Prior approval or full application: how they differ
On prior approval a council may only consider the matters the class lists. Here is what that means for timing, conditions, refusal and fallback value.
Asking whether you need prior approval or planning permission is really asking which of two quite different procedures applies. A prior approval application accepts that permission already exists, granted by the General Permitted Development Order 2015, and asks the council to approve a short list of prescribed matters. A full application under section 70 of the Town and Country Planning Act 1990 asks the council whether to grant permission at all, weighing the whole development plan.
For a landlord or investor the practical differences are the fee, the timetable, the grounds on which a council can say no, and what you are left holding if it does.
What prior approval is
Several classes in Schedule 2 to the Order grant permission subject to a condition that the developer first applies to the authority for a determination as to whether its prior approval is required for specified matters. The permission is already in place. The application is about details.
Prior approval classes sit across the Order: householder extensions beyond the normal limits, agricultural buildings, demolition, telecommunications apparatus, and the commercial to residential and other change of use classes in Part 3. Each class names the matters the council may consider, and those lists are the core of the procedure.
That is the structural point. On a full application the council weighs everything that is material. On a prior approval it may only consider what the class permits it to consider.
The limited matters a council may consider
Take a Part 3 change of use class as the example. The matters typically specified include transport and highways impacts, contamination risk, flooding risk, noise impacts on the intended occupiers, and in some classes the impact on the local provision of a particular service or the adequacy of natural light in habitable rooms. What is absent is as telling as what is present: there is usually no general design test, no loss of employment land test and no requirement to comply with housing mix policies.
Councils that dislike a particular class sometimes stretch the matters they are allowed to consider. A refusal that relies on harm to the character of the area, where the class does not list design, is vulnerable. Read the class, list the matters, and structure the submission to answer each one in turn with its own heading and its own evidence.
Some classes also require the developer to serve notice or to let the authority consult neighbours. The householder larger extension procedure works that way, and a neighbour's objection within the notification period is what brings the council's judgement into play at all.
Where the class requires evidence about transport, a short Transport Statement, chosen from the 66 report types, addressing trip generation, access and parking is more use than a paragraph of assertion, because the officer has to make a finding on the specified matter and cannot approve by default if there is nothing to read.
The deemed approval period
Most prior approval classes carry a period, commonly 56 days from a valid application, within which the authority must notify its decision. If it does not, the development may be carried out in accordance with the application. Some classes use a different period, and the householder larger extension procedure has its own timetable, so check the class rather than assuming 56 days.
Deemed approval sounds like a gift and behaves like a trap:
- The period runs from receipt of a valid application, so a missing fee or plan resets the clock.
- The development must then be carried out in accordance with the application as submitted, with no latitude for the changes that a full permission could absorb by condition.
- Any conditions in the class itself still apply, including time limits for completion in some change of use classes.
- Proving the period expired without a decision means keeping the submission receipt and the correspondence.
Chasing the authority for a decision is sometimes against your interest and sometimes essential. If the scheme is finely balanced, silence is a result. If you need certainty for a lender, a written decision is worth waiting for.
Conditions, and what they attach to
On a full permission, conditions are imposed by the authority and tailored to the development. On permitted development, the conditions are in the Order, the same for every site, and they are the limitations that make the class work: height limits, floorspace caps, the requirement that materials match, time limits for completion, and restrictions on further development.
Prior approval decisions can also carry conditions where the class allows, usually tied to the specified matters, such as a condition on the approved access arrangement or on a noise mitigation scheme. A condition going beyond the specified matters is open to challenge.
The practical consequence is that permitted development is less flexible once built. Breach a limitation in the Order and the development is unauthorised in its entirety, not merely in breach of a condition, because the permission the Order grants was conditional on those limits. A single qualifying criterion, such as a minimum period of prior vacancy or a floorspace cap, can decide whether the class is available at all.
Why a refusal is not a refusal of permission
If a council refuses prior approval, it has not refused planning permission. It has found that the prescribed matters are unacceptable, or that the proposal does not meet the class's qualifying criteria. The difference matters in three ways.
You can reapply with a revised scheme addressing the point, often quickly and cheaply, because the principle is not in dispute. You can appeal. Or you can apply for full planning permission for the same or a better scheme, with the prior approval right as a fallback argument, since a scheme that could lawfully be built under the Order is a relevant consideration when the council assesses an alternative.
That last route is the one investors underuse. A full application for a better designed conversion, with the permitted development scheme set out alongside it as the realistic alternative, often secures a more valuable consent than the class would have allowed.
| Feature | Prior approval | Full application |
|---|---|---|
| Source of permission | Granted by the General Permitted Development Order 2015 | Granted by the authority under section 70 |
| Matters considered | Only those specified in the class | All material considerations against the development plan |
| Typical period | Commonly 56 days, with deemed approval on expiry | 8 weeks for minor, 13 for major, extensions by agreement |
| Conditions | Set by the Order, plus limited conditions on specified matters | Tailored by the authority |
| Flexibility after consent | Low, since limitations are jurisdictional | Higher, through section 73 and section 96A |
| Effect of refusal | Permission not refused; class rights and appeal remain | Permission refused; appeal or new application |
Appeal rights compared
Both routes carry a right of appeal to the Planning Inspectorate against refusal. The difference is the scope of the appeal. On a prior approval appeal, the inspector considers the specified matters and the qualifying criteria, which is a narrow and often quick written representations case. On a full application appeal the whole planning balance is open, which takes longer and costs more.
Time limits differ by case type, so check the current deadline for the appeal you are making rather than relying on a remembered figure. Householder appeals run to a shorter timetable than other cases.
Deciding which route to use
Work through four questions. Does the site actually qualify for the class, on every criterion, including any vacancy, size or prior use requirement? Do the specified matters give the council enough room to refuse on the issues your site has? Is the scheme the class allows the scheme you want to build? And do you need a consent that a lender or purchaser will recognise without explanation?
Where the class fits and the scheme is modest, prior approval is faster and cheaper. Where the site has a real constraint within the specified matters, or the class forces a compromised layout, a Planning Statement supporting a full application with the permitted development fallback stated plainly is usually the better investment.
PlanScope can draft the planning, transport and supporting documents for either route from your site details and the answers in the guided flow, with the address checked against flood, heritage and designated site data as you go.
This is general guidance, not legal advice. A Lawful Development Certificate is the only formal way to confirm that works are lawful, so check the position with your local planning authority or a qualified professional before relying on it.
PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
What is the difference between prior approval and planning permission?
Prior approval applications accept that permission is already granted by the General Permitted Development Order 2015 and ask the council to determine specified matters. A full application under section 70 of the Town and Country Planning Act 1990 asks whether to grant permission at all, with every material consideration in play against the development plan.
How long does a prior approval take?
Many classes use a period of 56 days from a valid application, after which the development may proceed in accordance with the application if no decision has been notified. Some classes use different periods, and the householder larger extension procedure has its own timetable, so check the wording of the class.
Can a council refuse prior approval on design grounds?
Only where design falls within the matters the class specifies, which it often does not. A refusal resting on harm to the character of the area, where the class lists only transport, contamination, flooding and noise, is vulnerable on appeal. Read the class, list the matters, and answer each one separately in the submission.
Is a refusal of prior approval a refusal of planning permission?
No. It is a finding that the specified matters are unacceptable or that the qualifying criteria are not met. You can revise and reapply, appeal, or apply for full planning permission with the permitted development right as a fallback, which is often the route to a more valuable consent.
Which route gives more flexibility after consent?
A full permission. Conditions can be varied under section 73 and details amended under section 96A. Permitted development limitations are jurisdictional, so exceeding a height, floorspace or time limit in the Order makes the whole development unauthorised rather than merely in breach of a condition.