Planning Process

Publicity for a departure from the development plan

7 min readBy PlanScope Editorial Team

A proposal conflicting with the adopted plan triggers newspaper advertisement and a 21 day site notice. Referral to the Secretary of State is narrower than it was, and the committee cycle adds more time than the referral does.

An application that conflicts with the adopted development plan has to be advertised twice over: a site notice displayed for at least 21 days and a notice in a local newspaper. That is the publicity requirement for a departure from the development plan under article 15 of the Development Management Procedure Order 2015, and it applies whether or not the authority is minded to approve. Referral to the Secretary of State is a separate question, and since 2009 it catches far fewer departures than most agents assume.

Get those two things the wrong way round and you lose a month.

What makes an application a departure

Section 38(6) of the Planning and Compulsory Purchase Act 2004 requires the determination to be made in accordance with the development plan unless material considerations indicate otherwise. A departure is simply an application that does not accord with the plan, read as a whole.

That last phrase carries the weight. A proposal can breach one restrictive policy and still accord with the plan overall, because the plan is read as a composite document and the authority forms a planning judgement on the balance of its policies. Conflict with a single criterion in a design policy is not automatically a departure. Conflict with a settlement boundary, a site allocation or a strategic housing policy usually is.

The authority makes the call, and it makes it early, because the publicity route follows from it. If you believe the application accords with the plan and the case officer has advertised it as a departure, say so in writing at the start rather than in your appeal statement.

The additional publicity required

Article 15 of the Development Management Procedure Order 2015 sets out the publicity for each category of application. For development that does not accord with the development plan in force in the area, the authority must both publish a notice in a newspaper circulating in the locality and display a site notice for not less than 21 days.

That is the same publicity the Order requires for development affecting a public right of way, and a tier above the standard householder or minor application, which can be dealt with by site notice or neighbour letters alone.

Three practical consequences follow:

  1. The newspaper advertisement is placed on the paper's publication cycle, not the council's. A weekly local paper with a Tuesday deadline can add nine or ten days on its own.
  2. The 21 day period runs from the later of the two notices, so a site notice posted before the advert does not start the clock in the way the file suggests.
  3. The cost of the advertisement is recharged by some authorities under their published scale of charges, so check the local list before you budget.

None of this is discretionary. An authority that grants permission without the newspaper notice has a procedural defect on the face of the decision, which is a point worth noting if you are the objector rather than the applicant.

Referral where the authority is minded to approve

The old blanket requirement to notify the Secretary of State of every departure is gone. The Town and Country Planning (Consultation) (England) Direction 2009 replaced it with a narrower list of categories, so most departures are now decided locally without any referral at all.

The categories that still require consultation before an authority may grant permission include inappropriate development in the Green Belt above a floorspace threshold or otherwise affecting openness, substantial out-of-centre retail, leisure and office development, and development of playing field land where the statutory sports consultee has objected and maintained that objection. A separate direction deals with development in a flood risk area where the Environment Agency has objected on flood risk grounds and has not withdrawn the objection.

Where a direction applies, the authority notifies the Secretary of State, supplies the papers and must not issue the permission until the notice period has run. The Secretary of State may then call the application in under section 77 of the Town and Country Planning Act 1990, direct that it be refused, or simply let the authority decide.

Call-in is rare. The delay is not.

Time the referral adds

Budget the referral as a minimum of 21 days from the date the papers go in, and in practice longer, because the clock starts when the department confirms the submission is complete rather than when the officer posts it.

Layer that on top of the committee cycle. A departure is almost always a committee item rather than a delegated decision, because councils' schemes of delegation reserve departures to members. So the realistic sequence is: validation, 21 day publicity, officer report, committee resolution to grant subject to referral, referral period, then the decision notice. A minor application that would have been determined in eight weeks takes four to five months.

Agree an extension of time under article 34 early. It costs you nothing and it stops the authority refusing to beat the clock.

Framing the departure case

The case has to be built in the language of section 38(6). Name the policies the proposal conflicts with, rather than letting the officer find them. Then set out the material considerations said to outweigh that conflict, and explain why they do.

Useful material considerations in this setting include the age of the plan and whether its policies for the supply of housing are out of date, the weight to be given to an emerging plan at its stage of preparation, the absence of harm in fact where a boundary is drawn tightly, the delivery of a benefit the plan itself seeks, and consistency with national policy under the current National Planning Policy Framework. State the edition of the Framework you are citing, because it was renumbered in December 2024 and re-issued with policy-coded chapters on 17 August 2026.

Be honest about the conflict. Officer reports that describe a scheme as a departure and then conclude there is no conflict read badly at appeal, and inspectors notice. The stronger structure is: there is conflict, here is its extent, here is what outweighs it.

A properly argued Planning Statement is doing the whole job in a departure case, because there is no policy hook to hide behind. If the case turns on housing land supply or on the weight to be given to an emerging allocation, that analysis belongs in the statement rather than in a covering letter.

Alternatives to a departure application

Before accepting departure status, test three alternatives.

Read the plan as a whole again and see whether a reasoned case for compliance can be made, perhaps by relying on a supportive policy the officer has overlooked entirely. Consider whether a smaller or re-sited scheme falls inside the constraint. And where the land really is in the wrong place in the plan, consider whether promoting the site through the next local plan review or a neighbourhood plan allocation is the better route, accepting the timescale that implies.

A fourth option exists on some sites: where an authority has made a local development order, development of a described type within the order area has permission without an application. These are uncommon outside regeneration areas, but they are worth checking.

Documents the referral needs

Where a direction bites, the papers sent to the Secretary of State are the application and plans, the officer report with the recommendation and draft conditions, the committee resolution, the representations received, the development plan policies in conflict, and a statement of the material considerations relied on. Some directions also require the authority to confirm the publicity undertaken.

Your job as agent is to make the officer report capable of being sent as it stands. If the report fudges the conflict or omits the policy list, the department comes back with questions and the delay compounds. Supply a clear policy conflict table with the application, and the officer will usually lift it.

Browse the report types that a departure case typically needs, and read the companion note on what stops the eight week planning clock before you agree a determination date. If you are drafting the consultation response from the other side of the counter, the note on writing a planning consultation response covers the same ground in reverse.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What publicity does a departure application require?

Article 15 of the Development Management Procedure Order 2015 requires both a notice in a newspaper circulating in the locality and a site notice displayed for at least 21 days. That is a tier above the publicity for a standard minor or householder application, which can be handled by site notice or neighbour notification alone.

Does every departure go to the Secretary of State?

No. The Town and Country Planning (Consultation) (England) Direction 2009 replaced the old blanket requirement with a narrow list of categories, including certain Green Belt development, substantial out-of-centre retail and office schemes, and playing field development where the sports consultee maintains an objection. Most departures are now decided locally.

How much time does a departure add to the determination?

Expect four to five months rather than eight weeks on a minor application. The newspaper advertisement follows the paper's publication cycle, the 21 day period runs from the later notice, departures are usually reserved to committee rather than delegated, and any referral adds at least a further 21 days.

Can an application conflict with one policy and still accord with the plan?

Yes. The development plan is read as a whole, so conflict with a single criterion does not automatically make the proposal a departure. Conflict with a settlement boundary, a site allocation or a strategic housing policy usually does. If you disagree with the authority's classification, raise it in writing at validation.

Should the planning statement admit the policy conflict?

Yes. Section 38(6) of the Planning and Compulsory Purchase Act 2004 asks whether material considerations outweigh the conflict, so naming the policies breached and then setting out what outweighs them is the stronger structure. Reports that call a scheme a departure and then deny conflict read badly on appeal.

Sources and further reading

departure applicationdevelopment planpublicityplanning processsection 38

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Planning Process

View all →
Planning Process7 min read

Who the applicant should be on a leasehold site

Planning permission does not override a lease. A leaseholder applicant signs certificate B and serves notice on the freeholder, then still needs a licence to alter.

Read article →
Planning Process7 min read

Resubmitting after an invalid application notice

An invalidation notice is an administrative check, not a refusal. Supply the listed items as one package, and know when a local list requirement can be challenged.

Read article →
Planning Process7 min read

Section 106 completion and the decision timetable

Most of the delay between a committee resolution and a decision notice is conveyancing, not planning. The drafting gap, the parties to join and the timetable imposed.

Read article →
Planning Process7 min read

Online planning submission and the validation receipt

Submitting is not the same as being validated. What the council checks, the defects that invalidate householder applications, and the record to keep from the day you submit.

Read article →
Planning Process6 min read

Habitats screening where no European site is nearby

Being ten miles from the nearest designated site does not end the habitats question. Pathways travel further than people expect, and the council has to record its conclusion either way.

Read article →
Planning Process6 min read

Varying the time limit on an unimplemented permission

Section 73 is expressly barred from extending a time limit. That leaves two real options, and the one most developers overlook is making a lawful start before the deadline.

Read article →