Greater London Authority referable applications explained
Applications of potential strategic importance under the Mayor of London Order 2008 go to the GLA twice. Six weeks for the Stage 1 report, a fortnight for Stage 2, and the Mayor can direct refusal or take over.
A referable application in London is one that falls within the categories of potential strategic importance in the Town and Country Planning (Mayor of London) Order 2008, and the practical effect is that the borough cannot decide it alone. The Mayor sees it twice: once after validation, when a Stage 1 report says whether the scheme complies with the London Plan, and again before the borough issues its decision, when the Mayor can let the borough proceed, direct refusal or take the application over. Budget six weeks for the first stage and a further fortnight for the second.
Most developers plan for the thresholds and forget the Stage 2 fortnight. It sits at the end, after the committee resolution, when everyone has stopped watching.
Which applications are referable
The Schedule to the 2008 Order is the authoritative list, and you should read it rather than a paraphrase of it. The headline categories are:
- Residential development providing more than 150 houses or flats.
- Development including a building above a floorspace figure that varies by location, with the lowest figure applying outside central London and the City and much higher figures within them.
- Tall buildings, where the trigger height depends on location and on whether the site is adjacent to the River Thames.
- Development on Green Belt or Metropolitan Open Land above stated building and site area thresholds.
- Certain mining, waste and transport development, and development that would prejudice the implementation of the London Plan.
Two traps. The thresholds bite on the application as a whole, so a scheme of 148 flats plus two replacement dwellings is referable. And a section 73 application to vary a referable permission is itself referable, which surprises teams who treat variations as administrative.
Check the category before you fix the programme, because a scheme at 149 units has a materially different timetable from one at 151.
Stage one and stage two in practice
At Stage 1 the borough sends the application to the Greater London Authority shortly after validation. The Mayor then has six weeks to issue a report setting out whether the scheme complies with the London Plan, what would have to change for it to comply, and whether the Mayor is likely to intervene. The borough cannot determine the application until that report is issued or the period expires.
The Stage 1 report is written by GLA planning officers and published. Treat it as the single most useful document you will receive, because it tells you exactly what the Mayor's team will want resolved before Stage 2, and boroughs routinely adopt its conclusions in their own officer report.
At Stage 2 the borough notifies the Mayor of the decision it proposes to make, with its draft reasons, conditions and heads of terms. The Mayor has 14 days to respond with one of three outcomes: allow the borough to determine as it proposes, direct refusal, or take over the application.
The Mayor's direction powers
The power to direct refusal and the power to take over are both constrained, and neither is exercised lightly.
A direction to refuse is available where the borough proposes to grant and the Mayor considers the scheme unacceptable in strategic terms. A takeover requires the Mayor to be satisfied that the development would have a strategic impact on the implementation of the London Plan, that there are sound planning reasons for intervening, and that it is expedient for the Mayor to act as the local planning authority.
Where the Mayor takes over, he becomes the decision maker for that application, holds a public representation hearing and issues the decision himself. The borough's resolution falls away. There is no appeal against a direction to refuse as such, though the applicant retains the usual appeal rights against the refusal that follows.
Takeovers are rare in absolute numbers and concentrated in schemes where housing delivery or affordable housing is the point in dispute.
Timescales the referral adds
A referable scheme is major development, so the statutory determination period is 13 weeks, or 16 weeks for EIA development. In reality almost every referable application runs under a planning performance agreement with an agreed longer programme, because 13 weeks does not accommodate a six week Stage 1, a committee cycle and a 14 day Stage 2.
Sequence it backwards from the committee date:
- Validation, then referral to the Mayor.
- Six weeks to Stage 1.
- Design and documentation changes in response to Stage 1.
- Borough officer report and committee resolution.
- Stage 2 referral, 14 days.
- Section 106 completion, then the decision notice.
The section 106 is usually the longest item on that list and it runs in parallel rather than after, so start drafting heads of terms before the committee date. The note on what stops the eight week planning clock applies with more force here, because every one of these steps can pause.
Preparing for the Stage 1 report
GLA officers assess against the London Plan, and the assessment is policy by policy. The documents that get tested hardest are predictable.
An Energy Statement structured to the be lean, be clean, be green, be seen hierarchy, with the carbon shortfall and the offset payment calculated. A Whole Life Carbon Assessment and a Circular Economy Statement in the templates the Mayor publishes, which are prescriptive about format and will be sent back if the format is wrong. A Fire Statement, which for relevant buildings is also a Gateway One matter and must be prepared by someone with the necessary fire engineering competence, since the Building Safety Act 2022 framework makes that a legal requirement rather than a preference.
Affordable housing is assessed through the threshold approach, so decide early whether the scheme is going down the fast track route at the relevant percentage or submitting a viability assessment and accepting review mechanisms. That decision shapes the whole Stage 1 conversation.
Pre-application engagement with the GLA is available and chargeable under the Mayor's published schedule. On a scheme of any complexity it pays for itself, because the Stage 1 report then confirms a position you already know rather than announcing one.
Conditions and obligations through the process
The Mayor does not impose conditions directly unless he takes the application over. What happens instead is that the Stage 1 and Stage 2 reports set out what the Mayor expects, and the borough writes those expectations into its conditions and section 106 agreement.
Common items secured this way include the affordable housing tenure split and the early and late stage review mechanisms, the carbon offset payment, car-free or car-capped parking with permit restrictions, the urban greening factor, play space provision, and a commitment to the circular economy targets.
Mayoral community infrastructure levy is payable across Greater London in addition to any borough levy, and it is calculated and collected by the borough.
Where the Mayor takes over the application
Plan for it as a possibility rather than a certainty. If a takeover direction is issued, the GLA case officer becomes your point of contact, the representation hearing replaces the committee, and the hearing procedure allows the applicant, the borough and objectors to speak before the Mayor decides.
The practical preparation is the same work done earlier. A clear Affordable Housing Statement with the tenure split and the viability position evidenced, a design case that answers the Stage 1 report point by point, and a section 106 draft that is already agreed in principle with the borough.
This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
Which applications have to be referred to the Mayor of London?
Those falling within the categories of potential strategic importance in the Schedule to the Town and Country Planning (Mayor of London) Order 2008. The main triggers are more than 150 homes, floorspace above location-dependent figures, tall buildings above location-dependent heights, and development on Green Belt or Metropolitan Open Land above stated thresholds.
How long does GLA referral add to a planning application?
Six weeks for the Stage 1 report, during which the borough cannot determine, and a further 14 days at Stage 2 after the borough has resolved what it intends to do. Most referable schemes run under a planning performance agreement because the statutory 13 week period cannot absorb both stages plus a committee cycle.
Can the Mayor refuse a planning application?
The Mayor can direct a borough to refuse where the borough proposes to grant and the scheme is unacceptable in strategic terms. Alternatively the Mayor can take the application over and become the local planning authority, which requires strategic impact on the London Plan, sound planning reasons and expediency, and leads to a representation hearing.
Is a section 73 application to a referable permission also referable?
Yes, where the original permission was referable. Teams that treat variations as administrative are caught out by this, because the same Stage 1 and Stage 2 timetable applies. Check the category before programming any variation to a major London consent, including minor changes to conditions.
What does the Stage 1 report actually do?
It sets out whether the scheme complies with the London Plan, what would have to change for it to comply, and whether the Mayor is likely to intervene. It is written by GLA planning officers and published, and boroughs commonly adopt its conclusions in their own officer report, so treat it as the agenda for the rest of the application.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.