Viability evidence for a Class MA conversion
Why viability is absent from the Class MA prescribed matters, where it still shapes the scheme, how conversion costs and existing use value are evidenced, and when the full application fallback is worth preparing.
Prior approval under Class MA cannot be refused because the numbers do not work, because viability is not one of the matters the General Permitted Development Order allows the authority to consider. That sounds like good news for a conversion from commercial to residential, and in one sense it is. The trap is everything sitting outside the prior approval: the levy, the space standard, the natural light requirement, the cost of a building designed for offices, and the full application you may need as a fallback if the scheme does not fit the class. Viability work is still worth doing on a Class MA scheme. It just is not an argument you can run with the council.
What prior approval can and cannot consider
Class MA permits a change of use from commercial, business and service use in Class E to dwellinghouses in Class C3, subject to conditions and limitations in the Order and to prior approval on specified matters.
The prescribed matters are narrower than a full application. They cover transport impacts, contamination risk, flood risk, noise from commercial premises affecting the intended occupiers, the provision of adequate natural light in all habitable rooms, and in a conservation area the impact of losing a ground floor commercial use. Fire safety considerations apply where relevant.
Viability is absent from that list, and so is affordable housing. The authority cannot require a contribution through a planning obligation on a prior approval, which is the commercial attraction of the route. It also cannot refuse because the scheme is marginal, which is why no viability appraisal needs to be submitted.
Eligibility is where schemes fail. The building must have been in Class E use for a continuous period before the application, the class is unavailable on certain designated and safeguarded land and on listed buildings, and an Article 4 direction can remove the right entirely. The limitations have been amended more than once since the class was introduced in 2021, including changes in March 2024, so read the current text of the Order rather than any summary.
Where viability still matters on a conversion
Four places, none of which the council will discuss with you.
- The decision whether to use Class MA at all, against a full application that could deliver more units or a better mix.
- The levy liability, which is a real cost and is calculated independently of the prior approval.
- The cost of compliance with the space standard and the natural light requirement, which drives the unit count.
- The fallback case, if you later need a full application because the scheme has outgrown the class.
That third item is the one that reshapes schemes. Since April 2021 homes created under permitted development have had to meet the Nationally Described Space Standard, and every habitable room needs adequate natural light. In a deep plan office floor those two requirements together can cut the achievable unit count substantially, because the centre of the floorplate cannot take bedrooms.
Construction cost evidence for a change of use
Conversion costs are harder to estimate than new build and are routinely underestimated. The items that move the figure:
- Structural alterations for new openings, risers and stair cores, and any floor strengthening for residential loadings.
- New services throughout, since office mechanical and electrical installations rarely suit flats.
- Acoustic separation between units to meet Approved Document E, which in a concrete frame with raised floors is intrusive work.
- Thermal upgrade of the envelope and glazing to meet the energy requirements applying to a material change of use.
- Fire compartmentation, protected escape routes and, in taller buildings, the current requirements of Approved Document B.
- Window replacement where the existing openings cannot deliver adequate natural light or ventilation.
Use published cost data for conversions rather than new build rates, state the source and the date, and carry a contingency that reflects the age of the building. A 1970s frame with asbestos containing materials is a different proposition from a 2005 office, and an intrusive survey before purchase costs far less than a variation during construction.
Existing use value of a commercial building
Where viability does become a formal exercise, on a full application rather than a prior approval, the benchmark land value is derived from existing use value plus a premium, as set out in national viability guidance.
For a commercial building the existing use value is the value of the building in its current lawful use, taking account of its condition, lettability and the market for that use locally. A vacant 1970s office in a secondary location has a low existing use value, which strengthens a viability case. A let office with income has a high one, which weakens it, and buying at a price that assumes residential value does not change the benchmark. Guidance is clear that the price paid is not the test.
That distinction matters because the Class MA route avoids the question entirely, while the full application route puts it at the centre of the case, and a viability assessment on a conversion stands or falls on how the existing use value was evidenced.
Levy liability on a conversion
The levy is payable on a prior approval scheme, but most conversions pay little or nothing because of the deduction for existing buildings. The chargeable amount is reduced by the floorspace of existing buildings in lawful use, where the building has been in lawful use for a continuous period of at least six months within the three years before the day permission first permits the development.
Two practical consequences follow. Keep evidence of occupation, including leases, rates records and utility accounts, because the deduction depends on proving lawful use rather than asserting it. And be careful with long void periods, since a building empty for years may fail the in use test and the whole floorspace becomes chargeable.
Where the scheme is large enough to be phased, the timing of liability can be spread, and the mechanics are set out in our note on phasing a permission to spread the levy liability.
Affordable housing and the prior approval route
No affordable housing can be required on a Class MA prior approval. Some authorities dislike that and have responded with Article 4 directions removing the right in defined areas, usually town centres and employment locations, so the first check on any site is whether a direction applies.
On a full application the position reverses, and the development plan's affordable housing policy applies in the normal way, with the tenure split and any cascade arrangement negotiated. How those cascades operate when a provider cannot be found is covered in our note on the affordable housing cascade mechanism.
Preparing for a full application fallback
Run the two routes in parallel on anything marginal. Establish eligibility for Class MA first, since it is binary and quick to check. Then model the unit count achievable within the space standard and natural light requirement, and compare it with what a full application could deliver.
Where the full application wins, the Class MA fallback is still useful, because a realistic fallback position is a material consideration in the determination of the full application. Say what the fallback is, show that it is deliverable, and the authority has to weigh it.
To see which documents each route needs, enter your postcode on PlanScope and answer the guided questions on existing use and floorspace.
PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. This is general guidance, not legal advice; check the current text of the Order and the position with your local planning authority before relying on it.
Frequently asked questions
Can a council refuse Class MA prior approval on viability grounds?
No. Viability is not one of the matters the General Permitted Development Order allows the authority to consider, so no viability appraisal is required and the scheme cannot be refused for being marginal. The authority also cannot require affordable housing or a planning obligation on a prior approval.
What can the council consider on a Class MA application?
The prescribed matters only: transport impacts, contamination risk, flood risk, noise from commercial premises affecting intended occupiers, the provision of adequate natural light in all habitable rooms, fire safety where relevant, and in a conservation area the impact of losing a ground floor commercial use.
Do permitted development conversions have to meet space standards?
Yes. Since April 2021 homes created under permitted development must meet the Nationally Described Space Standard, and every habitable room needs adequate natural light. On a deep plan office floor those two requirements together often cut the achievable unit count, because the centre of the floorplate cannot take bedrooms.
Is the community infrastructure levy payable on a Class MA conversion?
It is chargeable, but most conversions pay little because the floorspace of existing buildings in lawful use is deducted. The building must have been in lawful use for a continuous period of at least six months within the three years before permission first permits the development, so keep leases and rates records as evidence.
Does the price I paid for the building set the benchmark land value?
No. On a full application, benchmark land value is derived from existing use value plus a premium, and national viability guidance is clear that the price paid is not the test. A vacant secondary office has a low existing use value, which strengthens a case; a let building with income has a high one.
Sources and further reading