Modifying a section 106 agreement that has become unviable
Section 106A is not a viability test. It asks whether the obligation still serves a useful purpose, and whether a modified version would serve it equally well.
A planning obligation can be changed in two ways. By agreement with the local planning authority at any time, using a deed of variation, or by application to the authority under section 106A of the Town and Country Planning Act 1990 once five years have passed since the obligation was entered into. The second route carries a right of appeal under section 106B; the first does not.
Most section 106 modification work goes down the first route, because it is quicker and because the statutory test is narrow. Understanding how narrow it is changes how you negotiate.
The two routes compared
| Feature | Deed of variation | Section 106A application |
|---|---|---|
| Timing | Any time | After the relevant period, normally five years |
| Needs authority's consent | Yes, it is a negotiated deed | No, it is a determination |
| Test applied | Whatever the authority will agree | Useful purpose test in section 106A(6) |
| Can add obligations | Yes | No |
| Appeal if refused | None | Section 106B appeal to the Secretary of State |
| Typical use | Live schemes, phasing, trigger changes | Legacy obligations on older permissions |
The statutory route only reaches obligations entered into more than five years earlier, unless a different period has been prescribed. For a scheme that stalled eighteen months after the deed was signed, the statutory route is simply not available, and the negotiation is the only option.
The useful purpose test
Section 106A(6) gives the authority three possible determinations on an application. That the obligation shall continue to have effect without modification. That it no longer serves a useful purpose and shall be discharged. Or that it continues to serve a useful purpose, but would serve that purpose equally well if modified in the way applied for, in which case it is modified accordingly.
Read that carefully, because it is not a viability test. An affordable housing obligation that has become expensive still serves a useful purpose, so the first limb is satisfied and the authority can leave it in place. The applicant's route is the third limb, which requires showing that the modified obligation would serve the same purpose equally well.
That is why successful applications tend to propose a different delivery of the same benefit rather than less of it. A change of tenure mix that keeps the same unit count. A commuted sum calculated to deliver an equivalent number of homes elsewhere in the authority's area. A revised trigger that still secures the infrastructure before occupation.
The viability reviews that were briefly available under sections 106BA to 106BC were introduced in 2013 and repealed by the Housing and Planning Act 2016. Anyone working from an older textbook should check that, because the repeal removed the only statutory mechanism that treated viability as the test.
Grounds that work and grounds that do not
Authorities and inspectors respond to changes in circumstance that are external and evidenced, rather than to a developer's changed appetite.
Arguments that tend to be taken seriously:
- The obligation requires something that has since been provided by another scheme or by the authority itself, so the purpose is already met.
- The trigger is impossible to meet, for example a highway work on land now outside anyone's control.
- The infrastructure the contribution was pooled towards has been abandoned or superseded in the current plan or infrastructure funding statement.
- A registered provider cannot be found for the units as specified and the marketing evidence supports that, a position often reached on the schemes covered in our note on renegotiating obligations on a stalled scheme.
- The obligation conflicts with a later statutory requirement, such as the biodiversity gain condition or current building standards.
Arguments that rarely succeed on their own: build cost inflation, a change in sales values, a change of ownership, or the fact that the scheme would be viable without the obligation. Those matter in negotiation, and they belong in a deed of variation discussion rather than a statutory application.
The evidence an authority expects
For either route, assume the authority will want an open book case tested by its own adviser, and assume it will recover the cost of that advice.
An appraisal prepared in line with the Planning Practice Guidance viability chapter and the RICS guidance on financial viability in planning is the starting point. Expect the authority to interrogate the benchmark land value, the developer return, the build cost source and the treatment of abnormals. A Viability Assessment that sets out inputs transparently, with sensitivity analysis, survives that process better than one that presents a single answer.
Beyond the appraisal, prepare:
- The executed deed and every variation already made, with the obligation clauses identified by number.
- The planning history, including any section 73 permissions and whether they carried the obligation forward.
- Evidence of the external change relied on, dated and sourced.
- Title information showing every party against whom the obligation is enforceable, including mortgagees.
- The authority's current infrastructure funding statement, to show whether pooled contributions have been spent or allocated.
Where affordable housing is the obligation in question, the position usually turns on the cascade in the deed and whether it has been exhausted, which is covered in our note on the affordable housing cascade mechanism.
Appealing under section 106B
If the authority refuses a section 106A application, or fails to determine it within the prescribed period, an appeal lies to the Secretary of State under section 106B. The procedure sits in the Town and Country Planning (Modification and Discharge of Planning Obligations) Regulations 1992, which also prescribe the form of the application and the notice requirements, so read them before submitting rather than after.
The inspector applies the same useful purpose test. An appeal that argues viability without addressing whether the modified obligation would serve the original purpose equally well is answering a question the inspector has not been asked.
Appeal decisions in this area are indicative of how inspectors have approached the test rather than binding precedent, and they are worth reading for the reasoning on what counts as the same purpose.
Timescales and costs
An illustrative sequence for a negotiated variation on a stalled scheme. Initial approach and heads of terms, four to six weeks. Appraisal preparation, three to four weeks. The authority's independent review, four to eight weeks depending on procurement. Member or delegated sign-off, two to six weeks. Engrossment and completion, two to four weeks. That is a four to six month programme in a case where everyone cooperates.
Costs fall into four buckets: your own planning and viability advice, the authority's legal costs and the fee for its independent appraisal review, your own legal costs on the deed, and the cost of any new survey work the modification triggers. All four are normally met by the applicant under an undertaking given at the outset.
For a section 106A application the arithmetic is different, because there is no fee for the application itself but the appeal route adds time. Twelve months from first approach to a decided appeal is realistic.
Drafting the variation
Two drafting habits prevent the next problem.
First, vary the specific clause rather than restating the whole deed, and keep a consolidated version alongside for the file. Successive deeds that each restate the obligation in slightly different words are how a trigger becomes unenforceable.
Second, settle who is bound. An obligation runs with the land under section 106(3), so every current owner and any mortgagee with a charge needs to be a party to the variation. Missing a mortgagee is the commonest cause of a deed that has to be redone.
Also check the interaction with the permission itself. A section 73 application creates a new permission, and unless the deed is drafted to attach to subsequent permissions, a fresh obligation or a deed of variation will be needed to tie it in. The way phasing and trigger drafting interacts with levy liability is set out in our note on phasing a permission to spread the levy liability.
Start with the clause and the five year date. Those two facts decide which route is open to you, and everything else is negotiation.
If you need the appraisal and supporting statements drafted before that negotiation starts, the Viability Assessment and the other 66 report types are set out by category.
This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required.
Frequently asked questions
When can I apply to modify a section 106 obligation?
Section 106A of the Town and Country Planning Act 1990 allows an application once the relevant period has expired, normally five years from the date the obligation was entered into. Before that, the only route is a negotiated deed of variation agreed with the local planning authority, which can be done at any time but cannot be appealed if refused.
Is viability a ground for modifying a section 106?
Not directly. Section 106A(6) asks whether the obligation still serves a useful purpose and, if it does, whether a modified obligation would serve that purpose equally well. An expensive obligation still serves its purpose, so viability evidence supports a negotiation rather than a statutory application. Sections 106BA to 106BC were repealed by the Housing and Planning Act 2016.
Can a section 106A application add new obligations?
No. The statutory route only modifies or discharges what is already in the deed. Adding obligations, changing parties or restructuring the agreement requires a deed of variation agreed with the authority, with every current owner and any mortgagee holding a charge joined as a party.
What is the appeal route if the authority refuses?
Section 106B gives a right of appeal to the Secretary of State against a refusal of a section 106A application, or against a failure to determine within the prescribed period. The procedure is in the Modification and Discharge of Planning Obligations Regulations 1992. The inspector applies the same useful purpose test as the authority.
How long does a negotiated variation take?
Allow four to six months where everyone cooperates: heads of terms, appraisal preparation, the authority's independent review, member or delegated sign-off, then engrossment. The applicant normally meets the authority's legal costs and the fee for its appraisal review under an undertaking given at the outset, as well as its own advisers' costs.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.