a whole life carbon assessment

Appliances, small power and lifts are not controlled by Part L but still belong in B6. Why figures vary so widely and what a checkable assessment states.

Read article →
Report Deep Dives7 min read

The maintenance section of a landscape strategy

The maintenance section is where a landscape strategy is won or lost. It has to name who does the work, for how long, paid from what, with what happens when planting fails.

Read article →