Building Regulations approval and planning permission
Two separate consents, two separate processes. What planning controls, what building control controls, and why one is no defence against the other.
Planning permission and Building Regulations approval are two separate consents from two separate processes, and most home projects need both. Planning asks whether the work should happen at all: the use of the building, its size, how it looks, what it does to your neighbours. Building control asks whether the work is built properly: structure, fire safety, insulation, drainage, ventilation, stairs, glazing. Getting planning permission tells you nothing about whether your drawings meet the technical standards, and a building control sign-off is no defence to a planning enforcement notice.
The practical risk is assuming that one covers the other. It does not, in either direction.
Two regimes with different questions
Planning control comes from the Town and Country Planning Act 1990. The council's planning department decides whether your proposal is acceptable development in that location, judged against the adopted local plan and national policy.
Building control comes from the Building Act 1984 and the Building Regulations 2010. The standards themselves sit in the Approved Documents, lettered A to S, covering structure, fire safety, contaminated ground, sound, ventilation, drainage, fuel and power, access, overheating, electrical safety and electric vehicle charging among others.
Different decision-maker, different test, different paperwork, different fee. A planning officer will not look at your lintel sizes. A building control surveyor will not care whether your extension overshadows next door.
What each regime actually controls
| Question | Decided by | Regime |
|---|---|---|
| Can I build a two-storey rear extension here at all | Planning department or permitted development rules | Planning |
| Is the extension too close to the boundary for fire spread | Building control | Building Regulations Part B |
| Will the extension block my neighbour's light | Planning department | Planning |
| Are the foundations deep enough for the clay soil | Building control | Building Regulations Part A |
| What the extension looks like from the street | Planning department | Planning |
| Insulation levels in the new walls and roof | Building control | Building Regulations Part L |
| Where the new soil pipe connects | Building control, and the water company | Building Regulations Part H |
| Whether I can drop the kerb to the highway | Highway authority | Highways Act 1980 |
The dropped kerb is a good illustration of a third regime existing alongside both, and the difference between a section 184 licence and a section 278 agreement catches people out on exactly that point.
Permitted development still needs building control
This is the single most expensive misunderstanding in householder work.
If your extension, loft conversion or garage conversion falls within permitted development, you do not need a planning application. You still need Building Regulations approval, because the two regimes are unrelated. A loft conversion is the clearest case: it almost always needs building control attention for the floor structure, the stair, escape windows, fire doors and insulation, whether or not planning permission was required.
A small number of works are exempt from the Building Regulations, set out in Schedule 2 to the Regulations. Detached single-storey buildings under 30 m² with no sleeping accommodation, ground-level conservatories and porches under 30 m² with the existing separation retained, and carports open on at least two sides under 30 m² are the common ones. Garden offices with a bed in them are not exempt, whatever the supplier's brochure says.
Fees, timescales and who decides
Planning fees come from a national schedule that is indexed annually, so take the figure from the current schedule rather than an older example. A householder application is normally determined in eight weeks, with a six-month right of appeal if refused.
Building control is a choice between two routes. The local authority's building control team, or a private registered building control approver, which is what approved inspectors became under the Building Safety Act 2022 reforms. Charges are set by each provider rather than nationally, so they are worth comparing.
Within the local authority route there are two application types. A full plans application has your drawings checked before work starts, with a decision normally within five weeks. A building notice skips the plan check and relies on site inspection, which suits simple work by a builder you trust and is risky on anything structural.
Taller and more complex buildings are different again. Buildings at 18 m or more, or seven storeys or more, fall under the Building Safety Regulator and a gateway process rather than ordinary building control.
Completion certificates and why they matter
Finish the work and the building control body issues a completion certificate. That certificate is the document a buyer's conveyancer asks for, and its absence is the reason thousands of sales get held up every year.
If work was done without approval, two routes exist. A regularisation certificate can be applied for retrospectively, which usually means opening up parts of the work for inspection. Or the buyer accepts an indemnity policy, which covers the risk of enforcement rather than confirming the work is safe.
Keep the certificate with the deeds, along with any electrical installation certificate, gas safety record and structural calculations. Scan them.
Enforcement differences
The two regimes enforce differently, and the time limits are not the same.
Under the Building Act 1984, carrying out work that contravenes the Regulations is an offence, and the local authority can serve a notice requiring the work to be altered or removed, exercisable within a period measured from completion of the work. Under planning law, the authority can serve an enforcement notice against unauthorised development, with immunity arriving after a statutory period. The Levelling-up and Regeneration Act 2023 moved those planning periods towards ten years in England, with commencement staged, so check the current position before relying on any date.
The two clocks run independently. Work can be immune from planning enforcement and still be a Building Regulations contravention that no certificate will ever cover.
Running both in parallel
The sensible sequence for a householder project is this.
- Establish whether the work is permitted development or needs an application, and consider a lawful development certificate if the answer is finely balanced
- Get the design to a stage where a planning decision is possible, with plans, elevations and a block plan
- Submit the planning application, with a short Planning Statement where the scheme is contentious or in a conservation area
- While planning runs, develop the technical design and decide between full plans and a building notice
- Submit the building control application once the planning position is settled, so you are not paying twice for a plan check on a design that has to change
- Notify your neighbours under the Party Wall etc. Act 1996 if you are building on or near the line of junction, which is a third regime again
- Book inspections at the stages your building control body specifies, and get the completion certificate before the final payment to the builder
Doing step five too early is the common waste. Doing step seven late is the common regret.
Illustrative example: a single-storey rear extension of 3.8 m depth on a semi-detached house outside a conservation area. It falls within permitted development, so no planning application is needed. It still needs a building control application, foundations designed for the nearby lime tree, Part L insulation levels in the new fabric, a party wall notice to one neighbour, and a completion certificate at the end. Four processes, one of which is not planning at all. This example is illustrative only.
Where you do need supporting documents for the planning side, you can browse all 66 report types and see what each costs before you commit to anything.
This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. A Lawful Development Certificate is the only formal way to confirm that works are lawful. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
Do I need Building Regulations approval if my work is permitted development?
Yes. The two regimes are unrelated. Permitted development means no planning application is required, and it says nothing about technical standards. A loft conversion, an extension or a garage conversion will still need building control attention for structure, fire safety, stairs, escape windows, insulation and drainage.
Is a completion certificate the same as planning permission?
No. A completion certificate confirms the work was inspected and found to comply with the Building Regulations. It gives no planning authorisation at all. A buyer's conveyancer will ask for it, and its absence commonly delays sales, so keep it with the deeds alongside electrical and gas records.
What is the difference between full plans and a building notice?
A full plans application has your drawings checked before work starts, with a decision normally within five weeks, which gives certainty on structure and fire safety. A building notice skips the plan check and relies on site inspection. It suits simple work and carries real risk on anything structural or unusual.
Which works are exempt from the Building Regulations?
Schedule 2 to the Regulations lists them. The common exemptions are detached single-storey buildings under 30 square metres with no sleeping accommodation, ground-level conservatories and porches under 30 square metres where the existing separation is kept, and carports open on at least two sides under 30 square metres.
Can the council enforce against old unauthorised building work?
The two regimes have separate time limits. Under the Building Act 1984 a contravention is an offence and a notice can require alteration or removal within a period from completion. Planning immunity arrives after its own statutory period, which the Levelling-up and Regeneration Act 2023 moved towards ten years in England.
Should I apply for planning and building control at the same time?
Usually not. Settle the planning position first, because a design change forced by the planning process means paying twice for a plan check. Develop the technical design in parallel, then submit the building control application once the planning outcome and the final layout are known.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.