Renegotiating obligations on a stalled scheme as costs rise
Build cost inflation can strand a consented scheme. Here are the statutory routes to vary an obligation, the evidence needed, and the options short of cutting affordable housing.
To renegotiate section 106 costs on a consented but unbuilt scheme you need three things in place before you make the approach: evidence that costs and values have moved since the appraisal that fixed the package, a route that fits the age of the obligation, and a proposal that is not simply a request for less affordable housing. Authorities hear the third request constantly and refuse it most of the time. The ones that get agreed come with an offer that protects the authority if the market recovers.
Start with the arithmetic, not the conversation. An approach made before the evidence is assembled sets the tone for everything that follows.
Evidence of the change in circumstances
The case rests on showing what has changed between the appraisal that underpinned the consent and today.
On the cost side, that means tender returns rather than indices where you have them. A set of priced subcontract packages from a live tender is worth far more than a published index movement, because the authority's reviewer will apply the index themselves and will ask why your figure is higher. Where tenders are not available, use a recognised cost index with the base date and the index series stated, and show the movement for the relevant work sections rather than for construction generally.
On the revenue side, comparable evidence for the units as designed, in the location, with dates. Agents' opinions are weak evidence on their own. Achieved prices on comparable schemes within the last year are strong.
Then the items that move quietly and matter: finance costs over a longer programme, professional fees, the cost of the obligations themselves indexed from the original date, and any new regulatory cost that did not exist when the consent was granted. Biodiversity net gain, the building safety regime and the Part L uplift have all added cost to schemes consented before they applied.
Set the original appraisal and the current one side by side with a single reconciliation table. The reviewer's first question is always what changed and by how much.
The routes available and their timing
Four routes, and the right one depends on how old the obligation is and whether the authority will engage.
A deed of variation by agreement under section 106A(1) is available at any time and is how most of these are resolved. It needs the authority's consent, which means officer support and sometimes a committee resolution.
An application to modify or discharge under section 106A(3) becomes available once the relevant period has passed, which is five years from the date the obligation was entered into. The grounds are that the obligation no longer serves a useful purpose, or that it continues to serve a useful purpose but would serve that purpose equally well if modified. Refusal carries a right of appeal to the Secretary of State.
A fresh planning application with a new obligation is sometimes cleaner, particularly where the scheme itself needs to change to be deliverable. It exposes the whole permission to reconsideration, which is a real risk where policy has moved against the scheme.
A section 73 application to vary conditions, with a deed of variation to carry the obligation across, suits cases where the design changes and the package needs adjusting at the same time. The obligation does not follow the new permission automatically, which catches people out.
Open book appraisal and what to disclose
A Viability Assessment for a renegotiation is read far more sceptically than one submitted with an application, because the authority has already agreed a package once.
Work from a benchmark land value established as existing use value plus an appropriate premium, and address the price actually paid separately. National guidance is clear that the price paid is not a justification for failing to comply with policy, and an appraisal that leads with the acquisition cost loses credibility in its first table.
Set out the developer return as a percentage of gross development value or of cost, say which, and justify it against the risk profile of this scheme rather than a market convention. Show the sensitivity of the conclusion to each main input, because a conclusion that flips on a half per cent movement in sales values is not a conclusion.
Expect publication. Guidance says viability assessments should be prepared on the basis that they will be made publicly available, and what can properly be redacted is narrower than most developers assume. Write it accordingly.
Be careful with abnormal costs, which is where most appraisals are picked apart. Abnormal costs that survive review are the ones evidenced by a quotation, a site investigation or a utility company estimate, not the ones carried as a percentage allowance.
The authority's own evidence and its reviewer
Almost every authority now commissions an independent review, charged to the applicant, and the reviewer will have seen a hundred of these.
Three things make that process go better. Share the model, not just the output, so the reviewer can test inputs rather than guessing at them. Respond to the review in a table, input by input, agreeing what you can and narrowing the dispute. And identify the two or three inputs the answer actually turns on, because a reviewer who agrees 40 lines and disputes three is close to a deal.
The authority will also have its own evidence: the plan viability study, its affordable housing programme, its knowledge of what other local schemes have delivered. Where your appraisal implies a return above what comparable local schemes have accepted, expect that to be raised.
One honest word about the politics. Members treat renegotiation as a question about the applicant as much as about the numbers. A developer who has already built out two phases at the agreed level and is asking about the third is in a different position from one who has never started.
Options short of cutting affordable housing
This is the section that decides whether an approach succeeds, and the range is wider than most openings suggest.
- Change tenure rather than quantum, moving some social rent to affordable rent or shared ownership, which reduces the grant gap without reducing the number of affordable homes.
- Defer payment triggers, so contributions fall due later in the programme when units are selling.
- Stage the triggers across phases, which is where phasing the obligation triggers does real work on a multi-phase site.
- Convert cash contributions to in kind delivery where the authority wants the facility more than the money.
- Remove or reduce contributions that are no longer necessary, which happens where a school place projection has changed or a highway scheme has been delivered by someone else.
- Accept indexation from a later date in exchange for a higher base figure.
- Offer a clawback or overage so the authority shares in any improvement.
Present the package with the Affordable Housing Statement updated to match, rather than leaving the officer to work out what the offer means for delivery on the ground.
Review mechanisms as the usual landing point
The compromise that gets agreed, more often than any other, is a review mechanism.
An early stage review applies where the scheme has not been implemented within an agreed period, reassessing viability before works start. A late stage review applies at or near completion, comparing actual costs and actual sales values with the appraisal assumptions and sharing any surplus above the agreed return, usually as a payment in lieu of affordable housing.
The drafting is where the value sits. Agree the inputs that will be fixed and the ones that will be revisited, the definition of the agreed return, the cap on any additional payment, the audit process, the timing, and what happens if the parties disagree. A review clause with no defined methodology produces a dispute at the worst possible moment, when the last units are selling.
For the authority, a review protects against agreeing a reduction and then watching the scheme sell into a strong market. For the developer, it converts an argument about forecasts into an agreement about facts. That is why it works.
If agreement is not reached
Keep the alternatives visible throughout, because they shape the negotiation.
Where the obligation is more than five years old, the section 106A(3) application and the subsequent appeal are a real route, and the prospect of it tends to focus minds. Where it is newer, the options are to implement the scheme as consented, to sell the site with the consent and let someone else carry the package, to submit a fresh application and appeal any refusal with the viability evidence tested at inquiry, or to leave the site.
None of those is costless. Say so to the client at the outset, and price the renegotiation attempt against them rather than treating agreement as the only outcome.
This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it.
Enter your postcode on PlanScope to see which reports your scheme is likely to need.
PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required.
Frequently asked questions
Can a section 106 obligation be changed?
Yes, by agreement at any time through a deed of variation under section 106A of the Town and Country Planning Act 1990. Where the authority will not agree, an application to modify or discharge can be made after the relevant period, which is five years from the date the obligation was entered into, with a right of appeal to the Secretary of State if it is refused.
Does the price paid for the land justify a reduction?
No. National guidance is explicit that the price paid for land is not a justification for failing to comply with policy requirements. The assessment works from a benchmark land value based on existing use value plus an appropriate premium, so an overpayment is treated as the developer's risk rather than a reason to reduce planning obligations.
Will the viability appraisal be made public?
Expect it to be. National guidance says viability assessments should be prepared on the basis that they will be made publicly available, with only limited redaction for information that is commercially sensitive in substance. Plan the appraisal on that footing, since a document written for private circulation and then published usually reads badly.
What is a late stage review?
A mechanism in the obligation requiring the actual costs and sales values to be reassessed at or near completion, with any surplus above the agreed return shared with the authority, often as a payment in lieu of affordable housing. It is the usual landing point in a renegotiation because it lets both sides accept a reduced commitment now without conceding the upside.
Does a section 73 application reset the obligation?
No. The obligation attaches to the permission that triggered it, so a new section 73 permission needs a deed of variation to bind it. Allow time for that deed, since the legal work frequently takes longer than the application itself and the permission cannot be issued until the deed is completed.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.