What happens in the weeks after an appeal is allowed

6 min readBy PlanScope Editorial Team

The appeal decision is the start of the next job, not the end of the last one. Pre-commencement conditions, levy notices and a six week challenge window all sit between the decision letter and a lawful start on site.

An allowed appeal grants planning permission on the day the decision is issued, and the clock starts that day. What most self-builders do not expect is how much work sits between that letter and a lawful start on site. You have conditions to discharge with the council that just refused you, levy notices to serve, and a six-week window in which someone else can challenge the decision in the High Court.

So read the decision properly before telling the builder to order materials.

Read the decision, then read the schedule of conditions

The inspector's reasoning matters less now than the formal part at the end. Check three things in order.

First, the description of development. Inspectors sometimes amend it, and the permission is for what the description says, not for what your drawings showed. Second, the plans list. Only the drawings numbered in the conditions are approved, and a revision number that differs by one letter from the drawing on your drive will cause problems at building control and on any future section 73 application. Third, the full schedule of conditions, read as a list of jobs with deadlines.

Separate the conditions into three groups as you read: those requiring something before development begins, those requiring something before occupation or before a particular stage, and those that simply control the development in perpetuity, such as a materials restriction or a removal of permitted development rights.

The pre-commencement conditions are the ones that bite. Starting work without discharging them leaves the development unlawful, and the courts have held that works carried out in breach of a condition precedent do not amount to a lawful implementation of the permission. That is the principle usually named after the Whitley case, and it has cost people their permission entirely when the three-year limit then expired.

Conditions the inspector added or altered

Inspectors rarely adopt the council's suggested conditions unchanged. Expect some combination of tightening, deletion and addition.

Where the refusal reason concerned a particular harm, the inspector will often impose a condition designed to control it, and that condition will be worded more precisely than the council's draft. Landscaping, boundary treatment, surface water drainage and construction hours are the usual subjects. If your appeal turned on parking or access, look closely at what the inspector required, because conditions following an evidenced parking case often specify numbers and dimensions rather than general compliance.

Also check for a condition requiring works to be carried out in accordance with a document submitted during the appeal. A method statement or a drainage note produced for the hearing becomes part of the permission, and it has to be buildable.

Discharging conditions with the council afterwards

The council remains the authority for discharge, however the appeal went. Applications to discharge conditions are made under the Development Management Procedure Order 2015, with a fee per request rather than per condition, and the fee schedule is indexed annually so check the current figure before you submit.

Practical sequencing advice from the other side of this process:

  1. Group conditions into as few discharge applications as the submission dates allow, because the fee is charged per request.
  2. Submit at least ten weeks before you want to start, since the authority has eight weeks and often uses them.
  3. Name the appeal reference and the condition numbers exactly as the inspector numbered them.
  4. Where a condition requires approval of a scheme, submit the scheme, not a statement promising one.
  5. Keep the written approval. It is the evidence that the permission was lawfully implemented.

Section 74A of the Town and Country Planning Act 1990 provides a deemed discharge route for some conditions where the authority fails to decide in time, after a notice period. It does not apply to every condition type, and the exclusions include conditions relating to environmental impact assessment and to obligations. Treat it as a backstop rather than a plan.

If the council's condition list looks longer than the inspector's reasoning justifies, the position on shortening a pre-commencement condition list is a separate argument that belongs before the decision, not after it.

Levy liability and the notices nobody serves on time

For development that is liable to the Community Infrastructure Levy, the collecting authority issues a Liability Notice once permission exists. Someone then has to assume liability, and a Commencement Notice has to be served before works begin.

This is where self-builders lose money. The self-build exemption for a dwelling you will occupy as your principal residence has to be claimed and granted before works begin, and the Commencement Notice has to be submitted before work starts. Miss either step and the exemption falls away, leaving the full charge payable with surcharges. The second part of the claim, with the evidence of occupation, follows within six months of completion.

The appeal decision does not change any of this. If anything it increases the risk, because the permission arrives after a long gap and the levy paperwork is the last thing on anyone's mind.

Do not forget building regulations. Planning permission and building control approval are separate consents, and an allowed appeal says nothing about the second.

The time limit for implementation

The default under section 91 of the Town and Country Planning Act 1990 is three years, and on an appeal decision that period runs from the date of the decision rather than from the original application. Check the condition itself, because inspectors occasionally impose a different period, and outline permissions carry their own reserved matters deadlines.

A lawful start means a material operation as defined in section 56 of the same Act, with the pre-commencement conditions discharged first. Digging a trench for the foundations counts. Erecting a site hut generally does not.

Correcting an error in the decision

Decisions contain mistakes: a transposed drawing number, a condition referring to the wrong document, a wrong site address. The Planning Inspectorate can correct a clerical or factual slip in a decision under the correction of errors provisions in the Planning and Compulsory Purchase Act 2004, on application, within the period before the decision can no longer be challenged.

Write to the Inspectorate quoting the appeal reference, identify the error precisely and say what the correct wording should be. A substantive change to the inspector's reasoning or to a condition's effect is not a slip and will not be corrected.

Challenge risk from someone else

A third party, including a neighbour who objected, can apply to the High Court under section 288 of the Town and Country Planning Act 1990 within six weeks of the decision date. The grounds are legal error rather than disagreement with the planning judgement, so most threats come to nothing. Even so, committing significant expenditure inside those six weeks carries a risk you should be aware of.

Costs are a separate track. If you applied for an award of costs during the appeal, that decision may be issued separately, and the sum is agreed or assessed afterwards.

Once the six weeks have passed and the pre-commencement conditions are discharged, the permission is as secure as any other. Keep the decision, the approved drawings, the discharge approvals and the levy notices together in one file, because the next person to ask for them will be a buyer's solicitor. If the next scheme needs a fresh Planning Statement or a different procedure choice, the lessons from picking the right appeal procedure carry over.

Enter your postcode on PlanScope to see which reports your next application is likely to need.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

When does the three year time limit run from on an allowed appeal?

From the date of the appeal decision rather than the original application, unless the inspector imposed a different period in a condition. The default three years comes from section 91 of the Town and Country Planning Act 1990. Outline permissions carry their own deadline for submitting reserved matters, so read the conditions rather than assuming the standard wording applies.

Can the council refuse to discharge a condition the inspector imposed?

Yes. The authority decides discharge applications whatever the appeal outcome, and it can refuse if the submitted scheme does not meet the condition. A refusal or non determination can itself be appealed. Submit the actual scheme rather than a statement of intent, and allow at least ten weeks before the date you want to start.

What happens if I start work before discharging a pre-commencement condition?

The works may not count as a lawful implementation of the permission, which matters if the time limit then expires. Courts have treated operations carried out in breach of a condition precedent as incapable of implementing the permission. The authority can also take enforcement action for breach of condition, so discharge first and keep the written approval.

Does the self-build levy exemption survive an appeal?

The exemption is unaffected by the appeal itself, but the procedure still has to be followed in order. Claim the exemption and have it granted first, serve the Commencement Notice before work starts, then submit the supporting evidence within six months of completion. Missing a step can mean the full charge becomes payable with surcharges.

Can a neighbour challenge an allowed appeal?

A third party can apply to the High Court under section 288 of the Town and Country Planning Act 1990 within six weeks of the decision date. The grounds are legal error, such as failing to take a material consideration into account, rather than disagreement with the planning judgement. Most threats do not proceed, but the window is worth knowing before you spend heavily.

Sources and further reading

planning appealappeal decisionplanning conditionscommunity infrastructure levyself build

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Refusals and Appeals

View all →
Refusals and Appeals7 min read

Reading an appeal decision to work out why you lost

A dismissed appeal decision tells you what to do next if you separate findings of fact from findings of judgement. Only one of those can be answered by a revised scheme.

Read article →
Refusals and Appeals7 min read

Appealing a refusal of a short term let change of use

A short term let appeal starts with whether permission was needed at all. The pattern and intensity of use, the London 90 night provision and the evidence that decides it.

Read article →
Refusals and Appeals7 min read

Appeals against agricultural prior notification refusals

On a Part 6 agricultural notification the authority may only consider siting, design and external appearance. Refusals that reach beyond that test are the ones most often overturned.

Read article →
Refusals and Appeals6 min read

Appeal start dates and what each deadline means

Every appeal deadline runs from the start date set by the Planning Inspectorate, not from the day you lodged. Here is what each stage requires and which deadlines are fatal if missed.

Read article →
Refusals and Appeals7 min read

Appeals where the refusal followed a committee overturn

When members refuse against their officer's recommendation, the authority has already published a professional assessment supporting your scheme. Here is how to use it.

Read article →
Refusals and Appeals7 min read

Appealing a refusal of technical details consent

The principle was settled by permission in principle and cannot be reopened. Here is how to tell a sound refusal from a vulnerable one, and when to appeal rather than resubmit.

Read article →