Which Reports Do I Need

Which reports a site on former landfill needs

9 min readBy PlanScope Editorial Team

On former landfill the number that governs everything is the characteristic situation, and it comes from gas monitoring rather than the desk study. What to commission, in what order, and which conditions to expect.

A plot on former landfill or made ground needs, at minimum, a Phase 1 preliminary risk assessment, a Phase 2 intrusive investigation with a programme of ground gas monitoring, a geotechnical assessment of settlement and foundation options, and a gas protection design with an independent verification plan. On most such sites it also needs a remediation strategy and a construction management plan dealing with dust and the handling of excavated material.

The number that governs everything is the characteristic situation, derived from gas monitoring rather than from the desk study. Until you have enough monitoring rounds, nobody can design the protection, price it, or tell you whether the plot is buildable at the price you paid.

Establishing the fill history and depth

The Phase 1 assessment is a desk exercise plus a walkover, and on an infilled site it has to answer three questions: what was tipped, over what period, and how deep.

Sources that actually produce answers:

  • Historic Ordnance Survey mapping at successive dates, which shows quarries, brickworks, ponds, gravel pits and railway cuttings before infilling and often shows the extent of tipping.
  • The Environment Agency's historic landfill dataset, published as open data, which records many sites that closed before modern permitting.
  • The local authority's contaminated land register and its own records, since district councils hold the Part 2A inspection records and often informal knowledge of local tipping.
  • Borehole and geological records held by the British Geological Survey, which sometimes record made ground thickness directly.
  • Aerial photography at several dates, and local recollection, which is less precise but often tells you where the deepest part of the hole was.

An important point on scope. Development within 250 metres of land used for the deposit of refuse or waste within the previous 30 years triggers consultation with the Environment Agency under Schedule 4 to the Development Management Procedure Order 2015. Check the current Schedule for the exact wording, but assume that a neighbouring landfill, as well as one under your own plot, brings a national consultee into your application.

Phase 1 and Phase 2 land contamination work is not a document to draft yourself. The responsibility for the land being suitable for use sits with the developer, and local planning authorities expect reports prepared in accordance with BS 10175 by suitably qualified and experienced persons. An AI-assisted draft can structure the report and set out the policy framework, and it is a starting point for that professional rather than a substitute for them.

Monitoring rounds and how many are enough

This is where programmes slip, so plan it first.

Ground gas monitoring means installing monitoring wells and visiting them repeatedly to record methane, carbon dioxide and oxygen concentrations, the gas flow rate, and the atmospheric pressure at the time. One visit tells you almost nothing, because gas emissions rise when barometric pressure falls and the worst case is what the design has to cover.

Published guidance expects a series of visits spread over months rather than weeks, with more rounds where a landfill is involved or where raised gas readings are found on the first visits. In practice a simple made-ground site might be assessed on a handful of rounds, while a site on or beside a former landfill routinely needs a dozen or more spread across at least six months, including rounds taken during periods of low and falling pressure. Take the current requirements from the relevant guidance and, more usefully, agree the monitoring scope in writing with the authority's contaminated land officer before you start. An officer who has agreed the scope is unlikely to reject the conclusion for want of rounds.

Two practical consequences. The monitoring programme, not the planning application, is usually the critical path on an infilled plot, so start it before you submit. And monitoring through a summer of high, stable pressure produces a dataset the officer will send back, so a programme that runs only from June to August is wasted money.

The characteristic situation and what drives it

The characteristic situation is a classification of ground gas risk, running from the lowest to the highest band, that determines what protection a building needs. It is derived from a gas screening value, which is the borehole gas flow rate multiplied by the maximum methane or carbon dioxide concentration recorded. Flow and concentration together, not either alone.

That formula explains the result that surprises people. A borehole showing high methane concentration but negligible flow can fall in a low band, while a modest concentration with a steady flow can fall in a higher one. The design driver is how much gas can actually arrive at a building, and a single high concentration reading with no flow is not it.

The bands and the protection measures that go with them are set out in the relevant CIRIA guidance and in BS 8485 for methane and carbon dioxide, with the standard using a points-based approach so that a given band can be satisfied by different combinations of membrane, ventilated subfloor void and floor slab type. Take the band thresholds and the protection scores from the current editions, because both have been revised.

Three things raise the band in practice: degradable content in the fill, depth of fill, and a high or fluctuating water table pushing gas towards the surface. Three things lower it: a thin layer of inert fill, free-draining ground, and a shallow deposit over competent natural strata.

Gas protection design and verification

Protection is a system, not a membrane, and the three elements have to be designed together.

A ventilated subfloor void or a passive venting layer gives the gas somewhere to go. A gas-resistant membrane, correctly specified and detailed at every penetration and junction, stops it entering. The floor slab itself contributes, with a reinforced cast in-situ slab contributing more than a beam-and-block floor.

Service entries are where systems fail. Every pipe, duct and cable passing through the membrane is a potential pathway, and the detail drawings matter more than the specification sheet. Specify sealed top-hat details and insist that all services enter above the membrane where the design allows.

Verification is a separate discipline and it has to be planned at design stage, not improvised on site. A verification plan sets out who inspects, at what hold points, what is photographed, what is tested, and what the acceptance criteria are. Independent verification by someone other than the installer is what authorities expect, and the relevant CIRIA good practice guidance on testing and verification of gas protection systems is the document to work to.

The commonest site failure is simple: the membrane is laid correctly, then a follow-on trade cuts it for a soil pipe and patches it badly. Hold points and photographs exist for that reason.

Settlement and what it does to the foundations

Fill settles, and fill with degradable content settles unevenly for decades.

A Geotechnical Assessment has to deal with the thickness and variability of the fill, its composition, the depth to competent strata, and the resulting foundation options. The realistic choices are usually piling through the fill to found in natural ground, ground improvement such as vibro or dynamic compaction where the fill is granular and non-degradable, a stiff raft designed for differential movement, or excavating the fill entirely on a shallow deposit.

Piling needs a specific caution on landfill sites. Driving or boring piles through a low-permeability cap creates vertical pathways for gas, so the pile design and the gas protection design have to be coordinated, with the pile caps and the slab detailing resolved together. A scheme where the structural engineer and the contamination specialist have not spoken is the scheme that fails verification.

Settlement also affects drainage, external levels, boundary walls and service connections, all of which need flexible joints and a maintenance expectation. Set that out in the submission rather than leaving it to building control.

Leachate, controlled waters and the permit question

Contamination is more than a gas question. Leachate from an infilled site can affect groundwater and surface water, and the Phase 2 assessment should sample water as well as soil where the conceptual model suggests a pathway.

Where the site lies in a source protection zone, or where a watercourse is near, expect the Environment Agency to focus on controlled waters rather than on human health. The remediation strategy then has to address that pathway, and a drainage design that infiltrates to ground through contaminated fill will not be acceptable.

Two regulatory points. The Environmental Protection Act 1990 Part 2A regime deals with land in its current condition and is the local authority's responsibility, while the planning system deals with making the land suitable for its proposed use. They are different tests and an officer will say so if you confuse them. And where the historic landfill still has a permit or where works would disturb permitted waste, there may be a separate environmental permitting requirement, which is the Agency's decision and not the council's.

Where the plot forms part of a wider brownfield site, the same investigation often does double duty, and the evidence overlaps with what is needed for a scheme replacing an employment building.

Conditions and the verification report

Expect a four-part contaminated land condition, and read its wording before you accept it:

  1. Submission and approval of a site investigation and risk assessment.
  2. Submission and approval of a remediation strategy where the assessment identifies unacceptable risk.
  3. Submission and approval of a verification report confirming the remediation and the gas protection were implemented as approved, before first occupation.
  4. Reporting of previously unidentified contamination encountered during construction, with works stopping until a revised strategy is approved.

Part 3 is the one that delays occupation on real projects, because the verification report cannot be produced until the work is done and tested, and the authority then has eight weeks to determine it. Build that into the programme and submit the verification plan early so the officer has already agreed the method.

Keep the whole file: the monitoring dataset, the gas screening calculation, the protection design, the installer's records, the photographs at each hold point, the integrity test results and the verification report. A Contaminated Land Assessment covering Phase 1 and Phase 2 is where this starts, and councils require a competent author for it. For specialist technical reports, qualified professional input may be required.

Enter your postcode on PlanScope to see which reports an infilled site is likely to need, or browse all 66 report types. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

This is general guidance, not legal advice. Check the position with your local planning authority and a qualified contaminated land specialist before relying on it.

Frequently asked questions

How many gas monitoring rounds are needed?

More than most programmes allow for. Guidance expects a series of visits spread over months, with more where a landfill is involved or raised gas readings are found. A site on or beside a former landfill routinely needs a dozen or more rounds over at least six months, including visits during low and falling barometric pressure.

What is a characteristic situation?

A classification of ground gas risk that determines the protection a building needs. It is derived from the gas screening value, which is the borehole gas flow rate multiplied by the maximum methane or carbon dioxide concentration. High concentration with negligible flow can fall in a low band, because what matters is how much gas can reach the building.

Does a neighbouring landfill affect my application?

Yes. Development within 250 metres of land used for the deposit of refuse or waste within the previous 30 years triggers consultation with the Environment Agency under Schedule 4 to the Development Management Procedure Order 2015. Check the current wording, but assume a nearby landfill brings a national consultee into the application.

Can I pile through landfill?

Often, but the pile design and the gas protection design have to be coordinated. Driving or boring piles through a low-permeability cap creates vertical pathways for gas to migrate, so the pile caps, slab detailing and membrane design need to be resolved together rather than by separate consultants working independently.

Why does the verification report delay occupation?

Because it cannot be produced until the remediation and gas protection are installed and tested, and the authority then has its determination period to approve it. Submit the verification plan early so the method is already agreed, and build the approval period into the programme ahead of first occupation.

Sources and further reading

contaminated landground gaslandfillgeotechnicalwhich reportsbrownfieldverification

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Which Reports Do I Need

View all →
Which Reports Do I Need7 min read

Signage across an industrial or business estate

Advertisement consent across a multi occupier estate is judged only on amenity and public safety. Deemed consent covers signs on business premises but rarely the shared entrance totem.

Read article →
Which Reports Do I Need7 min read

A substation to serve a new development

The distribution network operator usually builds the substation serving a new development, but siting, access and transformer noise fall to the applicant to resolve in the layout.

Read article →
Which Reports Do I Need7 min read

Enclosing a balcony on an existing flat

Flats have no permitted development rights, so enclosing a balcony needs permission. The amenity space argument, the fire performance question and the consents beyond planning.

Read article →
Which Reports Do I Need7 min read

Reconfiguring a car park and adding spaces

A car park reconfiguration is rarely refused on capacity. It is decided by surface water drainage, accessible bay dimensions, lighting spill and root protection areas.

Read article →
Which Reports Do I Need7 min read

Keeping a structure after a temporary permission expires

Once a temporary permission expires the structure is unauthorised and the removal condition is in breach. The section 73, fresh application, retrospective and immunity routes compared.

Read article →
Which Reports Do I Need8 min read

Bringing a long-empty building back into use

Resuming the use of a building that has stood empty for years may need no permission, or a full change of use application. The dividing line is abandonment, and it is decided on evidence.

Read article →