Appealing a refusal of a short term let change of use
A short term let appeal starts with whether permission was needed at all. The pattern and intensity of use, the London 90 night provision and the evidence that decides it.
If a council has refused permission for short term letting, the appeal turns on one question before anything else: was planning permission needed at all. Short term letting of a dwelling is not automatically a material change of use. Whether it crosses that line is a matter of fact and degree, judged on the pattern and intensity of the use rather than on the booking platform or the length of each stay. Get that argument wrong and the appeal becomes an argument about amenity you were never going to win.
You have six months from the date on the decision notice to appeal a refusal of full planning permission under section 78 of the Town and Country Planning Act 1990. Enforcement notice appeals run to a much shorter deadline set out on the notice itself, and that deadline is absolute.
When short term letting becomes a material change of use
Section 55 of the 1990 Act defines development as including a material change in the use of buildings or land. A dwelling let for short periods is still, in most cases, being used as a dwelling. The courts have treated the question as one of fact and degree for the decision maker, so there is no night count or turnover figure that settles it in England outside London.
What tends to push a use over the line is the character of what is happening, not the tenure. Markers an inspector will look at include:
- how many separate lettings there are in a year and how long each lasts
- whether the whole property is let or a room while the owner remains
- the number of occupants relative to the size of the dwelling
- comings and goings, luggage, taxis and the hours of arrival
- whether the operation looks like a business, with cleaning turnarounds, key safes and commercial management
- loss of residential community, where a significant number of units in one block have gone the same way
A single family home let for eight weeks a year while the owners are away looks like the use of a dwellinghouse. The same building let 200 nights a year to successive groups of ten, with professional management and no residential occupier, does not.
The London 90 night provision and its limits
In Greater London the position is partly codified. Section 44 of the Deregulation Act 2015 inserted provisions into the Greater London Council (General Powers) Act 1973 so that using a dwelling as temporary sleeping accommodation does not amount to a material change of use where the nights do not exceed 90 in a calendar year and the person providing it is liable for council tax.
That provision has sharper edges than most owners expect. The 90 nights are counted per calendar year across the whole dwelling, not per guest or per booking. Both conditions have to be met, so a property let through a company that is not the council tax payer falls outside it. The right can also be disapplied by direction on a locality or a specific property where the authority considers it necessary.
Outside Greater London there is no equivalent threshold. A council quoting 90 nights in a refusal reason in, say, Cornwall or Edinburgh is borrowing a London rule that does not apply, and that is a point worth making in the statement of case.
A new use class and associated permitted development right for short term lets in England has been consulted on, and a registration scheme has been legislated for. As at October 2026 the position should be checked against the current statutory instruments before you rely on it, because a reform that has been announced is not a reform in force.
Evidence of the pattern and intensity of use
Appeals on this issue are decided on evidence, and the appellant usually holds most of it.
Assemble the booking record: dates, duration of each stay, number of guests, and the gaps when the property was occupied by the owner or a long term tenant. Council tax and business rates history matters, as do utility bills showing occupancy patterns. Where the claim is that the use has not materially changed, show what the previous pattern looked like.
Where the council's case rests on complaints, ask for them. A refusal reason citing noise and antisocial behaviour supported by three complaints over two years is weaker than it reads, and an inspector will weigh the evidence rather than the assertion.
Photographs of the bin store, the parking arrangement and the key safe sound trivial. They answer the officer's description of a commercial operation far better than prose does.
Amenity and refuse grounds in refusals
Where the inspector accepts that a material change of use has occurred, the appeal moves to the planning merits. Refusal reasons normally cluster around noise and disturbance from arrivals, departures and groups using gardens and terraces late in the evening, waste storage and collection where a domestic bin cycle cannot cope with weekly turnover, parking demand that does not match the residential standard, and the loss of a dwelling from the housing stock where the local plan protects it.
The last of those is the hardest to answer, because it is a policy objection rather than an evidential one. Check the adopted development plan for a policy on the loss of residential accommodation, and read it closely: some apply only to the loss of a dwelling altogether, not to a change in how it is occupied.
The others are answerable with design and management. A management plan covering arrival hours, group size caps, a named local contact, a no-party clause and a commercial waste contract addresses most of the practical objections. Offer it as a condition rather than as a promise. Parking is the most common weak point, and the evidence that answers parking refusals is survey data rather than argument.
Certificate of lawfulness as an alternative route
If the real dispute is whether permission was ever needed, a Lawful Development Certificate is the formal route to settle it. An application under section 191 of the 1990 Act covers an existing use, and section 192 covers a proposed one. The burden of proof is on the applicant and the standard is the balance of probabilities.
A certificate under section 192 for a proposed pattern of letting is underused. It asks the authority to confirm that letting on a stated basis would be lawful, which gives a definite answer before money is spent, and a refusal can itself be appealed. The evidence has to describe the proposed use precisely, because the certificate only covers what it describes.
For an existing use, the ten year rule for changes of use applies in England, with the enforcement time limits amended by the Levelling-up and Regeneration Act 2023. Check the current position on the limits for your facts before relying on them.
Appealing a refusal or an enforcement notice
A refusal of planning permission goes to the Planning Inspectorate under section 78. Most of these are decided by written representations, which suits a case built on documents. Where there is a genuine factual dispute about what has been happening on site, a hearing can be worth asking for, and the trade-offs are set out in choosing between written reps, hearing and inquiry.
An enforcement notice appeal under section 174 is different and more consequential. The grounds are lettered, and on these facts the ones that matter are ground (c), that there has been no breach of planning control, ground (d), that the time for enforcement has passed, and ground (a), that permission ought to be granted. You can plead more than one. Ground (a) attracts a fee and brings a deemed application with it.
Before appealing at all, work out whether the refusal reasons can be answered by a revised scheme or a management package. Withdrawing and resubmitting rather than appealing is often faster where the objection is fixable. And where a refusal reason is so vague that you cannot tell what would make the scheme acceptable, note the possibility of a costs claim in the statement of case.
Where local licensing sits alongside
Planning and licensing answer different questions, and winning one does not settle the other. Depending on the property and the nation, you may also be dealing with a premises licence for alcohol, fire safety duties under the Regulatory Reform (Fire Safety) Order 2005, gas and electrical safety obligations, and in Scotland a short term let licence under the licensing scheme operating there. A registration scheme for England has been legislated for and should be checked for current status.
A grant of planning permission does not exempt you from any of that, and an absence of planning permission does not make a licence unobtainable.
This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it.
A Planning Statement that sets out the use, the evidence and the offered conditions in one place is the backbone of the appeal. Draft it, then have it reviewed before it is submitted.
PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
Do I always need planning permission to let my home short term?
No. Short term letting of a dwelling is only development where it amounts to a material change of use, which is judged on the pattern and intensity of the use as a matter of fact and degree. Occasional whole-home letting usually remains use as a dwellinghouse. Frequent commercial letting of the whole property is more likely to cross the line.
How does the London 90 night rule work?
Provisions inserted into the Greater London Council (General Powers) Act 1973 by the Deregulation Act 2015 mean using a London dwelling as temporary sleeping accommodation is not a material change of use where it does not exceed 90 nights in a calendar year and the provider is liable for council tax. Both conditions must be met.
How long do I have to appeal a refusal?
Six months from the date on the decision notice for a refusal of full planning permission under section 78. Enforcement notice appeals have a much shorter deadline, stated on the notice itself, and missing it ends the right of appeal. Check the dates on the paperwork rather than relying on a general rule.
Is a Lawful Development Certificate a better route than an appeal?
Often, where the dispute is about whether permission was needed rather than about planning merits. A section 192 application asks the council to confirm that a proposed pattern of letting would be lawful, and the burden of proof sits with the applicant on the balance of probabilities. A refusal can be appealed.
What conditions might make a short term let acceptable?
A management plan is the usual package: capped guest numbers, stated arrival and departure hours, a named local contact available at all times, a no-party clause, and a commercial waste contract with adequate storage. Offering these as conditions rather than assurances gives the inspector something enforceable to attach to a permission.
Does a licence remove the need for planning permission?
No. Licensing and planning are separate regimes answering different questions. A premises licence, a Scottish short term let licence or an entry on a registration scheme does not authorise a material change of use, and the absence of planning permission does not of itself prevent a licence being granted.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.