Transport contributions and the trip based calculation

7 min readBy PlanScope Editorial Team

Highway authorities build sustainable transport contributions from trip rates and mode share. Understanding how the figure is assembled is the only way to test whether it meets the statutory tests.

A transport contribution calculation in a section 106 agreement usually works forward from one number: the net new vehicle trips the development is predicted to generate. The highway authority multiplies that by a cost per trip, or applies a per dwelling rate from a supplementary planning document, and asks for the result. Both ends of that calculation rest on assumptions, and both are open to challenge. The statutory tests in regulation 122 of the Community Infrastructure Levy Regulations 2010 are the frame for any argument, because an obligation that fails them cannot lawfully be a reason for granting permission.

How the number is built

There are two common methods, and the difference matters when you come to challenge the figure.

The first is a tariff. The authority adopts a supplementary planning document setting a rate per dwelling or per 100 m² of floorspace, derived from an evidence base of planned transport schemes and the development expected to come forward over the plan period. The rate is applied mechanically.

The second is a scheme specific calculation. The transport assessment predicts trip generation, the authority converts the net new trips into a share of the cost of identified infrastructure, and the contribution follows. This method produces a bespoke number and leaves far more room for argument about every input.

A third variant appears where the contribution funds a specific measure: a bus service subsidy for a defined period, a pedestrian crossing, a cycle route, a package of controlled parking zone amendments. These are the easiest to test, because the measure either serves the development or it does not.

Work out which method you are facing before responding. Arguing about trip rates against a properly adopted tariff is wasted effort, and arguing about the plan period evidence base against a scheme specific calculation misses the point.

The trip rate data and where it bends

Most trip generation in England comes from the TRICS database, which holds surveyed trip rates for a wide range of land uses. The method is to select comparable surveyed sites, filter them, and take an average rate per dwelling or per unit of floorspace.

The filtering is where the number moves. Four choices do most of the work:

  1. Geographic filter. Including surveys from edge of town sites in low density areas raises car driver rates for an urban scheme.
  2. Parking provision at the surveyed sites. Sites with two spaces per dwelling generate more car trips than sites with half a space, so the comparator set has to match the proposal.
  3. Survey date. Older surveys predate changes in working patterns and online delivery, and very recent surveys may sit in an unrepresentative period.
  4. Development size band. A rate derived from 200 unit estates applied to a 25 unit infill site overstates the trips.

Ask for the TRICS output in full, including the site list and the filters applied. A rate presented as a single figure without the selection criteria is not evidence, and highway officers will normally provide the full output when asked.

Mode share, and the assumption that does the work

Total person trips get split between car driver, car passenger, bus, rail, cycle and walk. That split is usually taken from census travel to work data for the relevant output area or ward, sometimes adjusted for the proposed parking ratio or for measures in the travel plan.

Two points are worth pressing. Census travel to work data covers commuting, which is a minority of all trips, and applying a commuting mode share to total trip generation can distort the car driver figure in either direction. And where the authority applies a mode shift target from the travel plan to reduce the trips, it cannot then charge a contribution calculated on the unreduced trips. Pick one.

The arithmetic should be shown. A contribution request that states a cost per trip and a trip total without the mode share table behind it is not something you can respond to, and asking for it is reasonable rather than obstructive.

Testing the request against regulation 122

Regulation 122 allows an obligation to be a reason for granting permission only where it is necessary to make the development acceptable in planning terms, directly related to the development, and fairly and reasonably related in scale and kind to the development. Those three tests are the whole of the legal argument.

Necessity means the development would otherwise be unacceptable. If the transport assessment concludes there is no severe residual cumulative impact on the highway network, it becomes hard to argue that a contribution is necessary to make the scheme acceptable.

Direct relationship means the money must address an effect of this development. A contribution to a scheme on the other side of the district, which the development's traffic will never reach, does not meet it. Ask what the money will be spent on, where, and by when.

Scale and kind is proportionality. A 15 dwelling scheme asked to fund a quarter of a junction improvement serving 2,000 homes fails on scale. The authority's own evidence base usually contains the apportionment, so ask for it.

The pooling restriction that once limited contributions to five obligations per project was removed in September 2019, so the old argument about the sixth contribution has gone. In its place, authorities must publish an annual infrastructure funding statement showing what has been collected and spent, which is a useful document when testing whether earlier contributions towards the same scheme were ever used.

Monitoring fees and what they should cover

Travel plan monitoring fees are now standard. The Planning Practice Guidance on planning obligations recognises that an authority may seek a fee to cover the cost of monitoring and reporting, provided it is proportionate to the monitoring actually required.

Proportionate means costed. A monitoring fee should reflect the number of surveys, the officer time to review them and the duration of the obligation, typically five years for a residential travel plan. A flat fee applied to every scheme regardless of size is vulnerable, and so is a fee that duplicates the cost of the surveys the developer is already required to commission.

Ask for the breakdown. Where the authority cannot produce one, the fee is difficult to defend against the scale and kind test.

Where the works themselves sit in the highway, the contribution route is often the wrong one altogether, and the boundary between the two mechanisms is set out in section 278 agreements and where a section 106 starts.

Negotiating the figure down

Four lines of argument work in practice. Correct the trip rate inputs, with your own TRICS run and the selection criteria stated. Correct the mode share, with local data rather than district averages where the site is genuinely well served. Remove double counting between the travel plan measures and the contribution. And test the apportionment against the authority's own evidence base.

Viability is the fifth route, and a different one. Where the scheme cannot carry the full package of obligations, a viability assessment prepared in line with national guidance is the mechanism, and the authority will expect to see affordable housing and transport weighed against each other rather than transport alone. On a phased scheme, the timing of payments is often worth more than the headline reduction, and the approach in phasing a permission to spread the levy liability applies to obligations as well as to the levy.

Put the challenge in writing, early, to the highway officer and the case officer together. A reduction agreed before the committee report is written is worth several times the same argument made at appeal.

You can draft the transport and viability documents that support an obligations negotiation on PlanScope by entering the postcode and answering the guided questions, then have the transport modelling checked by a qualified transport planner.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What are the statutory tests for a planning obligation?

Regulation 122 of the Community Infrastructure Levy Regulations 2010 allows an obligation to be a reason for granting permission only where it is necessary to make the development acceptable in planning terms, directly related to the development, and fairly and reasonably related in scale and kind to it. All three must be met, and an inspector will delete an obligation that fails any of them.

Can I challenge the trip rates used in a contribution calculation?

Yes. Ask for the full TRICS output showing the sites selected, the filters applied, the survey dates and the parking provision at each surveyed site. Rates drawn from suburban sites with generous parking overstate car trips for an urban scheme, and rates from large estates overstate trips for a small infill development.

Is a travel plan monitoring fee lawful?

Authorities commonly seek one and national guidance accepts it, provided the fee is proportionate to the monitoring actually needed. Ask for a breakdown showing the number of surveys, officer time and the duration of the obligation. A flat fee applied regardless of scheme size, or one duplicating surveys the developer already funds, is hard to defend.

Does the pooling restriction on contributions still apply?

No. The restriction limiting contributions to five obligations towards a single infrastructure project was removed in September 2019. Authorities must instead publish an annual infrastructure funding statement setting out what has been collected and what it has been spent on, which is useful evidence when testing whether earlier contributions were ever applied.

What is the difference between a section 106 contribution and a section 278 agreement?

A section 106 obligation is a payment or restriction secured through the planning permission. A section 278 agreement under the Highways Act 1980 is the mechanism by which a developer carries out or funds works within the public highway, with the highway authority's approval. Works in the highway normally belong in the section 278, not in a contribution.

Sources and further reading

section 106transport contributiontrip ratestravel planplanning obligations

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Viability, Obligations and Commercial

View all →
Viability, Obligations and Commercial7 min read

Marketing evidence before a commuted sum is accepted

A commuted sum argument usually fails on the terms offered rather than on a lack of interest. Offer the units at the transfer value in your own appraisal, and record everything.

Read article →
Viability, Obligations and Commercial7 min read

Modifying a section 106 agreement that has become unviable

Section 106A is not a viability test. It asks whether the obligation still serves a useful purpose, and whether a modified version would serve it equally well.

Read article →
Viability, Obligations and Commercial7 min read

Agent of change obligations for a music or sports venue

Building homes beside an established venue means funding the mitigation. The split between conditions and obligations, noise deeds and their limits, and the drafting.

Read article →
Viability, Obligations and Commercial7 min read

Build cost indices and the date of the cost plan

Cost indices and tender price indices measure different things. How the base date, the index and the valuation date interact, and how to state the basis so it holds up.

Read article →
Viability, Obligations and Commercial6 min read

Professional fees and contingency in a development appraisal

Fees and contingency look like small lines in an appraisal and move the residual land value a long way. Both are tested, and both are defended with scope documents rather than convention.

Read article →
Viability, Obligations and Commercial6 min read

Affordable housing on a site with a demolition credit

Twelve houses replacing four is twelve gross and eight net. Whether the threshold and percentage are read gross or net can be the whole margin, and the levy applies a separate floorspace test with its own timing trap.

Read article →