Dealing with a new refusal reason in the appeal statement

6 min readBy PlanScope Editorial Team

Councils widen their case on appeal more often than they admit. How to object, answer in the alternative and build the costs record when a new refusal reason appears.

A council that refuses your application and then argues something different on appeal has not acted unlawfully, but it has handed you an advantage. The inspector decides the appeal as if the application had been made to them in the first instance, under section 79 of the Town and Country Planning Act 1990, so a new reason in the appeal statement can in principle be weighed. What the inspector cannot do is take it into account without giving you a fair chance to answer it.

So the response to a new ground is never outrage alone. It is a short procedural objection, a substantive answer in the alternative, and a note for the costs file.

Why new reasons appear after the decision

Three causes account for most of them.

The first is a thin decision notice. Article 35 of the Town and Country Planning (Development Management Procedure) (England) Order 2015 requires full reasons, clearly and precisely stated, with reference to the relevant policies. Where an officer has written two lines and the committee added a third from the floor, the council's appeal statement is the first time anyone sets the case out properly, and in doing so it widens.

The second is a change of hands. Appeal statements are often written by a different officer, sometimes a consultant, who reads the file afresh and spots a problem the original case officer did not pursue.

The third is tactical. A council defending a weak refusal reason on highway safety may bolt on landscape harm because it reads better at the public inquiry. That one is the easiest to isolate, because nothing in the committee report supports it.

Whether the inspector can consider the point

Yes, subject to fairness. The appeal is a rehearing, not a review of the council's decision, and the inspector must take into account any material consideration whether or not either party raised it. Inspectors regularly find against appellants on grounds the council never pleaded, and regularly dismiss reasons the council did plead.

The limit is procedural. Where a matter has not been put to a party, the inspector either gives that party the opportunity to deal with it or leaves it out of account. In written representations that usually means the Inspectorate allowing a further exchange. At a hearing or inquiry it means the point being identified at the case management stage and dealt with in evidence.

The practical consequence is that your objection should be framed as a request for a procedural remedy, not as a submission that the inspector lacks power.

Asking for the point to be disregarded

Write to the Inspectorate case officer within days of receiving the council's statement. Keep it to one page and make three moves.

  1. Identify the reason precisely, quoting the decision notice and the new wording side by side, so the difference is visible without cross-referencing.
  2. Show that the new matter formed no part of the decision: cite the officer report recommendation, the committee minute and the absence of any consultee objection on the point.
  3. Ask for a specific remedy, either that the matter be disregarded or that you be given time to respond to it.

Councils sometimes concede at this stage and confirm in writing that they rely only on the stated reasons. That letter is worth more than a paragraph of argument, because it fixes the issues in dispute and it is admissible if you later claim costs.

Answering substantively in the alternative

Always answer the point as well. An appellant who objects and stops there is relying on the Inspectorate to agree with the procedural argument, and that is a bad position to be in when the decision lands.

Structure the alternative answer so it cannot be read as acceptance that the matter is properly before the inspector. A short preface works: the appellant does not accept that this is a reason for refusal and asks that it be disregarded, but in case the inspector takes it into account, the position is as follows.

Then deal with it on the merits. If the new ground is heritage harm, produce the significance analysis you would have produced in a Heritage Statement at application stage. If it is noise, say what the measured background sound level was and which standard you assessed against. Thin assertions invite the inspector to split the difference.

Requesting a procedural change

A new ground sometimes makes the chosen procedure unsuitable. Written representations cannot test a disputed viability input or a contested trip rate, and a hearing gives the inspector a way to ask questions without the cost of an inquiry.

The Inspectorate can change the procedure on request at any stage before the event. Make the request early, explain what needs testing rather than simply asking for more time, and accept that a change will add weeks to the timetable. Where the new ground is narrow and documentary, resist the temptation: a written exchange is faster and the costs exposure is lower. The trade-offs between the three routes are set out in more detail in our note on choosing between written representations, a hearing and an inquiry.

Costs implications

An award of costs on appeal turns on unreasonable behaviour, and the national guidance on appeals treats introducing fresh reasons, or failing to substantiate a reason, as examples of it.

Two patterns attract awards. A council that pleads a new ground and then withdraws it after you have paid an expert to answer it has caused wasted expense. A council that pleads a new ground it never substantiates at all, relying on assertion, has failed to produce evidence to support its case.

Put the groundwork in at the time. Date-stamp the letter identifying the new ground, record the expert fee incurred in answering it, and refer back to both in the costs application. A costs claim assembled after the decision from memory rarely succeeds, and the related point about claiming costs where a refusal reason was vague applies with equal force here.

Illustrative example: a council refuses a nine-dwelling scheme on character grounds, then raises drainage capacity in its appeal statement. The appellant objects, answers the point with a one-page drainage note, and the council withdraws it two weeks before the hearing. The wasted fee for the drainage note is the measurable loss, and it is the figure the costs application should put forward.

Keeping the record straight

By the time an appeal is decided, the issues in dispute should be written down somewhere both parties have signed. On a hearing or inquiry that is the statement of common ground. On written representations it can be as simple as an exchange of emails confirming which reasons the council maintains.

Three habits help. Keep a single chronology of what was said when, with document references. Never let a new ground sit unanswered in correspondence, because silence reads as acceptance. And resist the urge to re-plead your whole case when the council widens its own, because a focused response is more persuasive than a longer one.

Where the new ground exposes a genuine evidential gap, consider whether withdrawing and resubmitting is the better commercial answer. An appeal you win on procedure but lose on substance has cost you nine months.

PlanScope drafts the supporting documents that close evidential gaps of this kind, and you can enter a postcode to see which reports your site is likely to need at planninglabs.co.uk.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Can an inspector consider a reason that was not in the decision notice?

Yes. Under section 79 of the Town and Country Planning Act 1990 the appeal is dealt with as if the application had been made to the inspector in the first instance, so any material consideration can be weighed. The constraint is fairness: a party must be given the opportunity to respond before a new matter counts against them.

How quickly should I object to a new ground?

Within days of receiving the council's statement, and before the written representations timetable closes. A late objection invites the Inspectorate to deal with the point by allowing extra time rather than excluding it, which is a weaker remedy. Put the objection in writing to the case officer and copy the council.

Should I answer a new ground I say is inadmissible?

Always answer it in the alternative. Preface the answer by recording that you do not accept the matter is properly before the inspector, then deal with it on the merits. Relying on the procedural objection alone leaves you with no substantive case if the inspector decides to take the point into account.

Does a new ground justify changing the appeal procedure?

Sometimes. Written representations cannot test a disputed trip rate, viability input or acoustic measurement, so a hearing may be the fairer route. Ask the Inspectorate early, explain what needs testing rather than asking only for more time, and accept that a change will add weeks to the programme.

Can I recover the cost of answering a reason the council later drops?

You can apply. National appeals guidance treats introducing fresh reasons, and failing to substantiate a reason, as behaviour that may be unreasonable. Awards are more likely where you identified the problem in writing at the time and can evidence a specific expert fee incurred in answering the point.

What if the council refuses to confirm which reasons it maintains?

Ask the Inspectorate to require a statement of the issues in dispute, which is standard on hearings and inquiries through the statement of common ground. On written representations, an exchange of emails recording the council's silence serves the same purpose and supports a later costs application.

Sources and further reading

planning appealsrefusal reasonsappeal costsplanning inspectorateappeal procedure

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Refusals and Appeals

View all →
Refusals and Appeals7 min read

Appeal timetables after the inquiry reform changes

Since the 2019 review, inquiry appeals run to an early fixed date and a managed timetable. What that moves forward, and how to staff and sequence the work.

Read article →
Refusals and Appeals6 min read

Appealing where a consultee objection was later withdrawn

A withdrawn consultee objection leaves the refusal reason without evidence. How to pin the council's position, build the costs record and choose between appeal and resubmission.

Read article →
Refusals and Appeals7 min read

Rebutting an ecology refusal where surveys were missing

An evidence refusal on ecology can usually be answered. The survey windows, the reasonable likelihood threshold and the condition wording to offer the inspector.

Read article →
Refusals and Appeals6 min read

Appeal site visits where internal access is needed

Nobody can make a neighbour let an inspector inside. When internal access really matters, how to request it, and the measured evidence that works when it is refused.

Read article →
Refusals and Appeals6 min read

Appealing where the refusal cites a policy not in the plan

A policy outside the development plan is a material consideration, not a requirement. How to frame the appeal, weigh emerging policy and handle a notice with no policy reference.

Read article →
Refusals and Appeals7 min read

The inspector's power to vary conditions on appeal

Section 79 lets an inspector treat the application as if made to them, so conditions can be rewritten, deleted or added. Including the risk in appealing a single condition.

Read article →