Statements of common ground before determination
Agreeing the facts with a case officer before the decision is a practice borrowed from appeals. Done properly it removes whole topics from the argument and leaves a clean record if you later appeal.
A statement of common ground planning applicants and case officers sign before determination is not a statutory document, and no regulation requires one. It is borrowed from appeal and plan-making practice, where the Planning Inspectorate expects the parties to set out what they agree before an inquiry or hearing. Used on a live application it does one useful thing: it takes topics off the table so the officer's report and any later appeal deal only with what is genuinely in dispute. On a major scheme with eight technical disciplines, agreeing six of them in writing by week ten changes the shape of the whole determination.
What agreeing the facts actually achieves
A case officer writing a committee report on a 180 unit scheme has to summarise highways, drainage, ecology, heritage, air quality, noise, affordable housing and viability. Most of that summary is uncontested description. If the highway authority has confirmed in writing that the access geometry, visibility splays and trip generation are accepted, the report can record that in three lines rather than three pages.
The second effect is on the applicant's side. A signed record of what the authority accepts stops the position moving when the case officer changes, which on a twelve month major application happens more often than anyone admits. It also exposes disagreement early, while there is still time to redesign.
What it does not do is bind the council. A statement of common ground is a record of a shared factual position, and the authority remains free to refuse on any material consideration. Treat it as a way of organising the argument rather than a concession extracted.
The topics that suit it
Factual and methodological matters work. Judgement does not.
- Agreed baseline data: traffic counts, survey dates, habitat classifications, existing floor areas, the lawful use of the site.
- Agreed methodology: the trip rate database and the sites selected from it, the noise survey positions and durations, the daylight method, the viability inputs that are not contested.
- Agreed policy framework: which development plan policies apply, which are out of date, the relevant parts of the National Planning Policy Framework in its current edition.
- Agreed compliance: that the scheme meets the space standard, that the parking provision accords with the adopted standard, that the drainage discharge rate is acceptable to the lead local flood authority.
Design quality, the planning balance, the weight given to harm, and whether very special circumstances exist are not candidates. An officer who signs up to a conclusion on any of those has fettered the recommendation, and will refuse to do so.
The boundary is not always obvious. Whether a building is a non-designated heritage asset is a judgement. Whether it appears on the council's local list is a fact. Draft on the fact side of that line.
Drafting it so an officer can sign
Write it as a table with three columns: the matter, the agreed position, and the document that evidences it. Keep each agreed position to a single sentence that a busy officer can read and accept or strike through. Number every row, because you will refer to the numbers later.
Send a draft, not a request for one. Case officers have no time to originate the document, and an applicant's draft that is scrupulously fair gets signed far more often than a request for the council's view. Include a column headed "not agreed" and populate it honestly with the points you know are contested. An officer reading a document that claims everything is agreed will stop reading.
Route it correctly. Highways matters belong to the highway authority, drainage to the lead local flood authority, ecology often to a county ecologist. Get those consultees to confirm their sections by email and attach the emails rather than asking the planning officer to speak for them.
One practical point on timing. Send it after the consultation responses are in and before the officer starts drafting the report, which on a major application usually means somewhere around week ten to fourteen. Too early and nobody has formed a view. Too late and the report is already written.
Where the council will not engage
Some authorities will not sign anything before a decision, as a matter of policy, usually on legal advice about fettering discretion. Others simply lack the resource. Neither refusal is a bad sign, and arguing about it wastes goodwill.
The fallback is a unilateral note of the agreed position sent to the officer with an invitation to correct anything that is wrong. Silence is not agreement, but a note that was sent, never contradicted and later contradicted at appeal is awkward for the authority to explain. Keep the sending email.
A Planning Performance Agreement is the formal alternative where the council offers one. It sets a programme, names the officers, fixes meeting dates and usually carries a fee. On a scheme large enough to justify the cost, the agreement can record agreed matters as a schedule, which gives you the same benefit with a contractual frame around it.
What it does to the committee report
Officers write reports defensively, because the report is the document that gets quoted at appeal and in any judicial review. A clear record of agreed matters lets the officer deal with those topics by reference rather than by rehearsal, and the report then spends its length on the contested planning balance.
That matters at committee. Members read the recommendation, the key issues and the conditions. A report in which highways, drainage and ecology occupy four lines each because they are agreed is a report in which the real debate is visible. Compare that with the twelve page report where a member hunting for the objection has to wade through uncontested technical summary.
Your planning statement should cross-refer to the agreed matters rather than repeating them, which also keeps the statement shorter and more readable.
Carrying it into an appeal
If the application is refused, the agreed matters go straight into the appeal statement of common ground, which the Planning Inspectorate requires for hearings and inquiries and encourages for written representations. Having done the work already saves weeks and removes a standard source of friction, because the parties are not starting from nothing six weeks before an inquiry.
It also constrains the council's case. The authority can resile from an agreed factual position, but it has to explain why, and inspectors notice when a council agrees survey data in March and disputes it in October. The documents the council has to produce are set out in the appeal questionnaire and what the council must supply, and an agreed matters schedule sits naturally alongside them.
Costs are the sharp end. Where a council takes a position at appeal that contradicts something it agreed without new evidence, that is the kind of unreasonable behaviour that supports a costs application.
Keeping it current
Schemes change. Every revision to the layout, the unit mix or the drainage design potentially unpicks an agreed row, and a statement that refers to drawing revision C while the council is assessing revision F is worse than no statement at all.
Version the document, date every row, and reissue it whenever amended plans are submitted. Note on the face of it which drawing numbers and which technical reports the agreement relates to. Where an amendment has stopped the eight week clock or triggered reconsultation, the reasons set out in what stops the eight week planning clock will usually tell you whether a reissue is needed.
The last version before determination is the one that matters. Send it, ask for confirmation, and file the reply.
You can draft the planning statement that sits alongside an agreed matters schedule on PlanScope by entering the postcode and answering the guided questions, then edit it as the agreed positions firm up.
PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
Is a statement of common ground required before a planning decision?
No. There is no statutory requirement for one on a live planning application. The formal requirement arises in plan-making and in appeal procedures, where the Planning Inspectorate expects the parties to agree facts before a hearing or inquiry. Using the same device before determination is a voluntary practice that some authorities adopt and others decline.
What should go in an agreed matters schedule?
Factual and methodological points: survey data and dates, the lawful use of the site, existing floor areas, agreed methodology for transport, noise or daylight work, the policies that apply, and compliance with numeric standards. Keep out matters of planning judgement such as design quality, the weight given to harm, or the overall planning balance.
Can a council refuse permission after signing a statement of common ground?
Yes. Agreeing facts does not fetter the authority's discretion, and it can still refuse on any material consideration, including one covered by the agreement if it gives reasons. What the document does is make an unexplained change of position visible, which carries weight with an inspector and can support a costs application at appeal.
When in the application process should it be sent?
After the consultation responses have arrived and before the officer begins drafting the committee or delegated report, which on a major application is typically around weeks ten to fourteen. Earlier than that and consultees have not formed views. Later and the report is already written, so the document changes nothing.
What if the council will not sign anything?
Send a unilateral note recording what you understand to be agreed and invite correction. Silence is not agreement, but an uncontradicted note is useful evidence if the authority takes a different line later. Where the council offers a Planning Performance Agreement, the agreed matters can sit in a schedule to it instead.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.