Developer profit: return on cost against return on value
A 20 per cent return on cost is a 16.7 per cent return on value. Which basis belongs in a viability appraisal, what the guidance range actually measures, and how the affordable margin differs.
Two appraisals of the same scheme can show a healthy margin and a loss, with no dishonesty on either side, because one expresses the developer profit viability return on cost and the other expresses it as a percentage of gross development value. The numbers are related by simple arithmetic, so there is no excuse for confusion. There is plenty of room for argument about which measure suits the scheme.
The two measures and how they differ
Profit on cost divides the developer's profit by total development cost, which covers land, construction, fees, finance, marketing and contributions. Profit on gross development value divides the same profit by the value of the completed scheme.
Because gross development value equals cost plus profit, the two are linked. A margin of x per cent on cost converts to x divided by one plus x on value.
| Profit on cost | Equivalent profit on gross development value |
|---|---|
| 10 per cent | 9.1 per cent |
| 15 per cent | 13.0 per cent |
| 17.5 per cent | 14.9 per cent |
| 20 per cent | 16.7 per cent |
| 25 per cent | 20.0 per cent |
That table is arithmetic rather than evidence, and it is illustrative of the relationship rather than a statement about any scheme. But it explains most viability disagreements that look substantive and are not. An applicant quoting 20 per cent and an authority quoting 17 per cent may be describing the same profit.
Why the basis changes the outcome
The choice of basis matters most where the ratio of cost to value is unusual.
On a high-value scheme with modest build costs, say a conversion in a strong market, value is large relative to cost, so a return measured on cost produces a bigger absolute profit than the same percentage measured on value. On a low-value scheme with heavy abnormal costs, the reverse holds, and a profit expressed on cost can look generous while the absolute figure is thin.
That is why return on cost is the more common measure for build-to-sell residential development, where the developer is being rewarded for deploying and risking capital, and why return on value appears more often in commercial and plan-wide work, where value is the metric the market talks in. Neither is right in the abstract. What matters is that the measure is stated, applied consistently across every appraisal in the case, and matched to how the risk actually sits.
What national guidance says about the range
The Planning Practice Guidance on viability says that for the purpose of plan making an assumption of 15 to 20 per cent of gross development value may be considered a suitable return to developers to establish the viability of plan policies. It also says a lower figure may be more appropriate where affordable housing delivery guarantees an end sale at a known value and so reduces risk.
Two points follow that practitioners sometimes skip. First, that range is expressed on gross development value, so quoting 15 to 20 per cent and then applying it to cost inflates the profit by roughly a sixth. Second, the range is framed for plan making. At application stage the guidance expects the return to reflect the actual risk of the specific scheme, and the plan-making assumption is a starting point rather than an entitlement.
Differential profit on affordable units
Affordable units sold to a registered provider under a pre-agreed contract carry very little sales risk. There is no void period, no incentive, no marketing cost and no exposure to a falling market between start on site and completion.
The guidance reflects that, and the standard practice follows it: a lower margin is applied to the affordable element than to the private element. In a blended appraisal that means two profit lines rather than one, each stated with its basis.
Expect the authority's reviewer to check three things. That the differential has been applied at all, since its absence inflates the cost of affordable delivery and strengthens an applicant's case for reducing it. That the affordable margin is calculated on the affordable revenue rather than on the whole scheme. And that the private margin has not been nudged upwards to absorb the difference. Where the affordable tenure mix changes through the cascade, the profit treatment should follow it, which is why this interacts with the affordable housing cascade mechanism.
Evidencing risk on a particular site
A return above the plan-making range needs reasons tied to the site rather than to the market in general. The reasons that carry weight are specific and documented.
- Abnormal ground conditions established by investigation, not assumed.
- A long build programme with exposure to cost inflation, evidenced by a priced programme.
- Pre-let or pre-sale uncertainty in a thin market, evidenced by agents' advice naming comparable schemes.
- Phasing and infrastructure that must be delivered before any revenue arrives.
- Planning risk where consent is conditional on matters outside the applicant's control.
What does not carry weight is an unevidenced assertion that the scheme is risky, a funder's hurdle rate presented as a policy requirement, or a return imported from a corporate investment policy. Funders' requirements are relevant context and the guidance treats them as such, but they do not set the planning assumption.
How reviewers test the figure
An experienced reviewer works through four checks, and knowing them makes a submission harder to pick apart.
- Is the basis stated, and is the same basis used in the policy-compliant appraisal and the proposed one. A switch between the two is the most common defect.
- Does the profit line sit consistently with the finance line. A scheme funded with high gearing and charged a high finance rate is already compensated for some of the risk the profit margin is said to cover.
- Is the margin applied to a sensible revenue figure, net of incentives and selling costs rather than gross of them.
- Does sensitivity testing show how the conclusion moves. A scheme that only becomes unviable at the applicant's chosen profit level invites a different conclusion.
Reviewers also check the arithmetic of any conversion between bases, because an error there changes the answer by more than most of the arguments in the report.
Stating the basis clearly
Write the profit assumption as a single sentence that cannot be misread: the measure, the percentage, the denominator and the element it applies to. For example, a return of 17.5 per cent on gross development value for the private residential element and 6 per cent on gross development value for the affordable element. Then show the absolute figures alongside, because an absolute number is harder to misinterpret than a percentage.
Set out the reasoning in the Viability Assessment rather than leaving it in a spreadsheet, and carry the same figures into the Affordable Housing Statement so the two documents agree. Where obligations are being revisited on a scheme that has stalled, the profit basis has to be reconstructed as at the original date as well as the current one, a point explored in renegotiating obligations on a stalled scheme.
Viability work is one area where a draft needs a chartered valuer's judgement rather than a template. PlanScope can structure the report and the policy framing, and qualified professional input may be required for the appraisal itself. Browse all 66 PlanScope report types and start a draft.
This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
How do you convert profit on cost to profit on gross development value?
Divide the margin by one plus the margin. A 20 per cent return on cost becomes 20 divided by 1.20, which is 16.7 per cent on value. The relationship holds because gross development value equals cost plus profit. Getting the conversion wrong shifts the answer by more than most of the arguments in a viability report.
What profit range does national guidance give?
The Planning Practice Guidance on viability says that for plan making an assumption of 15 to 20 per cent of gross development value may be considered a suitable return to developers. Note the denominator: applying that range to cost rather than value inflates the profit by roughly a sixth. At application stage the return should reflect the specific scheme's risk.
Why is a lower margin applied to affordable units?
Because a sale to a registered provider under a pre-agreed contract removes sales risk, void periods, incentives and marketing cost. The guidance recognises that a lower figure may be appropriate where affordable delivery guarantees an end sale at a known value. The affordable margin should be calculated on affordable revenue, not on the whole scheme.
Can a developer rely on its funder's required return?
Only as context. A funder's hurdle rate reflects that organisation's investment policy rather than the risk of the particular site, and planning guidance treats it as relevant background rather than a determinative figure. A return above the plan-making range needs site-specific evidence such as investigated ground conditions or a priced build programme.
Which basis should be used in an application appraisal?
Return on cost is more common for build-to-sell residential, where the developer is rewarded for deploying and risking capital, while return on value appears more often in commercial and plan-wide work. The important thing is to state the basis, use it consistently in both the policy-compliant and proposed appraisals, and match it to how the risk sits.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.