Section 184 licence or a section 278 agreement

7 min readBy PlanScope Editorial Team

The test is what you are doing to the highway, not how many houses you are building. One dwelling can need a section 278 agreement while nine may not.

The dividing line between a section 184 licence and a section 278 agreement is the nature of the works, not the size of your scheme. If you are crossing the footway or verge to reach your plot, that is a vehicle crossing under section 184 of the Highways Act 1980. If you are changing the highway itself, by moving a kerb line, forming a bellmouth, altering drainage, widening a footway or adding a crossing point, that is works in the highway and it needs an agreement under section 278.

One house can need a section 278 agreement. A scheme of nine houses served by an existing estate road might need nothing more than a section 184 licence. People get this the wrong way round constantly, and the cost difference between the two routes runs into tens of thousands.

What a section 184 licence covers

A vehicle crossing: the construction or alteration of a crossing over a footway or verge so that vehicles can get from the carriageway onto private land. In everyday terms, a dropped kerb.

The process is administrative. You apply to the highway authority, usually online, pay a fee, and the authority either carries out the work itself or specifies it and permits an approved contractor to do it. The authority decides the width, the kerb type, the construction build-up and whether the position is acceptable, and it will refuse where visibility is inadequate or where the crossing would sit too close to a junction or a traffic signal.

Three points worth knowing before you apply. The authority's decision on a crossing is separate from planning permission, so a permission showing an access does not guarantee the crossing will be licensed. Works to a verge may involve a statutory undertaker's apparatus beneath it, which brings its own costs and timescales. And carrying out the crossing without the licence is an offence, with the authority able to reinstate the kerb and recover the cost from you.

What a section 278 agreement covers

Section 278 allows the highway authority to enter into an agreement for the execution of works in the highway at the developer's expense where the authority is satisfied the works will benefit the public. It is used for new junctions and accesses beyond a simple crossing, carriageway widening, footway and cycleway alterations, traffic signals, pedestrian crossings, traffic calming, bus stop relocation, street lighting changes and highway drainage works.

It is a legal agreement rather than a permit, and it carries the apparatus you would expect of one. Technical approval of the design against the authority's standards. A road safety audit process. A surety bond or cash deposit covering the works. Commuted sums where non-standard materials will cost more to maintain. The authority's legal fees. Supervision and inspection fees during construction. And insurance requirements on both the designer and the contractor.

The design has to be produced by a suitably qualified highway designer working to the authority's standards, and the authority checks it rather than designing it for you. Submitting a sketch and asking the authority to develop it is not how the process works, though many applicants start there.

The cost structure of each

Element Section 184 licence Section 278 agreement
Application or legal basis Licence application and fee Negotiated legal agreement
Who designs Authority specifies the detail Your highway designer, to authority standards
Technical approval Not separately charged Checking fee, often related to works value
Safety audit Not normally required Audit stages required, with designer responses
Security None Bond or cash deposit
Future maintenance Standard materials adopted Commuted sum where materials are non-standard
Legal fees None Authority's legal costs, payable by you
Supervision Authority or approved contractor carries out works Inspection and supervision fees during construction
Typical duration Weeks Several months, sometimes a year

Nobody can give you a reliable national figure for either, because fees are set locally and the works cost depends entirely on what is being built. What you can do is ask the highway authority for its current fee scales and its standard agreement at pre-application stage, which both exist as published documents in most authorities.

The structural point is that a section 278 is a project in its own right, with its own design team, programme and risk. Treating it as a line in the build budget understates it.

The other highway consents you may need

Four more sit alongside these two and they catch people out in a different way.

Section 38 of the Highways Act 1980 is the adoption agreement for new streets that will be maintained at public expense. On a scheme of several dwellings served by a new road, a section 38 and a section 278 often run together: the new street is adopted under section 38 and its junction with the existing highway is built under section 278.

Section 50 of the New Roads and Street Works Act 1991 licenses the placing or altering of apparatus in the street, which is what you need if you are laying a private drain or duct under the public highway rather than relying on a statutory undertaker.

Section 171 of the Highways Act 1980 covers licences to deposit building materials in the highway or to make a temporary opening in it. Section 169 covers scaffolding licences and section 139 covers skip permits. These are short-term consents with short lead times, and they are usually the contractor's responsibility rather than yours, which is a good reason to say so in the building contract.

Where your works also affect a public sewer, the parallel question of whether you need a build-over agreement or a diversion follows a similar structure, and the reasoning in build over agreement or a sewer diversion applies in the same way: the test is what you are doing to the asset, not how big your scheme is.

Programme, and the Grampian condition

Where off-site highway works are needed, the planning permission will almost always carry a condition preventing development or occupation until the works are complete or until the agreement is in place. That is a Grampian condition, and it is lawful because it requires something on land outside the site without purporting to grant permission for it.

Read the wording carefully. A condition requiring the agreement to be entered into before development starts is manageable. A condition requiring the works to be completed before development starts can be unworkable, because the access is usually how you get plant onto the site. Ask for the trigger to be first occupation rather than commencement where that is defensible, and raise it before the decision issues.

The construction phase has its own documentation. Where the authority is concerned about plant movements, wheel washing and haul routes, a Construction Traffic Management Plan is normally required by condition, and it should be consistent with the section 278 programme rather than written separately.

Deciding which one you need

  1. Draw the access and mark the extent of land that is public highway. The highway boundary is rarely where the fence is, and the authority holds the definitive record.
  2. Ask whether anything within the highway changes. Kerb lines, levels, drainage, signs, lighting, road markings, surfacing beyond the crossing itself.
  3. If nothing in the highway changes except the crossing build-up, you are in section 184 territory.
  4. If anything else changes, assume section 278 and ask the highway authority to confirm at pre-application stage, in writing.
  5. Where a new street will be adopted, add section 38 and programme the two together.
  6. Price the design, the audit, the bond, the legal fees and the supervision separately from the construction cost.

Step four is the one to pay for. A written pre-application answer from the highway authority on which route applies is the single most useful document you can hold on a small scheme with a new access, and it costs a fraction of designing to the wrong standard.

A short Transport Statement submitted with the application, setting out the access arrangement, the visibility provided and the consents you expect to need, also helps the case officer see that the highway position is understood. Where utilities need diverting, a Utilities Assessment covers the same ground for the service providers.

This is general guidance, not legal advice. Check the position with your highway authority and local planning authority before relying on it.

Enter your postcode on PlanScope to see which reports and documents your access arrangement is likely to need. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Which consent do I need for a dropped kerb?

A vehicle crossing licence under section 184 of the Highways Act 1980. You apply to the highway authority, pay a fee, and the authority either carries out the work or specifies it for an approved contractor. The authority sets the width, kerb type and construction, and can refuse where visibility or the position is unacceptable.

When does a scheme need a section 278 agreement?

Whenever the highway itself changes beyond a simple crossing: a new bellmouth or junction, kerb line alterations, carriageway or footway widening, drainage works, signals, crossing points, lighting or traffic calming. One dwelling with a new access onto a classified road can trigger it, and the number of units is not the test.

What does a section 278 agreement cost?

There is no national figure because fees are set locally and the works cost depends on the design. Budget separately for the highway design, technical approval checking fee, road safety audit, surety bond or deposit, commuted sums for non-standard materials, the authority's legal fees and inspection and supervision charges during construction.

Does planning permission authorise the highway works?

No. Planning permission deals with the development on your land. Works in the public highway need their own consent, and a permission showing an access does not guarantee the crossing will be licensed or the agreement granted. Carrying out highway works without consent is an offence and the authority can reinstate at your cost.

What is a Grampian condition on highway works?

A condition preventing development or occupation until off-site works are secured or complete. It is lawful because it requires something on land outside the site without granting permission for it. Negotiate the trigger before the decision issues, because a condition requiring completion before commencement can block your own site access.

Sources and further reading

highwayssection 278section 184dropped kerbaccessself-build

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Comparisons

View all →
Comparisons7 min read

Site notice, neighbour letter or press advertisement

Councils choose between a site notice, letters to neighbours and a newspaper advertisement according to the type of application. For some applications the law requires two of them.

Read article →
Comparisons7 min read

Parking survey or compliance with parking standards

Adopted standards tell the council what your scheme should provide. A parking survey tells it what the street can actually absorb. Converted flats usually need the second.

Read article →
Comparisons6 min read

Travel plan or delivery and servicing plan

People go in the travel plan, vehicles go in the servicing plan. The content, conditions and monitoring that separate the two documents.

Read article →
Comparisons6 min read

Building Regulations approval and planning permission

Two separate consents, two separate processes. What planning controls, what building control controls, and why one is no defence against the other.

Read article →
Comparisons6 min read

Noise assessment or extraction statement for a kitchen

Plant noise and cooking odour are assessed by different people against different standards. Which document answers which objection on a restaurant or takeaway application.

Read article →
Comparisons7 min read

Prior approval or full application: how they differ

On prior approval a council may only consider the matters the class lists. Here is what that means for timing, conditions, refusal and fallback value.

Read article →