Prior approval refusals and the appeal route
An authority deciding a prior approval can only refuse on the matters the class lists, and if it misses the determination period the development may proceed. Here is how to tell which kind of refusal you have.
A refusal of prior approval is appealed to the Planning Inspectorate under section 78 of the Town and Country Planning Act 1990, in the same way as a refusal of planning permission, and the appeal has a strong chance where the authority has refused on a matter the relevant class does not let it consider. That is the whole point of the prior approval structure. The development is already permitted by the General Permitted Development Order 2015, and the authority is only deciding the limited matters the class lists.
The second thing worth knowing is that most prior approval classes carry a deemed approval. If the authority does not notify you of its decision within the period set by the class, the development may proceed, and a refusal issued after the period has expired is worth nothing.
What a prior approval decision does and does not decide
Prior approval is not planning permission. The permission comes from the Order, subject to the limitations and conditions in the class. The prior approval step asks the authority to approve specified details, and it can only refuse on the grounds the class gives it.
That produces two very different kinds of refusal, and they need different responses.
A refusal saying the proposal does not meet the limitations or conditions of the class at all. For example, a building that was not in the qualifying use for the required period, or a floor area above a stated limit. This is not a judgement about the prescribed matters, it is a statement that the right does not apply, and if the authority is correct the appeal fails.
A refusal on one of the prescribed matters, such as transport impact or flood risk. This is a planning judgement and an appeal is a straightforward merits argument.
Sort the refusal into one of those two categories before doing anything else, because the first needs a factual case about the building's history and the second needs a planning case about effects.
The matters the authority may consider in each class
Each class sets its own list, and the lists are short. Read the class as it currently stands rather than relying on a summary, because the prescribed matters have been amended several times.
| Class, by subject | Typical scope of prescribed matters |
|---|---|
| Commercial to residential under Part 3 | Transport and highways, contamination, flooding, noise from commercial premises, natural light to habitable rooms, and in a conservation area the effect of losing a ground floor use |
| Larger householder extensions under Part 1 | The effect on the amenity of adjoining premises, following the neighbour consultation procedure |
| Upward extensions under Part 20 | Transport, air traffic and defence safeguarding, contamination, flooding, external appearance, amenity of neighbours and the provision of adequate natural light |
| Telecommunications under Part 16 | Siting and appearance |
| Agricultural buildings under Part 6 | Siting, design and external appearance of the building |
Natural light is the one that catches residential conversions. The requirement is about adequate natural light in all habitable rooms, and a refusal on that ground is a technical matter answered with a daylight study rather than an assertion that the rooms have windows.
Refusals on matters outside the prescribed list
Authorities do sometimes refuse on grounds outside the list. Common examples are the loss of employment floorspace, the absence of affordable housing, the lack of amenity space, parking standards where highways is not a prescribed matter for that class, and general design objections where external appearance is not listed.
Where that happens, the appeal statement should do three things. Quote the class and its prescribed matters. Show that the stated reason for refusal falls outside them. Then deal with the prescribed matters properly anyway, because the inspector will determine the application on those matters and a bare procedural point leaves them nothing to grant on.
Local plan policy cannot add a prescribed matter. A development plan policy requiring, say, a minimum amenity standard does not become a ground of refusal for a prior approval application, although national space standards and the natural light requirement operate within the class itself where the class says so.
Deemed approval where the period expires
The determination period is set by the class. Commonly it is 56 days for change of use classes and upward extension classes, and 42 days for the larger householder extension procedure, running from the date the authority receives a valid application.
Where the authority fails to notify its decision within the period, the development may proceed in accordance with the details submitted. Three practical consequences follow.
First, you need to know exactly when the period started, which is why submission records matter. Second, the development must then be carried out in accordance with what you submitted, so the drawings and details in the application become the approved scheme. Third, the conditions in the class still apply, and deemed approval does not relieve you of them.
Do not rely on a deemed approval without checking the position carefully. Where the authority wrote within the period asking for further information, or where the application was arguably invalid because a required document or fee was missing, the period may not have run as you think. This is general guidance rather than legal advice, and a Lawful Development Certificate under section 192 is the only formal way to confirm that the works would be lawful.
Appealing to the Planning Inspectorate
The appeal route is section 78 and the procedure is almost always written representations, which suits prior approval appeals because the issues are narrow.
Time limits matter. The general limit for a section 78 appeal is six months from the date of the decision notice, and householder appeals have a much shorter window of 12 weeks, so a refusal of a larger householder extension prior approval needs quick action. Check the current limits on the appeals service before relying on either figure.
What makes these appeals succeed:
- A clear statement of the class relied on, with the limitations and conditions addressed one by one.
- Evidence on the qualifying facts where they are disputed, such as rates records, tenancy agreements and photographs for a prior use period.
- Technical evidence on each prescribed matter, proportionate to the objection. A daylight study, a transport note, a flood risk screening.
- A direct response to the reason for refusal, identifying where it goes beyond the prescribed matters.
What makes them fail is submitting the appeal on the same material that was refused, with a covering letter arguing the authority was wrong. If the refusal identified a gap, fill it.
Resubmitting rather than appealing
A resubmission is often faster and sometimes the only sensible route. Where the refusal identified a genuine shortcoming that the design can fix, a revised application answers it in 56 days rather than the several months an appeal takes.
Weigh four things. Whether the defect is fixable by design. Whether the authority has indicated what would be acceptable. The fee, which for prior approval is a fixed amount set by the national fee regulations and indexed, so check the current schedule rather than assuming. And whether a fresh application restarts a clock you would rather not restart, such as a vacancy period or a time limited class.
Where the refusal is procedurally wrong but the scheme also has a real problem, the pragmatic answer is often to resubmit with the problem fixed and keep the procedural argument in reserve. A Planning Statement that addresses the prescribed matters squarely, with the supporting evidence attached, is what prevents the second refusal.
Records that prove the submission date
Deemed approval depends entirely on dates, so treat the paperwork as evidence from the outset.
Keep the submission receipt from the national application service, the authority's acknowledgement, the validation email, the fee payment confirmation, and any correspondence about missing documents. Note the date the authority confirmed the application valid and the date it says the period expires, and diarise the expiry.
If the period passes with no decision, write to the authority stating that the period has expired, that you consider the development may proceed in accordance with the submitted details, and attach the dated records. That letter is often the thing that produces a late decision notice, which at least clarifies the position.
For related permitted development questions where the line between what needs an application and what does not is fine, see our notes on air conditioning condensers on commercial buildings and loft conversions with no external change to the house.
PlanScope drafts the narrative documents that sit around a prior approval or an appeal, structured to UK planning policy and flagging the facts that need confirming. You can browse the report types to see which supporting documents a prior approval usually benefits from. Reports should be reviewed before submission, and for specialist technical reports, qualified professional input may be required.
This is general guidance, not legal advice; check the current Order and the position with your local planning authority or a qualified professional before relying on it.
PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
Can I appeal a refusal of prior approval?
Yes, under section 78 of the Town and Country Planning Act 1990, usually by written representations. The general time limit is six months from the decision notice, and householder appeals have a much shorter window of 12 weeks, so a refused larger householder extension needs quick action. Check the current limits before relying on either.
What can the council take into account?
Only the prescribed matters listed in the relevant class, which are short lists and have been amended several times. For commercial to residential they typically cover transport, contamination, flooding, noise from commercial premises and natural light to habitable rooms. Local plan policy cannot add a prescribed matter.
What happens if the council misses the deadline?
Most classes provide that the development may proceed in accordance with the submitted details if the authority does not notify a decision within the period, commonly 56 days or 42 days for the householder procedure. The conditions in the class still apply, and the submitted drawings become the approved scheme.
Should I appeal or resubmit?
Resubmit where the defect is fixable by design and the authority has indicated what would be acceptable, because a revised application takes weeks rather than months. Appeal where the refusal goes beyond the prescribed matters, or where the qualifying facts are disputed and you have the records to prove them.
What records prove the submission date?
The submission receipt from the national application service, the authority's acknowledgement and validation email, the fee payment confirmation, and any correspondence about missing documents. Diarise the expiry date, and if it passes without a decision write to the authority setting out your position with the dated records attached.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.