Phasing a permission to spread the levy liability
A phasing condition on the decision notice turns one levy bill into several, each payable when its phase starts. Miss the condition and the whole site pays on day one.
A phased planning permission cil position is worth getting right at the decision stage, because each phase of a phased permission is treated as a separate chargeable development under the Community Infrastructure Levy Regulations 2010. That means a separate liability, separate notices, a separate instalment schedule and a separate set of reliefs. Spread the phases properly and the levy follows the build programme instead of landing in one lump before the first plot is sold.
Get the drafting wrong and the whole site becomes one chargeable development, payable on commencement of the first spadeful.
Why phasing changes the levy position
Levy liability crystallises on commencement of the chargeable development. On an unphased permission for 120 units, that is the moment the first material operation begins anywhere on the site, and the full charge becomes payable according to the authority's instalment policy, which is typically structured over a period measured in months rather than years.
On a phased permission, commencement of phase one triggers only the phase one liability. Phase four's charge waits until phase four starts, which on a long build-out can be several years later. The cash flow difference is the single largest levy lever available to a developer, and it costs nothing but careful condition drafting.
Indexation cuts the other way, since the levy figure is adjusted using the published index, so a later phase is not a frozen figure. The regulations set out how the calculation works, and the charging authority's current schedule and index figure should be checked rather than assumed.
What makes a permission phased for levy purposes
This is the part people get wrong. A phasing plan agreed later, through a discharge of conditions application, does not retrospectively make a permission phased.
The regulations treat a permission as phased where it is an outline permission permitting development to be implemented in phases, or a full permission granted subject to a condition providing for the development to be carried out in phases. The condition has to exist on the permission itself, and it has to define the phases well enough that each one can be identified on the ground.
So the practical requirements are:
- A condition on the decision notice providing for phased implementation.
- A phasing plan referenced by that condition, with phase boundaries drawn, not described.
- Enough clarity that the collecting authority can calculate a chargeable amount for each phase from the approved drawings.
- Consistency with the obligations in any section 106 agreement, so that triggers match phases.
Ask for the condition in your covering letter at submission, and check the draft decision notice before it is issued. A levy saving of this size does not deserve to be lost to a missing condition.
Each phase as a separate chargeable development
Once the permission is phased, treat each phase as though it were its own permission for levy administration.
| Step | What is needed per phase |
|---|---|
| Liability notice | Issued by the collecting authority for each phase |
| Assumption of liability | Submitted before commencement of that phase |
| Relief or exemption claim | Claimed and approved before commencement of that phase |
| Commencement notice | Submitted before the first material operation in that phase |
| Demand notice | Issued after commencement, setting the payment dates |
The sequencing is unforgiving and the deadlines are short. Nothing here is discretionary.
Commencement notices for each phase
The commencement notice is where money is lost. Submit it before the first material operation on that phase, and keep the proof of service.
Fail to submit one and the consequences are automatic: the right to pay by instalments falls away, so the whole phase charge becomes payable immediately, and a surcharge can be imposed. Appeals against surcharges exist but they turn on narrow grounds, and "the groundworker started early" is not one of them.
Two practical traps. Site clearance, demolition and service diversions can constitute a material operation, so a contractor mobilising on phase two while phase one is still being built can start phase two without anyone intending it. And a section 73 permission creates a new chargeable development, which needs its own notices even where the scheme is substantially unchanged.
Appoint one person to own the notices for the whole site. Not the contractor.
Interaction with the instalment policy
Charging authorities publish an instalment policy, and it applies to each chargeable development. A phased permission therefore gets a separate instalment schedule per phase, which is the compounding benefit of phasing: smaller sums, each spread.
The policy in force is the one published at the time, and authorities revise them, so read the current version rather than the one in a feasibility report from two years ago. Where the policy sets a minimum threshold below which instalments are not available, a small phase can fall below it and become payable in a single sum, which is an argument for not slicing phases too thinly.
Relief claims deserve particular care. Self-build exemption, social housing relief and charitable relief are claimed per chargeable development, must be granted before commencement, and carry clawback periods. On a phased scheme with affordable housing distributed across phases, the Affordable Housing Statement and the relief claims have to describe the same units in the same places.
Drafting the phasing plan
Draw the phases to the build programme and the infrastructure sequence, not to a tidy grid. Each phase should be capable of standing alone: access, drainage outfall, open space and parking within it or secured by an earlier phase.
Watch the boundaries. Phase lines running through a building, a road, an attenuation basin or a shared parking court create arguments about which phase has started. Keep the strategic infrastructure in phase one or in a defined infrastructure phase, and say in the agreement which phase delivers which obligation.
Where viability is finely balanced, the phasing also shapes the review mechanism, and the interaction with abnormal costs in the appraisal and the wider Viability Assessment needs to be consistent with the phase boundaries you have drawn.
Mistakes that collapse the phasing
The recurring ones, in rough order of frequency:
- No phasing condition on the permission, so the site is a single chargeable development however many phases the drawings show.
- Phases defined in a document the condition does not reference.
- A commencement notice submitted for phase one only, with later phases started silently.
- Relief claimed after commencement, which cannot be rescued.
- Section 106 triggers tied to unit numbers while levy phases are tied to land parcels, so nobody can say which obligation bites when.
- A section 73 variation that resets the chargeable development without new notices.
Each of those is an administrative failure rather than a planning judgement, which is what makes them irritating. They are also entirely avoidable with a one-page tracker showing, per phase, the liability notice date, the assumption of liability, the relief position, the commencement notice date and the payment dates.
Where the levy is being collected, some of it flows to the parish or to the neighbourhood proportion, and understanding how the neighbourhood share is spent helps when you are negotiating what else the scheme is asked to fund.
PlanScope can draft the planning statement, affordable housing statement and viability documents that sit around this, structured to national policy, with scheme-specific figures flagged as to be confirmed until your appraisal supplies them. Enter your postcode on PlanScope to see which reports a phased scheme is likely to need.
This is general guidance, not legal advice. The levy regulations have been amended several times and charging schedules are indexed annually, so check the current regulations and your charging authority's published schedule, and take specialist advice before relying on a phasing strategy.
PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
What makes a planning permission phased for levy purposes?
Either an outline permission that permits development to be implemented in phases, or a full permission granted subject to a condition providing for the development to be carried out in phases. The condition must be on the permission itself and must define the phases clearly enough to identify them, so a phasing plan agreed later by condition discharge does not qualify.
Does each phase need its own commencement notice?
Yes. Each phase of a phased permission is a separate chargeable development, so it needs its own assumption of liability, any relief claim granted before commencement, and a commencement notice served before the first material operation in that phase. Missing a notice removes the right to pay by instalments and can attract a surcharge.
Can relief be claimed after a phase has started?
No. Self-build exemption, social housing relief and charitable relief must be claimed and granted before commencement of the chargeable development they relate to. On a phased scheme that means before commencement of each relevant phase, and a claim made after the first material operation cannot be rescued.
Does phasing reduce the total levy payable?
Not directly. Phasing changes when each amount falls due rather than the rate charged, and later phases are adjusted by the published index, so the cash sum can rise. The benefit is cash flow: the charge follows the build programme instead of becoming payable in full when the first phase starts.
Does a section 73 permission affect the levy position?
Yes. A section 73 permission creates a new chargeable development, so fresh notices are needed even where the scheme is substantially unchanged. Developers regularly vary a permission late in the programme and overlook the notices, which is an avoidable way to lose instalment rights on a phase already under way.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.