Section 184 vehicle crossings and the dropped kerb

6 min readBy PlanScope Editorial Team

Section 184 of the Highways Act 1980 governs vehicle crossings over a footway or verge, and it is decided separately from planning permission. When both are needed, the technical objections to expect, and how to sequence the applications.

A section 184 dropped kerb is a highway consent, not a planning permission, and the two are decided by different people against different tests. Section 184 of the Highways Act 1980 deals with vehicle crossings over a footway or verge. The highway authority decides whether the crossing can be built, specifies how it is constructed, and either does the work itself or authorises an approved contractor to do it, at your expense. Planning permission is a separate question that only arises in particular circumstances.

Most householders discover this in the wrong order. They get planning permission for the driveway, assume the access comes with it, and then find the highway authority will not lower the kerb.

What section 184 controls

The section applies where the occupier of premises adjoining a highway takes, or proposes to take, a vehicle across a footway or a verge. You apply to the highway authority, which is the county council in a two-tier area and the unitary council or London borough elsewhere. On the strategic road network it is the national highway operator.

The authority considers the engineering and the safety of the crossing: the construction build-up to take vehicle loads, the gradient across the footway, the drainage, and whether the position is safe. It can refuse. It can also require a crossing to be constructed where someone is already driving over a footway without one, and recover the cost.

Doing the work yourself without consent is not an option. Interfering with the highway is an offence, you can be required to reinstate it at your own cost, and in the meantime driving across an unaltered footway risks damage you will be liable for.

When planning permission is also needed

Four situations, and a property can fall into more than one:

  1. The access is onto a classified road. The permitted development right for forming a means of access does not extend to a trunk or classified road, so a new or widened access onto an A, B or C road needs planning permission.
  2. An Article 4 direction has withdrawn the relevant permitted development right, which is common in conservation areas.
  3. The hard surfacing exceeds what is permitted. Surfacing a front garden is permitted development only where the surface is porous or where water drains to a permeable area within the curtilage.
  4. Works affect a listed building, its curtilage, or a protected tree or hedge in or near the access.

Where none of those applies, the access itself is usually permitted development and section 184 is the only consent you need. A lawful development certificate is the only formal way to confirm that works are lawful, so if there is any doubt and the property may be sold, that is the route rather than an officer's email.

Consent Who decides What it covers
Section 184 vehicle crossing Highway authority Construction and safety of the crossing
Planning permission Local planning authority The access and surfacing where not permitted development
Listed building consent Local planning authority Works to a listed building or curtilage structure
Tree consent Local planning authority Works to a protected tree or hedge

Visibility, gradient and the verge

The technical objections are predictable, and knowing them before you apply saves a refusal.

Visibility is the most common. The authority will want sight lines from a set-back point in the access along the carriageway in both directions, and a boundary wall, fence or hedge inside that triangle has to come down to a low height. If the obstruction is a protected tree or hedge, you have a second consent to obtain and a harder case to make, which is why a tree survey is worth commissioning early where there is anything substantial on the frontage.

Gradient matters because a car has to cross the footway without grounding and without the drive falling towards the road. Authorities set a maximum gradient over the first few metres and require surface water to be contained within the site rather than discharged onto the highway, which often means a permeable surface or a drainage channel across the entrance.

Then there is everything already in the footway. Lamp columns, signs, telecoms chambers, gullies, street trees, bus stops, parking bays and crossings all constrain the position. Statutory undertakers' apparatus can sometimes be moved, at your cost, and that cost is occasionally larger than the crossing itself. Proximity to a junction or a pedestrian crossing is a flat refusal in many authorities.

Costs, inspection and who does the work

The authority publishes its charges, usually as an application or inspection fee plus the cost of the works, and it will quote once it has assessed the site. The variables are the width of the crossing, the footway construction, whether a verge has to be crossed and whether services need diverting.

The work is carried out by the authority or by a contractor it has approved for working on the highway. A general builder cannot do it, and a builder who offers to is offering to create a problem. Ask for the quotation and the specification in writing, and check whether reinstatement of the footway surfacing either side is included.

An illustrative example on a classified road

Illustrative example. A semi-detached house fronts a B road with a 30 mile an hour limit and a 1.8 metre footway. The owner wants a driveway for one car.

Because the road is classified, planning permission is required for the access as well as the section 184 consent. The highway authority asks for visibility in both directions and for the front boundary wall to be reduced to 600 millimetres within the splay. A telecoms chamber sits where the owner wanted the entrance, so the access is moved 1.5 metres along the frontage. The surface is specified as permeable with a channel at the back of the footway. The planning application is submitted with a block plan showing the splay and the surfacing, and the section 184 application follows the grant. The details here are illustrative only.

Sequencing the two applications

Do it in this order:

  1. Ask the highway authority informally whether a crossing is likely to be acceptable at the position you want, before you spend anything.
  2. If planning permission is needed, apply for it, with the visibility splay and the surfacing shown on the drawings so the highway response deals with them.
  3. Once permission is granted, apply under section 184, referring to the planning permission.
  4. Pay, have the works carried out, and keep the authority's completion paperwork with the property deeds.

Applying for the crossing first can work where no planning permission is needed, and it is the better order where the highway position is the real uncertainty. What does not work is building the drive and arranging the crossing afterwards, because a refusal leaves you with a hard standing and no lawful way onto it.

If works go ahead without the permission they needed, the route back is narrower than people expect, and the power to refuse to entertain a retrospective application can close it where enforcement has already started.

One more practical point. A dropped kerb gives you a crossing, not a reserved space. In a civil enforcement area the council can act against a vehicle parked across a dropped footway, which is the mechanism to use rather than anything in planning law. The supporting documents an access application needs are usually few, and getting the drawings right matters more than the quantity.

This is general guidance, not legal advice. Check the position with your highway authority and local planning authority before relying on it.

Enter your postcode on PlanScope to see which documents a householder access application is likely to need. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Is a dropped kerb the same as planning permission?

No. A dropped kerb or vehicle crossing is consented by the highway authority under section 184 of the Highways Act 1980, which deals with the construction and safety of the crossing. Planning permission is a separate matter from the local planning authority, and it is only needed in particular circumstances.

When do I need planning permission for a new access?

Where the access is onto a classified road, because the permitted development right does not extend to trunk or classified roads. Also where an Article 4 direction has withdrawn the right, where the hard surfacing is not porous and does not drain within the curtilage, or where a listed building or protected tree is affected.

Can I build the crossing myself?

No. The work is carried out by the highway authority or by a contractor it has approved for working on the highway. Interfering with the highway without consent is an offence, and you can be required to reinstate it at your own expense. A general builder offering to do the job is offering to create a problem.

What usually causes a refusal?

Inadequate visibility from the access, a position too close to a junction or pedestrian crossing, an unacceptable gradient across the footway, surface water that would discharge onto the highway, and street furniture or statutory undertakers' apparatus in the way. Apparatus can sometimes be moved, at a cost that occasionally exceeds the crossing itself.

Does a dropped kerb stop others parking across my drive?

It does not reserve the space, but in a civil enforcement area the council can take action against a vehicle parked across a dropped footway. That is the route to use rather than anything in planning law, and it is worth knowing before a dispute with a neighbour starts.

Sources and further reading

dropped kerbsection 184vehicle crossinghighways acthouseholderaccess

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Glossary

View all →
Glossary7 min read

Purchase notices and blight notices distinguished

Both notices force a public body to buy. One follows a planning decision, the other a public scheme, and the tests, recipients and timetables are entirely different.

Read article →
Glossary7 min read

Extant planning permission and how to keep it alive

A permission is extant while it can still be lawfully implemented. Here are the section 91 and 92 time limits, what counts as a material start, and the options once a consent has gone.

Read article →
Glossary6 min read

Design review panel and its weight

Panel reports are advice, not decisions. What gives them weight is independence, composition and whether the scheme in front of the council is the one the panel saw.

Read article →
Glossary6 min read

Open book viability appraisal

Open book means the authority and the public see your inputs. National guidance expects publication, redaction is the exception, and review mechanisms capture what the appraisal got wrong.

Read article →
Glossary6 min read

Abnormal load route: what it means in a planning case

An abnormal load route is the agreed path an oversized indivisible load takes to site, with the bridges, junctions and street furniture it affects. The planning evidence and the statutory notification are separate processes.

Read article →
Glossary6 min read

No satisfactory alternative: the second derogation test

The second derogation test asks whether the purpose of a development could be achieved another way with less harm to a European protected species. It is judged on purpose, not on the applicant's preference.

Read article →