Air conditioning and mechanical plant at a house
Cooling plant at a dwellinghouse falls outside the permitted development classes. The Part 14 heat pump rights are narrower than installers suggest, and noise decides the application.
There is no permitted development right for air conditioning at a house. Fixing a condenser to an external wall or standing one in the garden is operational development that changes the external appearance of the building, and no class in Schedule 2 to the General Permitted Development Order 2015 covers cooling plant at a dwellinghouse. So an air conditioning unit planning permission application is usually needed, and installers who say otherwise are thinking of the heat pump rights.
Those rights exist and they are narrower than they sound.
Why cooling plant falls outside the rights
Part 1 of Schedule 2 covers development within the curtilage of a dwellinghouse: extensions, roof alterations, porches, outbuildings, hard surfaces, chimneys and flues, solar equipment. Nothing in it covers mechanical plant for cooling.
Part 14 covers renewable and low-carbon energy equipment, and Class G within it deals with air source heat pumps. A heat pump moves heat into a building to provide space heating or hot water. A cooling-only split system does not, so it is not an air source heat pump within the meaning of the class, whatever the equipment schedule calls it.
That leaves reversible units, which heat and cool. The honest answer is that it depends on the installation and the purpose. A unit installed and used as the dwelling's heating system has a Class G argument. A unit installed principally to cool a loft conversion in summer does not, and an authority looking at the heating system already in the house will reach the same view.
What Class G actually allows
Where a genuine air source heat pump is proposed, Class G grants a right subject to conditions and limitations. They cover the volume of the outdoor unit, its siting, the number of units, compliance with the Microgeneration Certification Scheme Planning Standards or an equivalent standard, and restrictions on designated land.
The conditions have been amended more than once, including changes to the boundary distance and the volume limit, so read the current text of Class G in the Order rather than a summary. An installer's guidance sheet printed two years ago may be describing a version of the class that no longer applies, and the conditions and limitations that attach to every class are worth reading alongside, as set out in our note on GPDO conditions and limitations.
One condition deserves separate attention. The Microgeneration Certification Scheme planning standard for heat pumps sets a sound limit of 42 dB(A) at the assessment position, which is taken at the nearest neighbouring habitable room window. Meeting it is a condition of the permitted development right, so a unit that exceeds it is not permitted development at all.
Where the right is not available, a householder application follows, and that is the same route as for air conditioning.
Noise, and where the neighbour stands
Noise is the reason these applications are refused. A condenser running on a still summer evening, two metres from a neighbour's bedroom window, is a genuine amenity problem rather than a technical one.
Authorities assess it in one of two ways. For a small domestic unit, often a straightforward judgement on siting and the manufacturer's sound power data. For anything larger, or where there is an existing complaint history, an assessment against BS 4142:2014+A1:2019, comparing the rating level of the plant with the background sound level and adding corrections for tonality and intermittency.
| Factor | Effect on the assessment |
|---|---|
| Distance to the nearest habitable room window | The single biggest variable |
| Background sound level at night | A quiet suburban street gives little headroom |
| Tonal content, such as a compressor hum | Attracts a correction that raises the rating level |
| Hard surfaces and narrow passages | Reflections increase the received level |
| Acoustic enclosure or barrier | Effective if designed, not if improvised |
| Operating hours | Night running is what generates complaints |
A short Noise Impact Assessment using manufacturer data and a measured background level is usually enough for a domestic unit, and it costs far less than an appeal. Where plant is already installed and causing a problem, the separate statutory nuisance route under the Environmental Protection Act 1990 is open to the neighbour, and that runs whether or not planning permission exists.
Siting to reduce objection
The design decisions that make these applications work are unglamorous and effective.
- Put the unit on the elevation furthest from neighbouring habitable rooms, which is usually a flank wall facing your own garden rather than a rear wall facing theirs.
- Keep it off party boundaries and out of narrow side passages, where reflections and rattle transmit.
- Mount on anti-vibration feet or a free-standing frame rather than brackets bolted into a wall shared with a bedroom.
- Set a night-time setback on the controls and say so in the application, because it can be conditioned.
- Screen with a slatted enclosure designed for airflow, and show the free area on the drawing.
- Avoid roof mounting, which raises the source above boundary screening and carries it further.
Where the plant serves a loft conversion or a rear extension, include it in that application rather than applying separately afterwards. An officer assessing the whole scheme can condition the plant, while a later standalone application invites a fresh look at something the neighbours have already lived with.
Designated land and listed buildings
In a conservation area, a National Park, a National Landscape or the Broads, the permitted development rights in Part 14 are restricted, and plant on a wall or roof fronting a highway is normally outside them. Expect the conservation officer to resist anything visible from the street, and expect the authority to ask for the unit to be relocated rather than screened.
For a listed building, fixing a condenser to the fabric is likely to need listed building consent under section 7 of the Planning (Listed Buildings and Conservation Areas) Act 1990 whether or not planning permission is needed, and the duty in section 16 to have special regard to the building's special interest applies. Pipe runs through historic walls are assessed as closely as the unit itself.
Our note on permitted development limits in a conservation area sets out how the designations narrow the rights more generally.
If the unit is already installed
An unauthorised unit is a planning breach, and the realistic options are to apply retrospectively, to relocate it, or to remove it.
The enforcement time limits for operational development in England were changed by the Levelling-up and Regeneration Act 2023, lengthening the period during which an authority can act. Check the current limit and the date from which it applies before assuming an installation has become immune, because the older four year figure is still widely quoted.
A Lawful Development Certificate under section 191 of the Town and Country Planning Act 1990 is the only formal way to establish that an existing installation is lawful. For something you have not yet installed, section 192 gives the equivalent certainty in advance.
An illustrative example. A two-storey semi with a converted loft, the owner wants a single outdoor unit serving two bedrooms. The installer proposes the rear wall at first floor level, three metres from the neighbour's bedroom window. Relocating it to the ground floor on the flank wall facing the owner's own garden, on anti-vibration mounts behind a slatted screen, with a night setback, converts a likely refusal into a straightforward approval. Same equipment, different drawing.
Make the case in a short Planning Statement covering the siting choice, the sound data, the operating hours and the reason an alternative position was rejected. Officers approve what they can explain to a complainant.
This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
Do I need planning permission for an air conditioning unit at home?
Usually yes. Fixing a condenser to a wall or standing one in the garden is operational development affecting the external appearance of the building, and no class in Schedule 2 to the GPDO 2015 covers cooling plant at a dwellinghouse. The heat pump rights in Part 14 Class G apply to equipment providing heating or hot water.
Does Class G cover a reversible heating and cooling unit?
It depends on the installation and purpose. A unit installed and used as the dwelling's heating system has a Class G argument. One installed principally to cool a room in summer, where the house already has a heating system, does not. Where the position is unclear, a certificate under section 192 gives a formal answer.
What noise limit applies to a heat pump under permitted development?
The Microgeneration Certification Scheme planning standard sets a sound limit of 42 dB(A) at the assessment position, taken at the nearest neighbouring habitable room window. Meeting it is a condition of the Class G right, so a unit that exceeds the limit is not permitted development and needs a planning application.
How do councils assess noise from domestic plant?
For a small unit, often a judgement on siting using the manufacturer's sound power data. For larger plant or where there is a complaint history, an assessment against BS 4142:2014+A1:2019, comparing the rating level with the background sound level and adding corrections for tonality and intermittency. Night-time background levels give the least headroom.
What if a unit has already been installed without permission?
Apply retrospectively, relocate it, or remove it. The enforcement time limits for operational development in England were lengthened by the Levelling-up and Regeneration Act 2023, so check the current limit rather than relying on the older four year figure. A certificate under section 191 is the only formal way to establish lawfulness.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.