National Highways holding directions on an application
A direction from National Highways prevents the local planning authority issuing a decision, even after a committee resolution. It is a brake rather than an objection, and resolving the underlying issue is the only reliable way to lift it.
A National Highways holding direction stops a council granting planning permission while the strategic road network implications of a scheme are resolved. It is not an objection and it is not a refusal. It is a legal brake, issued when the body responsible for motorways and trunk roads has been consulted and is not yet satisfied, and while it is in force the local planning authority cannot issue a decision even if its committee has resolved to approve.
Developers discover it at the worst possible moment, which is after the committee has voted.
When the strategic road network is engaged
The strategic road network is the motorway and trunk road system in England, managed by National Highways rather than by the county or unitary highway authority. A scheme engages it where development would materially affect traffic on it, which in practice means sites near a junction, sites served by a route feeding a junction, and any proposal with a direct access onto a trunk road.
Consultation flows from the statutory consultee arrangements in the Development Management Procedure Order 2015, which require the authority to consult the relevant body before granting permission for development of a described kind. National Highways then responds in one of four ways: no objection, no objection subject to conditions or obligations, a direction restricting the grant of permission while matters are resolved, or a recommendation that permission be refused.
Government policy on how the body approaches this sits in the Department for Transport circular on the strategic road network and the delivery of sustainable development, which aligns the test with national planning policy: an objection on capacity grounds requires a severe residual cumulative impact, not merely a measurable one.
What a holding direction does
The direction is addressed to the local planning authority and prevents it granting permission for the period stated. The authority can continue to process the application, consult, report to committee and resolve its position. What it cannot do is issue the decision notice.
Three consequences follow immediately.
The statutory determination period keeps running, so a major application can pass 13 weeks while the direction sits in place. The applicant's agreed extension of time, if there is one, may expire. And where a section 106 agreement is being negotiated in parallel, the completion date drifts because there is no decision to complete against.
A direction is not a judgement on the merits of the scheme. Most are issued because a modelling question is unresolved or a mitigation scheme is not yet secured, and most are lifted.
Duration and extension of the direction
Directions are time limited and routinely extended where matters remain unresolved. A new direction replaces the old one when the period runs out, so an applicant who assumes the brake comes off automatically at the end of the stated period is usually disappointed.
Plan on the direction lasting as long as the underlying issue does. The only reliable way to shorten it is to resolve the issue, which means the programme is in your hands more than it looks.
Where the issue will not resolve and the authority cannot determine, applicants sometimes appeal against non-determination to move the decision to the Planning Inspectorate. That is a tactic with real consequences, including the loss of the authority's support and the cost of an inquiry, and it should be taken on advice rather than out of frustration.
Getting a direction lifted
The sequence that works is unglamorous and it starts before the application.
- Engage before submission. National Highways operates a spatial planning function that will agree a scope for the transport work, and an agreed scope removes most of the later argument.
- Agree the base data. Survey dates, count locations, seasonality and the treatment of atypical conditions should be settled before any model is built.
- Agree the committed development list. What counts as committed, and what growth factors apply, decides the future year flows more than the proposal itself does.
- Run the assessment years the body expects, usually an opening year and a later design year.
- Offer mitigation in a deliverable form, with a scheme drawing, a cost and a mechanism.
- Provide the safety analysis using recorded collision data for the junctions concerned.
Respond to each point in the direction individually and in writing, with a tracker showing what has been provided. A single long technical note rarely closes a direction. A point-by-point response usually does.
Evidence the body expects
The transport evidence base on an SRN case is more formal than on a local highway case.
A Transport Assessment prepared to the circular's expectations, with trip generation drawn from a recognised trip rate database and justified site selection rather than cherry-picked comparators. Junction modelling appropriate to the junction type, with the model files supplied so they can be checked rather than only the summary outputs. Sensitivity testing, because a model that only works on the central case will not persuade.
Alongside it, a Travel Plan with measurable targets, a named coordinator, monitoring surveys and a mechanism for remedial measures. Sustainable transport measures carry real weight under the circular, and a travel plan that is a list of aspirations carries none.
On smaller schemes a Transport Statement may be the right document, and it is worth asking the body which it expects rather than defaulting to the larger one.
Conditions and obligations in response
Most directions are discharged by securing something rather than by argument alone.
Grampian conditions preventing occupation until highway works are complete are standard, and they are enforceable because they bite on the development rather than on third-party land. Obligations in the section 106 agreement commonly cover a financial contribution towards a wider junction improvement, travel plan monitoring fees, and a bond or security for works to be delivered under a highway agreement.
Where works on the strategic network itself are required, those are delivered through an agreement with National Highways rather than through the planning permission, and the design approval process for them is long. Start it in parallel rather than in sequence.
Programme implications
Treat a strategic road network case as adding months, and build the sequence into the appraisal: scoping before submission, assessment, consultation response, direction, resolution, discharge of the direction, committee resolution if not already given, section 106 completion, decision.
Two further items are worth pricing in. Model audit, where the body or its technical advisers check your junction model and come back with queries, routinely takes several weeks and arrives after you thought the work was finished. And where mitigation on the trunk road itself is needed, the design approval process for those works runs on its own timetable, which is longer than the planning one and does not speed up because a committee date is approaching.
The item that most often derails the programme is agreeing the base traffic data, because surveys must be taken in neutral months and a survey taken in August or late December will be rejected. Missing a neutral window costs a season.
The note on what stops the eight week planning clock covers the other procedural brakes that can operate at the same time, and a clear Planning Statement that sets out the transport position honestly tends to shorten the exchange rather than lengthen it.
This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
What is a National Highways holding direction?
A direction addressed to the local planning authority preventing it from granting planning permission for a stated period while strategic road network issues are resolved. The authority can keep processing the application, consult and even resolve to approve, but it cannot issue the decision notice while the direction is in force.
How long does a holding direction last?
It is time limited but routinely extended, with a new direction replacing the old one where the issue remains unresolved. Assuming the brake comes off automatically at the end of the stated period is a common mistake. The direction effectively lasts as long as the underlying technical or mitigation question does.
Is a holding direction the same as an objection?
No. Most are issued because a modelling question is unresolved or mitigation is not yet secured, and most are lifted. A recommendation that permission be refused is a separate response. Under the Department for Transport circular, an objection on capacity grounds requires a severe residual cumulative impact.
Can I appeal if the direction will not be lifted?
An appeal against non-determination moves the decision to the Planning Inspectorate once the statutory period has passed. It is a real option but it carries consequences, including losing the authority's support and the cost of an inquiry. Take it on advice rather than out of frustration with the delay.
What transport evidence does National Highways expect?
A transport assessment to the circular's expectations with justified trip rates, junction modelling with the model files supplied rather than only summary outputs, sensitivity testing, assessment at an opening year and a later design year, recorded collision data for the junctions, and a travel plan with measurable targets and monitoring.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.