Schedule 1 or Schedule 2 development under the EIA rules
Almost every housing and commercial scheme sits in Schedule 2 of the EIA Regulations 2017, so screening is what decides it. The thresholds, sensitive areas and cumulation.
Whether your scheme is Schedule 1 or Schedule 2 EIA development decides one thing immediately: Schedule 1 means environmental impact assessment is mandatory with no argument, and Schedule 2 means it depends on whether the development is likely to have significant effects on the environment. Almost everything a housebuilder or commercial developer brings forward in England sits in Schedule 2, so the question that matters in practice is how screening works and what tips a borderline case.
The two schedules are in the Town and Country Planning (Environmental Impact Assessment) Regulations 2017. Read the regulations themselves rather than a summary, because the thresholds are precise and the sensitive area rule changes the answer on a lot of sites.
Mandatory assessment against case-by-case screening
Schedule 1 lists descriptions of development where assessment is required because of what the project is. Crude oil refineries, nuclear installations, integrated chemical works, motorways and special roads, thermal power stations with a heat output of 300 megawatts or more, airports with a basic runway length of 2,100 m or more, quarries and open-cast mines where the site surface exceeds 25 hectares, and intensive poultry rearing above 85,000 broiler places all appear there. If your project answers to one of those descriptions, there is no screening stage and no discretion.
Schedule 2 works differently. Column 1 gives a description of development and column 2 gives an applicable threshold or criterion. Meeting the threshold does not mean assessment is required. It means the development has to be screened, and the authority then decides whether the likely effects reach the level that requires assessment.
| Schedule 1 | Schedule 2 | |
|---|---|---|
| Trigger | The description alone | Description plus threshold, or a sensitive area |
| Assessment | Mandatory | Only where screening identifies effects at that level |
| Screening opinion | Not needed | Required before the application is determined |
| Determination period | 16 weeks | 16 weeks where assessment is required, otherwise the normal period |
Reading the Schedule 2 thresholds
For most development in built-up areas the relevant entry is urban development projects, which covers housing, shopping centres, car parks, sports stadiums, leisure centres and multiplex cinemas. Three limbs apply, and meeting any one of them brings the scheme into Schedule 2:
- the development includes more than 1 hectare of urban development that is not dwellinghouse development
- the development includes more than 150 dwellings
- the overall area of the development exceeds 5 hectares
Industrial estate development has its own entry with a 5 hectare threshold. Water management, waste, extraction, agriculture, energy and infrastructure categories each have separate figures, and the numbers in one category tell you nothing about another.
So a 148 unit scheme on 4 hectares is outside the thresholds on every limb, and a 149 unit scheme on 5.2 hectares is inside on the third. The gap between those two schemes is not environmental, which is exactly why screening exists as a separate judgement rather than a calculation.
Sensitive areas remove the threshold
This is the limb that catches people. Regulation 2 defines Schedule 2 development as development of a description in column 1 that either meets the applicable threshold or criteria in column 2 or is in a sensitive area.
Sensitive area covers Sites of Special Scientific Interest, National Parks, National Landscapes, World Heritage Sites, scheduled monuments, European protected sites and the Broads. Any part of the application site falling within one of those means the threshold drops away and the scheme requires screening however small it is.
Check this before you conclude a scheme is out of scope. A 20 unit site with one corner clipping an SSSI boundary is Schedule 2 development, and so is a farm building conversion inside a National Park. The screening opinion may well conclude that there are no likely effects at that level, and that opinion is what you need on file.
Where protected species are part of the picture, the screening work and the ecology work overlap, and it is worth settling whether you are relying on a protected species licence or on standing advice before the screening request goes in.
Cumulative effects and the selection criteria
Schedule 3 sets out the criteria the authority applies. The characteristics of the development come first, including its size and design, the cumulation with other existing or approved development, the use of natural resources, waste production, pollution and nuisance, and the risk of major accidents. Then the location, covering existing land use, the quality and regenerative capacity of natural resources, and the absorption capacity of the natural environment. Then the characteristics of the likely effects themselves.
Cumulation is the criterion that most often turns a negative screening opinion into a positive one. An authority looking at your 120 unit scheme will take account of the 90 units already permitted on the adjoining field and the employment allocation behind both. The combined traffic, drainage and ecological effects are the ones in play, and the fact that each scheme individually sits below a threshold is beside the point.
Do the cumulation work yourself before you ask for an opinion. Pull the permissions and allocations within a sensible radius, state them, and explain why the combined effects do or do not reach that level. An authority given that analysis tends to engage with it. An authority left to assemble it alone tends to be cautious.
Dividing a project and why it fails
Splitting a site into phases, or into separate applications by separate companies, in the hope of staying under a threshold does not work. The courts have consistently required the authority to consider the whole of the project rather than an artificially divided part of it, and the regulations are read in a way that gives effect to that.
The practical test is whether the parts are functionally interdependent. Two parcels sharing a single access road, a single drainage outfall and a single phasing plan are one project whatever the application numbers say. But two separate schemes brought forward years apart by unconnected owners are not.
Where the division is real, document why. Separate ownership, separate access, separate markets and separate timing are the features that make the case, and they are much easier to establish contemporaneously than three years later at an inquiry.
Who can prepare the Environmental Statement
Regulation 18 requires the Environmental Statement to be prepared by competent experts, and it requires the statement to include a note of the relevant expertise or qualifications of those experts. That is a legal requirement rather than a matter of good practice.
An Environmental Impact Assessment draft produced from structured data and policy text is a useful way to set up the chapter structure, the scoping position and the list of topics the authority will expect. It is a starting point for the competent experts who have to prepare and sign the statement, not a substitute for them. The same applies to the ecology baseline work feeding into it, where a Preliminary Ecological Appraisal usually comes first.
Screening a borderline scheme
Ask for a formal screening opinion under regulation 6 rather than forming a view internally. The authority has three weeks to adopt one, or longer if agreed in writing, and a negative opinion is the document that protects the permission against challenge later.
A screening request that gets a clean answer contains the site area and unit numbers against each relevant limb, the designations within and adjoining the site with distances, a cumulation schedule of nearby permissions and allocations, a short topic-by-topic note on likely effects, and the mitigation already designed in. Keep it to a dozen pages. A request the size of an Environmental Statement invites the conclusion that one is needed.
If the opinion comes back positive, request a scoping opinion under regulation 15 straight away. The authority has five weeks, and the scope it sets determines your survey programme, which in turn sets your earliest submission date. On a site with ecology seasons in it, that single document can move a start on site by a year.
Enter your postcode on PlanScope to see which reports a site of your scale and designation profile is likely to need.
This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. For specialist technical reports, qualified professional input may be required. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
What is the difference between Schedule 1 and Schedule 2 EIA development?
Schedule 1 development requires environmental impact assessment because of what the project is, with no screening stage and no discretion. Schedule 2 development has to be screened, and assessment follows only where the authority concludes the development is likely to have effects on the environment at a level that requires it, judged against the Schedule 3 criteria.
What is the housing threshold for Schedule 2 EIA?
Under the urban development projects entry, a scheme falls within Schedule 2 if it includes more than 150 dwellings, includes more than 1 hectare of urban development that is not dwellinghouse development, or has an overall area exceeding 5 hectares. Meeting any one limb is enough to require a screening opinion.
Does a small site in a National Park need EIA screening?
If it answers to a description in column 1 of Schedule 2, yes. Regulation 2 treats development in a sensitive area as Schedule 2 development regardless of the column 2 threshold, and sensitive areas include National Parks, National Landscapes, SSSIs, World Heritage Sites, scheduled monuments and European sites. The opinion may still be negative.
Can a scheme be split into phases to avoid EIA?
No. The courts have required authorities to consider the whole of the project rather than an artificially divided part of it. The practical test is functional interdependence, so parcels sharing one access, one drainage outfall and one phasing plan are one project. Where a division is real, record the separate ownership, access and timing at the time.
Who has to prepare an Environmental Statement?
Regulation 18 of the EIA Regulations 2017 requires the statement to be prepared by competent experts and to include a note of their relevant expertise or qualifications. A structured draft can establish the chapter structure and the scoping position, but the assessment itself has to come from those qualified experts.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.