Varying the time limit on an unimplemented permission

6 min readBy PlanScope Editorial Team

Section 73 is expressly barred from extending a time limit. That leaves two real options, and the one most developers overlook is making a lawful start before the deadline.

You cannot extend the time limit on a planning permission by a section 73 application. Section 73(5) of the Town and Country Planning Act 1990 says so expressly: permission cannot be granted under that section to the extent that it would change a condition by extending the time within which development must be started. That one subsection removes the obvious route, and it surprises people every year. What remains is a fresh application for the same development, determined against today's policy, or a lawful start on site before the permission runs out.

Why permissions expire

A full planning permission carries a condition requiring development to begin within three years of the grant, unless the authority has directed a different period. Outline permission works differently: reserved matters have to be applied for within three years, and development has to begin within two years of the final approval of reserved matters.

Those periods come from sections 91 and 92 of the 1990 Act, and the three year default replaced the earlier five year period in 2004. The authority can substitute a longer or shorter period where it is justified, and on a large phased scheme a longer period is often negotiated at the outset. That is far easier than fixing the problem later.

An expired permission is gone. There is no revival, no late implementation, and nothing in the system that treats a nearly started scheme as started.

Whether the time condition can be varied

The short answer is no, and the statutory bar is explicit.

Section 96A, the non-material amendment power, does not help either. It cannot be used to alter a condition in a way that is material, and extending the life of a permission is plainly material.

The Levelling-up and Regeneration Act 2023 inserted a further variation power into the Act, and its commencement and scope are worth checking at the time you need it, together with how your authority is applying it in practice. Do not assume it provides a route to extend a time limit.

There was once a dedicated extension of time procedure, introduced during the financial crisis for permissions granted before October 2010. It allowed a simplified application to replace an expiring permission. That scheme ended in October 2012 and has not returned, though it resurfaces in conversation every time the market slows.

The fresh application route

The standard answer is a duplicate application: the same development, the same drawings, submitted again before the original expires. If granted, you hold two permissions and can implement either.

It is a full application, with the full fee, full validation requirements and a full determination period. The authority determines it against the development plan and material considerations as they stand now, not as they stood when the original was granted.

Overlapping permissions need thought. Where two permissions for the same land are inconsistent with each other, implementing one may make the other incapable of lawful implementation, and the courts have looked closely at this in recent years. On a multi-phase site, take advice before relying on a patchwork of consents.

Where the existing permission has already been implemented in part, the position is different again, and the mechanics are set out in varying a permission for development already begun.

Policy changes since the original grant

This is the real risk in a resubmission, and it is why the fresh application is not a formality.

Biodiversity net gain is the clearest example. The statutory biodiversity gain condition attaches to permissions granted after the relevant dates, so a scheme permitted before then and resubmitted now will need a biodiversity net gain assessment using the statutory metric, a biodiversity gain plan approved before development begins, and a 30 year management commitment. On a greenfield site that can change the layout and the land budget.

The others to check are the current edition of the National Planning Policy Framework and its policy codes, a local plan adopted or reviewed since the grant, nutrient neutrality catchments designated since, the fire statement requirement for relevant buildings at Planning Gateway One, the Part L uplift and overheating requirements, revised Environment Agency climate change allowances, and a changed affordable housing policy or levy rate.

Make a list, check each, and price the gap before deciding. A resubmission that triggers nutrient mitigation on a scheme that did not previously need it is not a renewal, it is a new project.

Starting work instead

The alternative is to make a lawful start before the permission expires. Section 56(4) of the 1990 Act lists what counts as beginning development: among them digging a trench for foundations, laying out a road, a material change of use, and work of demolition.

Two cautions. The operation has to be genuine rather than token, and an inspector or a court will look at whether it was carried out with the intention of implementing the permission. And every condition that has to be complied with before development begins must be discharged first, because work carried out in breach of a true pre-commencement condition does not lawfully implement the permission.

That second point defeats more attempted starts than the first. Read the decision notice, list every condition with a pre-commencement trigger, and apply to discharge them with enough time for an eight week determination. Then do the works, document them with dated photographs and a site record, and notify the authority.

Once a permission is lawfully implemented it does not expire, although conditions requiring completion within a period, or a phasing condition, can still bite.

Costs and programme compared

Route Fee Time Main risk
Fresh duplicate application Full application fee 8 or 13 weeks plus preparation Determined against current policy, so new requirements apply
Lawful commencement Condition discharge fees only Time to discharge pre-commencement conditions Operation found not to be genuine, or conditions not discharged

The arithmetic usually favours commencement where the site is controlled, the pre-commencement conditions are few, and the scheme will genuinely be built. It favours a fresh application where the scheme has changed, where the conditions are onerous, or where a funder needs a clean, current permission.

A site being acquired needs the position checked before exchange. The search work described in planning history searches before you buy a site should identify the expiry date, the pre-commencement conditions and any evidence of an earlier attempted start.

Deciding before the expiry date

Work backwards from the expiry date on the decision notice. Allow eight weeks for condition discharge, plus the time to prepare the information each condition requires, which on drainage, remediation or ecology can be months rather than weeks.

For the resubmission route, allow the determination period plus preparation, plus a margin for the authority to seek amendments. Submitting a duplicate application six weeks before expiry leaves no room at all.

Put the expiry date in the project risk register the day the permission is granted, with a review trigger eighteen months out. The planning statement for any resubmission should explain the planning history and deal openly with what has changed in policy since the original grant, because the case officer will find it anyway.

You can draft that statement on PlanScope by entering the postcode and answering the guided questions, then check it against the current validation list before submitting.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Can section 73 be used to extend a planning permission?

No. Section 73(5) of the Town and Country Planning Act 1990 expressly prevents a permission being granted under that section where it would change a condition by extending the time within which development must be started. Section 96A non-material amendments cannot do it either, because the change would be material.

What counts as beginning development?

Section 56(4) of the 1990 Act lists the material operations, including digging a trench for the foundations, laying out a road, work of demolition and a material change of use. The operation must be genuine rather than token, and carried out with the intention of implementing the permission rather than merely preserving it.

Do I have to discharge conditions before starting?

Every condition with a pre-commencement trigger must be discharged before the works that are intended to implement the permission. Work carried out in breach of a true pre-commencement condition does not lawfully begin the development, so the permission can still expire. Allow eight weeks for determination of each discharge application.

Will a resubmitted application need biodiversity net gain?

If permission is granted after the relevant commencement dates, yes. The statutory biodiversity gain condition attaches to the new permission even though the original pre-dated the regime. That means an assessment using the statutory metric, a gain plan approved before development begins, and a 30 year management commitment.

Is there still an extension of time application?

No. The simplified procedure introduced during the financial crisis applied only to permissions granted before October 2010 and ended in October 2012. It has not been reinstated. The current options are a fresh application for the same development or a lawful start on site before the permission expires.

Sources and further reading

section 73time limitexpiring permissioncommencementplanning process

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Planning Process

View all →
Planning Process7 min read

Section 106 completion and the decision timetable

Most of the delay between a committee resolution and a decision notice is conveyancing, not planning. The drafting gap, the parties to join and the timetable imposed.

Read article →
Planning Process7 min read

Online planning submission and the validation receipt

Submitting is not the same as being validated. What the council checks, the defects that invalidate householder applications, and the record to keep from the day you submit.

Read article →
Planning Process6 min read

Habitats screening where no European site is nearby

Being ten miles from the nearest designated site does not end the habitats question. Pathways travel further than people expect, and the council has to record its conclusion either way.

Read article →
Planning Process7 min read

Environment Agency objections and how they are lifted

Most Environment Agency objections are holding objections about missing information. Work out which type you have before you spend money answering the wrong question.

Read article →
Planning Process7 min read

Statements of common ground before determination

Agreeing the facts with a case officer before the decision is a practice borrowed from appeals. Done properly it removes whole topics from the argument and leaves a clean record if you later appeal.

Read article →
Planning Process6 min read

The agent's authority to submit a planning application

Planning law does not require the applicant to own the site, but it does require the correct ownership certificate and notices. Naming the applicant precisely matters most when the section 106 agreement is drafted.

Read article →