The neighbourhood portion of CIL and how it is spent

7 min readBy PlanScope Editorial Team

Fifteen per cent of levy receipts go to the parish, rising to 25 per cent with no cap where a neighbourhood plan is made. What it can fund, what must be reported, and what happens in unparished areas.

When a development pays the Community Infrastructure Levy, a slice of it has to leave the district or borough council and go to the parish or town council for the area where the building happened. The cil neighbourhood portion is 15 per cent of the levy collected from development in that parish, capped at a figure linked to the number of council tax dwellings there, and it rises to 25 per cent with no cap where a neighbourhood plan is in place. The money is handed over twice a year and the parish decides what to do with it.

How the portion is calculated and passed on

The levy is charged on most new floorspace at rates set in the charging authority's own charging schedule. Of what is actually received from development in a parish, the charging authority must pass on 15 per cent.

There is a ceiling on the basic 15 per cent. It is capped at £100 for each council tax dwelling in that parish in the year, with indexation applied as the Community Infrastructure Levy Regulations 2010 provide. A parish of 400 homes therefore has a ceiling in the region of £40,000 a year before indexation, and anything above that stays with the charging authority.

Payments are made twice a year, covering receipts in each half of the financial year. The practical effect is a lag: money collected from a development in May arrives in the parish's account the following spring, and a parish treasurer planning a project needs to know which half-year the receipts fell into.

The higher proportion where a neighbourhood plan is made

Where a neighbourhood development plan has been made for the area, or a neighbourhood development order including a community right to build order is in place, the proportion rises to 25 per cent and the cap falls away entirely.

That is the single strongest financial argument for making a neighbourhood plan, and it is often undersold during the plan-making process. On a parish that is going to receive a large allocation, the difference between 15 per cent capped and 25 per cent uncapped can run into hundreds of thousands of pounds over the plan period.

The plan has to be made, not merely drafted. A plan at examination or awaiting referendum does not trigger the higher rate, and the date it is made determines which receipts attract 25 per cent. Parishes in the middle of plan-making sometimes ask the charging authority to confirm in writing how receipts will be apportioned either side of that date, which is a sensible precaution.

What the money may be spent on

The spending power here is wider than the charging authority's own. A parish or town council may use neighbourhood funds to support the development of its area by funding the provision, improvement, replacement, operation or maintenance of infrastructure, or by funding anything else that addresses the demands that development places on the area.

That second limb is unusually broad. It covers things a council could not normally fund from levy receipts at all.

Spending type Typical examples Normally within the powers
Infrastructure provision Play equipment, footpath, bus shelter, village hall extension Yes
Maintenance and operation Grounds maintenance of a new open space, running costs of a hall Yes, unlike the authority's own levy spending
Addressing demands of development Traffic calming study, speed indicator devices, allotment lease Yes, under the wider limb
General parish running costs Clerk salary, insurance, routine administration No, not tied to the demands of development
Projects outside the parish Contribution to a facility in a neighbouring village used by residents Possible where it addresses local demand, record the reasoning

The honest difficulty is the boundary of that wider limb. There is no definitive list, and a parish spending decision that cannot be connected to the demands development places on the area is open to challenge. The safe practice is a short written rationale for each decision, recorded in the minutes, linking the spend to growth in the parish.

Reporting duties on the parish council

A parish that receives neighbourhood funds in a financial year has to publish a report for that year. The report has to be published by 31 December following the end of the financial year and must set out the receipts for the year, the expenditure, a summary of what the money was spent on, and the amount retained at year end.

Publication means on a website if the parish has one, and the charging authority has to be sent a copy. Small parishes miss this, and the consequence is not trivial.

Unspent money can be clawed back. Where funds are not spent within five years of receipt, or are not applied in accordance with the regulations, the charging authority may serve notice requiring repayment. A parish sitting on four years of receipts while it designs a project should talk to the charging authority before year five rather than after.

Where there is no parish council

Most urban areas in England have no parish or town council. In those areas the neighbourhood proportion is not passed to anyone, and the charging authority keeps it.

It does not simply disappear into the general levy pot, though. The charging authority has to spend it in the areas where the development took place and has to engage with the communities there about how. In practice that produces local ward-based funding programmes, neighbourhood capital grant schemes and community panels, and the quality of that engagement varies a great deal between authorities.

If you live in an unparished area and want to know what happened to the money, the charging authority's infrastructure funding statement is the document to ask for. Authorities have to publish one annually, setting out levy receipts, expenditure and what remains.

How residents can influence spending

Four routes do most of the work, in rough order of effectiveness.

  1. Stand for or attend the parish council. Neighbourhood funds are decided in parish meetings, which are open to the public and usually sparsely attended.
  2. Get a project into the parish's project list before the money arrives, because the lag between receipt and decision is where influence sits.
  3. Support a neighbourhood plan, which raises the proportion from 15 to 25 per cent and removes the cap.
  4. In an unparished area, respond to the charging authority's consultation on neighbourhood spending and read the infrastructure funding statement.

Evidence helps more than enthusiasm. A parish asking for play provision gets further with a short assessment of existing provision against the population, which is the same analysis as an Open Space Assessment for a planning application. The same holds for community facilities, where a Social Infrastructure Assessment sets out capacity against need.

Where the neighbourhood portion stops

Two limits are worth knowing. The neighbourhood portion comes only from the levy, so a development that pays nothing under the charging schedule generates nothing for the parish, however large it is. Self-build homes, social housing and some charitable development carry reliefs that reduce or remove liability.

And the levy sits alongside planning obligations, which are negotiated separately and are usually what funds affordable housing and larger infrastructure. A parish that expected a windfall from a major scheme sometimes finds the benefit came through the obligations instead, which is why reading both the decision notice and the agreement matters. The way affordable units are secured in those agreements is covered in the affordable housing cascade mechanism, and the timing of levy payments in phasing a permission to spread the levy liability.

Rates and caps in the regulations change, so check the current charging schedule and the current regulations before relying on a figure. PlanScope drafts the supporting assessments that sit behind a funding case. Browse all 66 PlanScope report types and start a draft.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

How much of the Community Infrastructure Levy goes to the parish?

Fifteen per cent of the levy actually received from development in that parish, capped at £100 for each council tax dwelling in the parish in the year, with indexation as the regulations provide. Where a neighbourhood development plan has been made, the proportion rises to 25 per cent and the cap no longer applies.

When is the money paid over?

Twice a year, covering receipts in each half of the financial year. That creates a lag between a development paying the levy and the parish receiving its share, often of several months. Parish treasurers planning a project need to know which half-year the receipts fell into before committing to a timetable.

Can a parish spend neighbourhood funds on maintenance?

Yes. The regulations allow spending on the provision, improvement, replacement, operation or maintenance of infrastructure, or on anything else that addresses the demands development places on the area. That is wider than the charging authority's own levy spending powers, which do not extend to maintenance in the same way.

What happens if the parish does not spend the money?

The charging authority may require repayment where funds are not spent within five years of receipt, or where they have not been applied in accordance with the regulations. A parish saving towards a larger project should discuss the timetable with the charging authority well before the five year point rather than after it.

Who gets the neighbourhood portion in an area with no parish council?

The charging authority keeps it, but must spend it in the areas where the development took place and must engage with those communities about how. Many authorities run ward-based grant programmes or community panels. The annual infrastructure funding statement shows what was received, what was spent and what remains.

Sources and further reading

cilneighbourhood planparish councilcommunityinfrastructurefunding

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Viability, Obligations and Commercial

View all →
Viability, Obligations and Commercial6 min read

Section 278 works and how they sit in viability

Section 278 works cost more than the tarmac. How design and supervision fees, statutory undertaker diversions and commuted maintenance sums belong in a viability appraisal.

Read article →
Viability, Obligations and Commercial6 min read

Edge of centre: measuring walking distance in practice

Edge of centre is 300 metres from the primary shopping area for retail and from the town centre boundary for everything else. How to measure it, and why connection matters as much as distance.

Read article →
Viability, Obligations and Commercial6 min read

Deferring an affordable housing contribution by agreement

Authorities will usually stage a commuted affordable housing sum. The money is made or lost in the trigger definitions, the indexation basis and the security attached.

Read article →
Viability, Obligations and Commercial6 min read

Sales value evidence and the new build premium

Revenue moves a viability conclusion more than any other line. How to build a sales schedule from real transactions, derive the new build premium from paired evidence, and deduct incentives properly.

Read article →
Viability, Obligations and Commercial6 min read

Developer profit: return on cost against return on value

A 20 per cent return on cost is a 16.7 per cent return on value. Which basis belongs in a viability appraisal, what the guidance range actually measures, and how the affordable margin differs.

Read article →
Viability, Obligations and Commercial6 min read

Payments in kind and land payments for CIL

Levy liability can be met by transferring land or providing infrastructure, but only where the charging authority has published a notice saying it will accept them. The valuation and the timing decide whether it is worth it.

Read article →