Specifying odour abatement in an extraction statement
The abatement specification follows from the odour risk assessment. Cooking type, extract volume and receptor distance set the number of treatment stages needed.
The abatement specification in a ventilation and extraction statement follows from an odour risk assessment, not from a product catalogue. Establish the risk level first, from the cooking type, the extract volume and the distance to the nearest sensitive receptor, and the required stages of treatment follow. A statement that specifies a carbon filter without saying why that level of treatment is needed gives the environmental health officer nothing to assess.
Defra's guidance on the control of odour and noise from commercial kitchen exhaust systems is the reference almost every authority works from, and its risk-based structure is what an odour abatement extraction statement should mirror.
How risk determines the stages
The risk assessment combines three things: the type and volume of food cooked, the size of the extract system, and the proximity and sensitivity of receptors. Chargrilling and deep frying generate far more odorous compounds than a sandwich counter. A flue discharging two metres below a flat window is a different proposition from one discharging above a ridge on an isolated building.
Set the three out explicitly and state the resulting risk level. Then the abatement stages are a conclusion rather than an assertion.
| Risk level | Typical abatement |
|---|---|
| Low | Grease filtration, good flue termination, no further treatment |
| Medium | Grease filtration plus one odour treatment stage |
| High | Grease filtration plus two or more treatment stages in series |
An officer reading a high risk assessment with single stage treatment will ask for more. An officer reading a low risk assessment with three stages will usually accept it but may question the fan noise that comes with the pressure drop.
Grease filtration first
Every system starts with mechanical grease removal, because grease carries odour and because downstream treatment fails without it. The canopy filters do the coarse work, and a secondary panel or bag filter stage follows where the risk level warrants it.
Three points belong in the statement: the filter type and efficiency class at each stage, the access arrangement for changing them, and the replacement interval. A carbon bed installed behind a neglected grease filter stops working within weeks, and the authority knows it.
Ductwork cleanliness is part of the same picture. Reference the cleaning standard the operator will work to, and state the inspection interval. Grease accumulation in ductwork is a fire risk as much as an odour one.
Comparing the treatment technologies
Three technologies account for most installations, and they behave differently.
Electrostatic precipitation charges particles and collects them on plates, removing fine grease and smoke particulates efficiently. It has a continuing power demand and needs regular plate washing, and it does little for vapour-phase odour on its own.
Activated carbon adsorbs vapour-phase compounds and is the usual answer to residual odour. Its weakness is capacity: the bed saturates, and performance falls off without warning unless the replacement interval is managed. Specify the bed depth or contact time, the carbon mass, and the replacement regime.
Ultraviolet and ozone systems oxidise odorous compounds in the airstream. They work best in combination with other stages rather than alone, and ozone generation needs careful control because ozone is itself a pollutant. Where ozone is proposed, state the residual control measure.
For a high risk installation, the common arrangement is grease filtration, then electrostatic precipitation for particulates, then carbon for vapour-phase odour, in that order. Putting carbon before particulate removal shortens its life dramatically.
Flue route, termination and dispersion
Dispersion does as much work as treatment, and it costs less to get right at design stage.
The guidance points to high level discharge, with the terminal at least a metre above the ridge of the building it serves and clear of surrounding buildings and openable windows. A flue that stops at eaves level, or discharges into a courtyard, pushes odour towards receptors however good the abatement.
Efflux velocity matters as well. A discharge in the region of 10 to 15 metres per second lifts the plume and promotes mixing, and a low velocity discharge allows it to fall back down the facade. State the design velocity and the terminal type, and avoid cowls that deflect the plume downwards.
Four things to show on the drawings:
- The flue route in plan and section, from canopy to terminal.
- The termination height relative to the ridge and to the nearest openable window on any building within the relevant distance.
- The position of any adjacent flue, intake or plant that could cause re-entrainment.
- The structural fixings and any external appearance consequences, which is the planning rather than the technical question.
On a listed building or in a conservation area the external flue is usually the point of difficulty, and an internal riser to roof level, if one can be found, resolves more objections than any abatement specification.
Fan selection and the noise it brings
Every stage of abatement adds pressure drop, and pressure drop means a bigger fan. That is where the noise comes from.
Expect the authority to assess fan and plant noise against BS 4142:2014+A1:2019, comparing the rating level with the background sound level and applying corrections for tonality and intermittency. Night-time background levels at a residential facade above or beside a restaurant give very little headroom.
Deal with it in the same document: the fan sound power data, the attenuator specification, the duct lagging where ductwork runs past a bedroom, anti-vibration mounts, and the operating hours. The method for establishing the background level is set out in our note on the baseline sound survey chapter of a BS 4142 report, and a separate Noise Impact Assessment is often the cleaner way to present it where the plant is substantial.
Maintenance and access
Abatement that cannot be maintained will not be maintained. The statement should set out the maintenance schedule stage by stage, name the access route to each component, and confirm that the access does not require a scaffold or a road closure.
Include the replacement intervals, the responsible party, and the record keeping. Many authorities condition a maintenance schedule, and offering one that is realistic is better than accepting a condition written by someone who has not seen the plant room.
An illustrative example. A 90 cover restaurant on the ground floor of a converted building with flats above, chargrill and wok cooking, extract volume around 1.5 cubic metres per second, nearest openable window five metres from the proposed flue line. That is a high risk case. The specification is canopy grease filters plus a secondary panel filter, electrostatic precipitation, a carbon bed with stated contact time, an internal riser to a terminal one metre above the ridge, discharge at 12 metres per second, an inline attenuator, and quarterly filter changes with annual carbon replacement. The statement runs to a dozen pages and the application is approvable.
What the submitted statement should contain
A schedule of cooking equipment and the menu type. The design extract volume and the canopy specification. The abatement stages in sequence with performance data. The flue route, termination height and efflux velocity. The fan and noise data with mitigation. The maintenance schedule and replacement intervals. And the risk assessment that justifies the whole chain.
Put that in a Ventilation and Extraction Statement rather than spreading it across a design and access statement and a supplier's leaflet. Where the authority has asked specifically about odour rather than the system, a standalone Odour Assessment addresses the receptor side of the question.
Councils usually expect a suitably qualified author for this work, and professional review before submission is strongly advised.
Settle the flue route before the kitchen layout. A terminal that cannot reach the ridge changes everything downstream of it.
This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required.
Frequently asked questions
How is kitchen odour risk assessed?
By combining the type and volume of food cooked, the size of the extract system, and the proximity and sensitivity of receptors. Chargrilling and deep frying rank high, a sandwich counter low. Defra's guidance on commercial kitchen exhaust systems sets out the risk-based approach, and the resulting level determines how many treatment stages are needed.
What order should abatement stages be installed in?
Grease filtration first, then particulate removal such as electrostatic precipitation, then activated carbon for vapour-phase odour. Putting carbon ahead of particulate removal shortens its life dramatically, and installing any treatment behind a neglected grease filter means it stops working within weeks.
How high should the flue terminate?
At high level, with the terminal at least a metre above the ridge of the building it serves and clear of surrounding buildings and openable windows. A discharge at eaves level or into a courtyard pushes odour towards receptors regardless of the abatement fitted, and no filter specification compensates for it.
Does efflux velocity matter?
Yes. A discharge in the region of 10 to 15 metres per second lifts the plume and promotes mixing, while a low velocity discharge allows it to fall back down the facade. State the design velocity and the terminal type in the statement, and avoid cowls that deflect the plume downwards.
Why does abatement create a noise problem?
Each treatment stage adds pressure drop, which requires a larger fan. Authorities assess plant noise against BS 4142:2014+A1:2019, comparing the rating level with the background sound level and adding corrections for tonality and intermittency. Night-time background levels at a residential facade above a restaurant leave very little headroom.