GPDO conditions and limitations: breaching each one
A limitation defines the scope of permitted development; a condition governs how it is carried out. The difference decides the enforcement route and whether your client has an appeal.
A limitation in the General Permitted Development Order defines what was granted. A condition attaches to a grant that already exists. Exceed a limitation and the development was never permitted, so it is unauthorised development. Breach a condition and you have development that was permitted but is being carried out unlawfully. The gpdo conditions and limitations distinction decides which enforcement route the authority can use, which appeal rights your client has, and how you advise on putting it right.
Practitioners use the words loosely in conversation. Authorities do not, when they are drafting a notice.
How Schedule 2 is structured
Each Class in Schedule 2 has the same three-part shape, and reading it in that order avoids most mistakes.
First, the grant. "Development consisting of the enlargement, improvement or other alteration of a dwellinghouse" is the opening of Class A of Part 1. Anything outside that description is not within the Class at all.
Second, the limitations, introduced by the words "Development is not permitted by Class A if". These are the familiar numbers: the 50 per cent curtilage rule, the depth limits for rear extensions, the eaves height within two metres of a boundary, the exclusions on article 2(3) land.
Third, the conditions, introduced by "Development is permitted by Class A subject to the following conditions". For Class A these cover materials of similar appearance, obscure glazing and non-opening windows on upper side elevations, and the roof pitch of an upper-storey extension.
The ordering is not decorative. The limitations describe the boundary of the permission. The conditions describe how a development inside that boundary must be built.
The difference that matters in practice
Take a rear extension on a semi-detached house, 3.5 metres deep. The Class A limit is 3 metres. The extension is not permitted development at all, because it exceeds a limitation, and it is unauthorised development requiring planning permission.
Now take the same extension at 2.8 metres deep, finished in a render that looks nothing like the brick of the host dwelling. The depth is within the limitation, so the development was permitted. But the materials condition has been breached.
The two situations produce different legal consequences:
| Issue | Limitation exceeded | Condition breached |
|---|---|---|
| Status of the development | Never permitted, unauthorised | Permitted, carried out in breach |
| Primary enforcement tool | Enforcement notice | Breach of condition notice or enforcement notice |
| Appeal to the Planning Inspectorate | Yes, under section 174 | Not against a breach of condition notice |
| Route to regularise | Retrospective application or certificate of lawfulness | Comply, or apply for permission for the variation |
That appeal difference is the one clients care about. An enforcement notice can be appealed on the ground that planning permission ought to be granted, which is a full merits hearing. A breach of condition notice under section 187A carries no appeal to an inspector at all. The only challenge is judicial review, and the only defence to prosecution is in the magistrates' court on narrow grounds.
So an authority faced with a materials breach has a tool that bypasses the merits entirely. Authorities do not always use it, and when they do, the conversation changes.
Conditions precedent and the prior approval trap
Some conditions have to be satisfied before development begins, and those behave like limitations in effect even though they sit under the conditions heading.
The clearest examples are the prior approval classes. Class MA permits the change of use from commercial, business and service use to dwellinghouses, subject to a condition that the developer applies for and obtains prior approval before beginning development. Carry out the conversion without that application and there is no permission to breach, because the grant was conditional on a step that never happened.
The same logic applies to the notification requirements in Part 6 for agricultural buildings, to the larger home extension procedure in Part 1, and to the Part 16 telecommunications classes. Treat any "before beginning development" requirement as going to the existence of the permission rather than to its performance.
Where the condition is one to be observed after completion, such as keeping a window obscure-glazed or removing a temporary structure when the use ceases, the position is less settled. Some authorities take the view that a continuing breach removes the benefit of the permission entirely. Others treat it strictly as a breach of condition. The practical answer is that either route may be used against your client, and an application for a lawful development certificate is the way to test it.
Which enforcement route follows
Authorities have several instruments and they are not interchangeable.
A planning contravention notice under section 171C is an information-gathering step, requiring the recipient to answer questions about the use and operations on the land. Failing to respond is an offence, and the answers can be used later.
An enforcement notice under section 172 specifies the breach, the steps required and a compliance period, and carries a right of appeal on the grounds in section 174.
A breach of condition notice under section 187A applies only where there is a planning permission with a condition, requires compliance, and has no appeal route.
A temporary stop notice can halt activity immediately, and an injunction under section 187B is available where the breach is serious enough.
Which one arrives tells you how the authority has characterised the breach, and if the characterisation is wrong, that is worth challenging before anything else.
Time limits and the 2023 Act change
The old position was four years for operational development and for change of use to a single dwellinghouse, and ten years for everything else. That changed in England through the Levelling-up and Regeneration Act 2023, which brought the operational development and single-dwelling periods up to ten years, commencing on 25 April 2024 and applying to breaches occurring on or after that date.
So for recent development the period is ten years across the board, while older breaches may still be covered by the four-year rule depending on when they occurred. Check the commencement position and the facts carefully, because this is the single most consequential date in advising on an existing breach.
Immunity also behaves differently for limitations and conditions. A breach of condition that is continuing starts a fresh period with each day of non-compliance in substance, whereas a completed building becomes immune once the period has run from substantial completion.
Retrospective routes and the evidence they need
Three routes exist and the choice is strategic.
A retrospective planning application under section 73A asks the authority to grant permission for development already carried out. It puts the merits in front of the officer, and a refusal can be appealed, but it also tells the authority exactly what has happened.
A certificate of lawful existing use or development under section 191 asserts that the development is already lawful, through immunity or because it never needed permission. The burden of proof sits with the applicant, on the balance of probabilities, and national guidance makes clear that the applicant's own evidence need not be corroborated if it is not contradicted.
Doing nothing is a real option where immunity is close and the breach is minor, and it is the option that gets advisers into trouble, because the client hears it as approval.
Evidence for a certificate application should be dated and documentary: photographs with metadata, invoices, delivery notes, council tax or business rates records, utility accounts, tenancy agreements, and statutory declarations from people with direct knowledge. Aerial imagery is useful for establishing when a structure appeared.
Advising a client who has already built
Work through it in order. Establish the facts and the dates, in writing, before offering any view. Identify whether the problem is a limitation or a condition, by reading the Class text rather than a summary. Check the immunity position against the relevant time limit. Then choose between compliance, a retrospective application and a certificate.
One honest note on strategy: a retrospective application is sometimes the better route even where a certificate might succeed, because it ends the uncertainty and produces a decision notice a purchaser's solicitor can read. Certificates are stronger in law and harder to explain in a transaction.
Common breaches worth checking first on householder work are the materials condition, the obscure glazing condition on upper side windows, outbuildings used as independent dwellings rather than as ancillary accommodation, and windows replaced in a way that turns out to be development, as covered in replacement windows and doors. Garden structures and equipment raise similar questions, for example ground mounted solar arrays in a domestic garden.
Where a retrospective application is the chosen route, the Planning Statement has to do unusual work, explaining both the planning merits and the history honestly. Browse the 66 report types for the technical documents the authority is likely to ask for alongside it.
This is general guidance, not legal advice, and enforcement positions turn on specific facts and dates, so take advice from a qualified professional. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
What is the difference between a limitation and a condition in the GPDO?
Limitations appear under the words development is not permitted by Class X if, and define the boundary of the grant. Exceed one and the development was never permitted. Conditions appear under development is permitted subject to the following conditions, and govern how permitted development must be carried out. Breaching one is a breach of condition.
Can a breach of condition notice be appealed?
Not to the Planning Inspectorate. A breach of condition notice under section 187A carries no appeal on the merits. The only challenge is judicial review, and the only defence to prosecution is in the magistrates' court on narrow grounds. That is why authorities sometimes prefer it to an enforcement notice.
What happens if I skip the prior approval step?
There is no permission to breach. Where a Class requires the developer to apply for and obtain prior approval before beginning development, as Class MA does, carrying out the work without that application means the conditional grant never took effect. Treat any before beginning development requirement as going to the existence of the permission.
What are the current enforcement time limits?
In England the Levelling-up and Regeneration Act 2023 raised the four-year periods for operational development and change of use to a single dwellinghouse to ten years, commencing on 25 April 2024 for breaches occurring on or after that date. Older breaches may still fall under the four-year rule, so the dates matter.
Retrospective application or lawful development certificate?
A certificate asserts the development is already lawful and the burden of proof sits with the applicant on the balance of probabilities. A retrospective application under section 73A puts the merits before the authority and produces an appealable decision. Certificates are stronger in law; a decision notice is easier to explain in a transaction.