Most of the delay between a committee resolution and a decision notice is conveyancing, not planning. The drafting gap, the parties to join and the timetable imposed.

A section 106 completion delay is the most common reason a scheme that has been approved still has no permission six months later. A resolution to grant planning permission subject to the completion of a section 106 agreement is not a decision. It is a statement of what the authority intends to do once the deed is signed, and until the decision notice is issued there is no permission, no implementation clock and nothing a funder can lend against.

Understanding what actually has to happen between the resolution and the notice is what lets you compress it. Most of the delay is conveyancing rather than planning.

A resolution to grant is not a permission

The legal position is firm. Only the issued decision notice grants permission, and the authority's duty to have regard to material considerations continues right up to the moment it is issued. That principle, established in the line of cases following Kides v South Cambridgeshire District Council, means a resolution can be revisited where circumstances change.

So the risks running during the gap are real:

  • A new edition of the National Planning Policy Framework or a newly adopted local plan changes the policy position.
  • The council's housing land supply position changes, which alters the weight in the balance.
  • A new application or appeal decision on an adjoining site becomes a material consideration.
  • Membership of the committee changes and officers are asked to report the matter back.

None of those is an argument for ignoring the deed. They are arguments for completing it quickly, and for diarising the policy events you can see coming.

Who drafts the deed and who pays

In most authorities the council's own legal team or an external solicitor instructed by the council prepares the first draft, and the applicant pays the council's reasonable legal costs through an undertaking given before drafting starts. That undertaking is often the first thing to go wrong, because nobody chases it.

Three practical moves shorten this stage. Give the costs undertaking the week of the resolution rather than waiting to be asked. Ask whether the authority has a standard template or model deed and work from it rather than offering your own precedent. And identify the actual solicitor who will do the drafting, because an instruction sitting in a shared inbox is not an instruction.

Where the council is slow and the obligations are straightforward, consider offering a unilateral undertaking instead. Section 106 of the Town and Country Planning Act 1990 allows an obligation to be entered into by agreement or otherwise, so an owner can covenant unilaterally. Authorities are often reluctant where the obligations are complex, and it is a realistic route where the terms are a simple payment or a restriction.

The gap between heads of terms and drafting

Heads of terms agreed at committee are usually a page. The deed is thirty. Everything in between is drafting, and drafting exposes the questions the heads of terms left open.

Heads of terms say The deed has to say
A contribution towards education The sum, the indexation basis and date, the trigger, the repayment term if unspent, and the project
Affordable housing at the policy level Numbers, tenure split, unit types, transfer mechanism, nomination rights, mortgagee exclusion clause, cascade
Open space to be provided Specification, phasing trigger, maintenance arrangement, transfer or commuted sum, adoption route
Travel plan with monitoring Monitoring sum, duration, targets, remedies if targets are missed

Agree the mechanics before the first draft rather than in comments on it. The single most useful document at this stage is a one page schedule listing each obligation with its trigger, its sum, its index, its review and its release. Hand that to the drafting solicitor and you remove two rounds of amendments.

Indexation is where most of the arguments happen, and the question is always the same three things: which index, from what base date, and to what date. Get them written down. Where affordable housing is in play, the drafting of the Affordable Housing Statement and the deed should use identical figures and definitions.

Title problems that stall completion

A planning obligation binds the land, so everyone with an interest in the land that the obligation needs to bind has to be a party to it. That is a conveyancing exercise, and it is where schemes lose months.

The recurring problems:

  1. Unregistered land, or registered title with a plan that does not match the application red line.
  2. Third party land included for access, drainage or visibility splays, where that owner has to be joined.
  3. An option or conditional contract where the applicant has no interest in the land yet, so the registered proprietor must be a party.
  4. Restrictive covenants that conflict with the obligations. These do not prevent completion, though your funder will want them flagged.
  5. Tenancies, including agricultural tenancies, where the tenant's interest has to be considered.

Run the title work in parallel with the application rather than after the resolution. An Official Copy of the register and title plan, a plan comparison against the application boundary, and a list of everyone who needs to be joined can be assembled in a fortnight and will save you two months later. The same discipline that applies to planning history searches before you buy a site applies here.

Mortgagees and other parties to the deed

Where the land is charged, the authority will normally require the lender to be a party or to consent. From the council's point of view, an obligation that could be defeated by a lender enforcing its security is not worth having.

Lenders are generally willing, and they are generally slow. Their credit process has its own timetable, their panel solicitor has to review the deed, and they will want the affordable housing mortgagee exclusion clause in a form their standard terms accept. Start that conversation at resolution stage, not when the deed is in final form.

Other parties sometimes needed include a management company for open space, a registered provider where affordable units are being transferred, and a statutory undertaker with apparatus on the site. Each adds a review cycle, so identify them early and circulate drafts to all parties simultaneously.

The timetable the council imposes

Authorities commonly attach a period to the resolution within which the agreement must be completed, after which the application is either refused under delegated powers or reported back to committee. Check the wording of your resolution for the period and the consequence, because they vary.

Where the period is going to be missed for reasons outside your control, ask for an extension in writing before it expires and set out why. A request made in advance with a credible explanation, such as waiting on a lender or joining a third party owner, is normally treated differently from a request made after the deadline has gone.

Running alongside this is the determination period itself. Where no extension of time has been agreed, the authority is formally out of time, which affects its performance statistics and gives you a non-determination appeal you almost certainly do not want to use. Agreeing a written extension of time keeps both sides comfortable, and it is worth understanding what else stops the eight week planning clock.

Keeping the resolution alive

Treat the period after resolution as an active project rather than a waiting period. The things worth doing:

Keep a dated list of outstanding items with the party responsible for each, and circulate it weekly. Nothing else moves a multi-party deed along as effectively.

Watch the policy horizon. If a local plan examination is reporting or a new Framework edition is due, say so in your correspondence and ask the authority to prioritise accordingly.

Settle the plans to be attached before the deed is engrossed, since a late plan change means re-engrossment and re-execution by every party.

And confirm in writing what the decision notice will say, including the conditions and the plan numbers, because the notice is the document you will be living with. A mismatch between the deed, the conditions and the plans is the thing that causes trouble later, as anyone who has looked at varying a permission for development already begun will know.

Enter your postcode on PlanScope to see which reports your scheme is likely to need alongside the obligations work.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Is a resolution to grant planning permission binding?

No. Only the issued decision notice grants permission, and the authority's duty to have regard to material considerations continues until that notice is issued. A resolution can therefore be revisited where circumstances change, which is why completing the deed quickly matters more than it appears to.

Who drafts a section 106 agreement?

Usually the council's legal team or an external solicitor it instructs, with the applicant paying the authority's reasonable legal costs under an undertaking given before drafting starts. Giving that undertaking in the week of the resolution, and working from the council's own template, removes a surprising amount of delay.

Why do title problems delay a section 106?

A planning obligation binds the land, so everyone with a relevant interest has to be a party. Unregistered land, title plans that do not match the application boundary, third party land included for access or drainage, options where the applicant holds no interest yet, and tenancies all require work that is better done in parallel with the application.

Does a mortgage lender have to be a party to the deed?

Where the land is charged, authorities normally require the lender to be a party or to consent, because an obligation defeated by enforcement of the security would be worth little. Lenders are usually willing and usually slow, so start the conversation at resolution stage rather than when the deed is in final form.

What happens if the agreement is not completed in time?

Authorities commonly attach a completion period to the resolution, after which the application is refused under delegated powers or reported back to committee. Check the wording of your resolution, and if the period will be missed for reasons outside your control, request an extension in writing before it expires.

Can I offer a unilateral undertaking instead?

Section 106 of the Town and Country Planning Act 1990 allows an obligation to be entered into by agreement or otherwise, so an owner can covenant unilaterally. Authorities are often reluctant where obligations are complex, but it is a realistic route where the terms amount to a simple payment or restriction.

Sources and further reading

section 106planning obligationsdecision noticetitleaffordable housingplanning process

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Planning Process

View all →
Planning Process7 min read

Online planning submission and the validation receipt

Submitting is not the same as being validated. What the council checks, the defects that invalidate householder applications, and the record to keep from the day you submit.

Read article →
Planning Process6 min read

Habitats screening where no European site is nearby

Being ten miles from the nearest designated site does not end the habitats question. Pathways travel further than people expect, and the council has to record its conclusion either way.

Read article →
Planning Process6 min read

Varying the time limit on an unimplemented permission

Section 73 is expressly barred from extending a time limit. That leaves two real options, and the one most developers overlook is making a lawful start before the deadline.

Read article →
Planning Process7 min read

Environment Agency objections and how they are lifted

Most Environment Agency objections are holding objections about missing information. Work out which type you have before you spend money answering the wrong question.

Read article →
Planning Process7 min read

Statements of common ground before determination

Agreeing the facts with a case officer before the decision is a practice borrowed from appeals. Done properly it removes whole topics from the argument and leaves a clean record if you later appeal.

Read article →
Planning Process6 min read

The agent's authority to submit a planning application

Planning law does not require the applicant to own the site, but it does require the correct ownership certificate and notices. Naming the applicant precisely matters most when the section 106 agreement is drafted.

Read article →